290 likes | 387 Views
King Fahad Cardio. Surgery & Disease center Project Group.1. Prepared By Supervisor : Prof.Naif bin Humaid mahmoud Abdullrhman Bin Mohammed ALMannaa Abdullah ALQhtani Yazed ALarafj Emad Shieraz
E N D
King Fahad Cardio. Surgery & Disease center ProjectGroup.1 Prepared By Supervisor : Prof.Naif bin HumaidmahmoudAbdullrhman Bin Mohammed ALMannaa Abdullah ALQhtani YazedALarafj EmadShieraz Faisal ALolyani MeshariALOabied
Project Introduction • The work comprises of detailed shop drawing design of civil, structural, building works, electrical, plumbing and mechanical installation work, site work and all other works for the construction, completion of the King Fahad Cardio- Surgery and Disease Center Building. This is a seven (7) storey building a total floor area of 70.000 m2, one (1) of which is basement. • The project duration is 720 calendar days from the site handover date confirmed with a signed acceptance by ABV Rock Group Ltd., Project Manager.
Project Highlights • Client : King Saud University, Ministry for Higher Education • Design Consultant : Zuhair Fayez Partnership • Shop Drawing : ABV Rock Group Limited • Contractor : ABV Rock Group Limited • Contract Type : Lump sum contract • Project Area : 70.000 M2 [Building/Floor Area] • Project Start Date : 27th December 2009 • Project Finish Date: 29 April 2012 (After Receiving an Extension Time)
Progress Achievements: • Partial Site hand over from 27th December accepted • Excavation in hand-over area of the building mostly completed • Structural work with foundation started, into the fifth floor. • Masonry works started in basement, ground and 1st floor
Abdullah ALQhtani • description quantity unit cost total cost حفر بالموقع لعمق لايتجاوز 7 متر للبدروم من منسوب الارض الطبيعية حفر 105300m3 35 3685500 excavate over site to form basement not exceeding 7m deep نقل خارج الموقع 90000 13 1170000 quantity daily prod of crew crew make up man hours total man hours total crew hours avg wage rate 105300 100 1forman - labor3 per unit 11232 3744 12.5 0.106 labor subtotal rate per hour equip subtotal total cost 140400 6×700÷8=525 1965600 2106000 20 3بوكلين__1 شويل- 2 truck قلابي 90000÷12.5=7200h 7200(88+75)=1173600$ 1173600÷90000=13 13 100m3/day÷8h/day=12.5m3/h حفر خنادق لزوم كمرات الربط والاساسات بعمق لايتجاوز 1 متر من مكنسوبالارض 76م3 50 3800 excavate trenches for tie beams and bases not exceeding1 m deep حفر قواعد الاعمدة لعمق لايتجاوز 1 متر من منسوب الارض الطبيعية 308م3 50 15400 excavate pits for column pads not exceeding 1m deep commencing at existing ground level ردم بمواد حبيبية معتمدة تم اختيارها من مواد نواتج الحفر او من خارج الموقع 9006م3 12$/m3 108072 حسب توصيات تقرير فحص تربة الموقع وذلك لتعويض المناسيب متضمنة اعمال الدك وماشابه ذلك من اعمال حسب المواصفات القسم 02200 approved granular fill selected from excavated material according or imported fill material to site soil report recommendation and subject to engineers approval in making up levels including compaction and the like as per specifications section 02200 quantity daily prod of crew crew make up man hours total man hours total crew hours avg wage rate 9006 600m3/day 2 per unit 234.156 117 12.5 0.026 labor subtotal rate per hour equip subtotal material total cost material total cost $/m3 2927 350 40950 5 $/m3 45030 88907 10$ سعة تريلا20م3 ×6رحلة /يوم=120م3/يوم ÷ 8س/يوم=15م3/ساعة 600م3/يوم لشويل÷120م3/يوم للقلابي =5تريلا 9006م3÷120÷5تريلا=15يوم=120ساعة 120س(5تريلا×150$/س +125$/س)=$105000 105000$÷9006=12$/ م3 مواد ردم انشائية موردة من خارج الموقع ومدكوكة بصورة جيدة فوق الاساسات و 18097م3 35$/m3 633395 القواعد للوصول إلى المناسيب شاملا ذاك الدك حتى الوصول الى الكثافة المطلوبة طبقة من الحصى الخشن المدموك بسمك 100مم تحت البلاطات على سطح الاوض 80م3 8$/m3 640 100mmthick drainage layer to underside of slab on grade as per specifications section 02200 معالجة التربة ضد النمل الابيض تحت البلاطات وعلى طول محيط المبنى 16060م2 8$/m3 128480 to formation subgrade of slabs and beds including periphery of building حصر وملأ الفراغات بالصخر حسب ظروف الموقع 500م3 1000$/m3 500000 allow for cavity filling as required total cost 6245287$
sample calculation FOR CONCRETE By Emad & Faisa;
التأمين الهندسي في المملكة العربية السعودية
مقدمة : • وصل التأمين في المملكة العربية السعودية متأخراً , و خصوصاً في الجانب الهندسي , وحتى الآن لا تزال استخدامات التأمين محدودة في المشاريع الضخمة , ولعلنا في هذه الجزئية نعرّج على أنواع التأمين الموجودة بالمملكة , ونأخذ على سبيل المثال – الشركة التعاونية للتأمين – بحكم قدمها بالسوق السعودي علاوةً على تربعها على سوق شركات التأمين .
أنواع الـتأمين الهندسي : • أولاً : تأمين المقاولين "ضد جميع الأخطار " • ثانياً : تأمين تجهيزات وآليات المقاولين • ثالثاً : تأمين عطب الآلات • رابعاً : تأمين خسائر الأرباح الناتجة عن عطب الآلات • خامساً : تأمين المراجل وأوعية الضغط • سادساً : تأمين الأجهزة الألكترونية
تأمين المقاولين ضد جميع الأخطار • الأكثر شيوعاً .. المستخدم في هذا المشروع
يطلب من طالب التأمين أن يحضر البيانات التالية : • اسم المشروع و رقمه , الموقع , العنوان , المقاولين الرئيسين و الباطن ,المهندسين الاستشاريين • وصف أعمال المشروع : المساحة , نوع الأساسات , طرق التشييد , مواد التشييد
بعد ذلك يطلب منه أن يجيب على بعض الأسئلة المتعلقة بالمشروع و منفذ المشروع : • هل المقاول سابق خبرة ؟ • مدة التأمين • مدى الخطوة في : الحرائق , الفيضان , العواصف , التفجير , البراكين , الزلازل • ما مدى مستوى السلامة ؟ • تفاصيل التربة التحتية • المياه الجوفية • مواسم الأمطار • مدى تأثر الممتلكات المحيطة بالمشروع
يشمل التأمين في هذا النوع على : • الأضرار المادية : • الأعمال الدائمة و المؤقتة , منها : المواد التي تم توريدها من قبل صاحب العمل • تجهيزات و معدات التشييد • الاليات المستخدمة في الانشاءات • إزالة المخلفات • الممتلكات الكائنة بموقع العمل
المسؤولية تجاه الغير : • الإصابات الجسدية • الممتلكات • الكابلات و المواسير