MACT – Subpart ZZZZ (4Z) Reciprocating Internal Combustion Engines (R.I.C.E.) EPA Enforcement Workshop . Joe Foutz November 15, 2012 NC DAQ Charlotte, NC Mooresville Regional Office. MACT – Subpart ZZZZ (4Z) .

metta
Download Presentation

Joe Foutz November 15, 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MACT – Subpart ZZZZ (4Z)Reciprocating Internal Combustion Engines (R.I.C.E.)EPA Enforcement Workshop Joe Foutz November 15, 2012 NC DAQ Charlotte, NC Mooresville Regional Office

  2. MACT – Subpart ZZZZ (4Z) If you have a ….. Stationary Reciprocating Internal Combustion Engine (R.I.C.E.) You’re Subject !!

  3. MACT – Subpart ZZZZ (4Z) Compliance Date Existing CI at Area Source May 3, 2013 Existing SI at Area Source October 19, 2013

  4. NC – Engine Population (with an Air Permit)

  5. MRO – Engine Population TOTAL Engines 336 CI Engines at Area Source w/ Emission Limit 42 CI Emergency at Area Source 86 SI Emergency at Area Source 24 New Emergency at Area Source 73 New Non-Emerg. at Area Source 28 Emergency Major Source 47 Assorted Others 36

  6. Emission Limits Area Source – Non Emergency - Existing CI (Table 2d) - 300 < HP ≤ 500 : CO conc. of 49 ppmvd or 70% CO reduction - 500 < HP : CO conc. of 23 ppmvd or 70% CO reduction - Existing SI (Table 2d) - 500 < 4SRB : formald. conc. of 2.7 ppmvd or 76% formald. reduction - 500 < 4SLB : CO conc. of 47 ppmvd or 93 % CO reduction *stack test conducted at any load (40 CFR 63.6620(i)). However, pressure drop cannot change by more than 2 inches of water at 100 % load from the pressure drop recorded at initial performance testing (Table 2b) Table 3 for Subsequent Stack Testing

  7. Emission Limits Major Source – Non Emergency - 500 < Existing or New 4SRB (Table 1a) - 500 < New 2SLB, CI (Table 2a) - 250 ≤ New 4SLB (Table 2a) - 100 ≤ Existing CI (Table 2c) - 100 ≤ Existing 2SLB, 4SLB, 4SRB ≤ 500 HP (Table 2c) - 100 ≤ Existing Landfill Gas ≤ 500 (Table 2c) *Stack test at 100 % of load +/- 10% for engines greater than 500 HP (40 CFR 63.6610(d)(5)) Table 3 for Subsequent Stack Testing

  8. Stack Test Process • Submit Stack Test Protocol to NC DAQ 45 days prior to test Stationary Source Compliance Branch (SSCB) will review and approve • Notify Regional Office 15 days prior to test Difficult for Peak Shavers • Regional Office may observe the stack test • Submit Stack Test Report/Results within 30 days to SSCB via Regional Office.

  9. Non-Permitted Facilities • Must Comply with MACT 4Z • No Compliance Inspections • Complaint Oriented Inspections Only

  10. Questions Contact : Joe Foutz 704-235-2225 Joe.Foutz@ncdenr.gov Or Your Regional Office Asheville RO Mooresville RO Raleigh RO 828.296.4500 704.663.1699 919.791.4200 Fayetteville RO Washington RO Wilmington RO 910.433.3300 252.946.6481 910.796.7215 Winston-Salem RO 336.771.5000