1 / 21

Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective

Une division d'Hydro-Québec. TransÉnergie. Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective. Marc Foata and Van Nhi Nguyen. Background. Early 1980s, increasing number of catastrophic failures on our 735 kV system Two major blackouts Safety threats to the workers

michaela
Download Presentation

Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Une division d'Hydro-Québec TransÉnergie Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective Marc Foata and Van Nhi Nguyen

  2. Background • Early 1980s, increasing number of catastrophic failures on our 735 kV system • Two major blackouts • Safety threats to the workers • Environment concerns due to oil spills and fire PL

  3. Background • 1984- 1987: Study works of HQ - ABB joint teams many measures implemented; among these measures: • Welded cover instead of bolted type • Physical separation of radiators and conservator from main tank and with devices to prevent oil spilling in case of pipe rupture • Modifications to tank reinforcement beams • Fire extinguishing walls and oil retention basin AND most importantly higher test levels for more reliable performances and larger margin in insulation PL

  4. Background • 1987-1992 Major R&D project on arc-induced explosion and tank ruptures • 1992 New requirement in Hydro-Québec specifications, no minimum level is enforced but question must be adressed during the design review • 1992-1993 Joint effort with ABB for a more resistant tank design • 1992-2006 All our transformer suppliers have demonstrated adequate ability to take into account this new requirementin their analysis PL

  5. Mitigation approaches • Protection: Improve fault interruption delay so that very low energy is released • Insulation: Correct all design weaknesses so that no fault can occur • Containment: Make a pressure resistant tank that can safely withstand or evacuate all energy levels PL

  6. Results • Protection: 3.5 cycles average fault interruption time, reduced to less than 3 cycles • Insulation: Several weaknesses have been identified and corrected. Yet the possibility of a major fault could not be totally discarded • Containment: Very little knowledge on the subject, a R&D project is initiated PL

  7. Failure statistics 735 kV (25 years) • 175 failures that resulted in 111 high energy arcs causing 44 tank ruptures and finally 18 fires PL

  8. Rupture vs Fault Energy 700 kV PL

  9. "Worst" worst rupture modes PL

  10. "Less" worst rupture mode PL

  11. "Least" worst rupture mode PL

  12. R&D Simulation tools • Theoretical part based on analytical and numerical models identifying fundamental parameters. Derive a straightforward method for calculating the static pressure. PL

  13. R&D Arc simulation setup • Experimental part involving simulation of the dynamic load factor F to be applied to the static pressure to take into account the dynamic effects. PL

  14. R&D Results Pressure Displacement PL

  15. R&D Results & Conclusions • Arc induced explosions can be simulated but sophisticated tools are required • Deformation, not pressure, should be used to determine tank rupture. • Dynamic factor have been proposed to extrapolate static calculations • Testing by high pressure gas injection is possible • New tank resistance specification has been formulated PL

  16. New specifications - Philosophy • Priority is given to the protection of the workers • Worst energy levels may not always be containable by the tank • First rupture point must be the cover • Required calculation tools must be accessible to transformer designers • Must take into account the highly dynamic phenomena involved • Must be easily verified PL

  17. New specifications - Objectives • Stimulate new tank designs • Exchange technical information with manufacturers • Aiming in long term to see that new tank designs meet arc energy requirements PL

  18. New specifications - Formula • Ps – Calculated tank pressure withstand • F – Dynamic (time & location) amplification • E – Fault energy level to withstand • K – Arc energy conversion factor • C – Tank expansion coefficient PL

  19. New specifications – Dynamic factor • Time related dynamic factor (pressure and deformation) • Proximity related dynamic factor • Takes into account tank volume PL

  20. Manufacturers' response • All transformer suppliers since 1992 have shown adequate tank withstand analysis • One supplier has proposed an improved tank design (double arc containment capability to 20 MJ) • Containement of the highest levels of arc energy require complicated pressure venting system with numerous rupture disk all over the tank or double-walled tanks PL

  21. Where do we go from here ? • Present design can contain up to 10 MJ for the largest tanks (735 kV) • More resistant tank design can be achieved • Need to implement specifications with minimum energy requirement to meet . Utilities need to agree on reasonable levels • Testing by high pressure gas injection is feasible and more appealing than real arc testing PL

More Related