340 likes | 1.14k Views
Une division d'Hydro-Québec. TransÉnergie. Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective. Marc Foata and Van Nhi Nguyen. Background. Early 1980s, increasing number of catastrophic failures on our 735 kV system Two major blackouts Safety threats to the workers
E N D
Une division d'Hydro-Québec TransÉnergie Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective Marc Foata and Van Nhi Nguyen
Background • Early 1980s, increasing number of catastrophic failures on our 735 kV system • Two major blackouts • Safety threats to the workers • Environment concerns due to oil spills and fire PL
Background • 1984- 1987: Study works of HQ - ABB joint teams many measures implemented; among these measures: • Welded cover instead of bolted type • Physical separation of radiators and conservator from main tank and with devices to prevent oil spilling in case of pipe rupture • Modifications to tank reinforcement beams • Fire extinguishing walls and oil retention basin AND most importantly higher test levels for more reliable performances and larger margin in insulation PL
Background • 1987-1992 Major R&D project on arc-induced explosion and tank ruptures • 1992 New requirement in Hydro-Québec specifications, no minimum level is enforced but question must be adressed during the design review • 1992-1993 Joint effort with ABB for a more resistant tank design • 1992-2006 All our transformer suppliers have demonstrated adequate ability to take into account this new requirementin their analysis PL
Mitigation approaches • Protection: Improve fault interruption delay so that very low energy is released • Insulation: Correct all design weaknesses so that no fault can occur • Containment: Make a pressure resistant tank that can safely withstand or evacuate all energy levels PL
Results • Protection: 3.5 cycles average fault interruption time, reduced to less than 3 cycles • Insulation: Several weaknesses have been identified and corrected. Yet the possibility of a major fault could not be totally discarded • Containment: Very little knowledge on the subject, a R&D project is initiated PL
Failure statistics 735 kV (25 years) • 175 failures that resulted in 111 high energy arcs causing 44 tank ruptures and finally 18 fires PL
R&D Simulation tools • Theoretical part based on analytical and numerical models identifying fundamental parameters. Derive a straightforward method for calculating the static pressure. PL
R&D Arc simulation setup • Experimental part involving simulation of the dynamic load factor F to be applied to the static pressure to take into account the dynamic effects. PL
R&D Results Pressure Displacement PL
R&D Results & Conclusions • Arc induced explosions can be simulated but sophisticated tools are required • Deformation, not pressure, should be used to determine tank rupture. • Dynamic factor have been proposed to extrapolate static calculations • Testing by high pressure gas injection is possible • New tank resistance specification has been formulated PL
New specifications - Philosophy • Priority is given to the protection of the workers • Worst energy levels may not always be containable by the tank • First rupture point must be the cover • Required calculation tools must be accessible to transformer designers • Must take into account the highly dynamic phenomena involved • Must be easily verified PL
New specifications - Objectives • Stimulate new tank designs • Exchange technical information with manufacturers • Aiming in long term to see that new tank designs meet arc energy requirements PL
New specifications - Formula • Ps – Calculated tank pressure withstand • F – Dynamic (time & location) amplification • E – Fault energy level to withstand • K – Arc energy conversion factor • C – Tank expansion coefficient PL
New specifications – Dynamic factor • Time related dynamic factor (pressure and deformation) • Proximity related dynamic factor • Takes into account tank volume PL
Manufacturers' response • All transformer suppliers since 1992 have shown adequate tank withstand analysis • One supplier has proposed an improved tank design (double arc containment capability to 20 MJ) • Containement of the highest levels of arc energy require complicated pressure venting system with numerous rupture disk all over the tank or double-walled tanks PL
Where do we go from here ? • Present design can contain up to 10 MJ for the largest tanks (735 kV) • More resistant tank design can be achieved • Need to implement specifications with minimum energy requirement to meet . Utilities need to agree on reasonable levels • Testing by high pressure gas injection is feasible and more appealing than real arc testing PL