1 / 18

Anatomy of a Successful LNG Project Gastech 2008

Anatomy of a Successful LNG Project Gastech 2008. Original Conceptual Photo of EG LNG Train 1. Anatomy of a Successful LNG Project GasTech 2008. - Henry Aldorf Regional Vice-President Business Development - Bonifacio Monsuy Deputy Managing Director EG LNG - Al Pace Project Director.

miette
Download Presentation

Anatomy of a Successful LNG Project Gastech 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Anatomy of a Successful LNG ProjectGastech 2008 Original Conceptual Photo of EG LNG Train 1

  2. Anatomy of a Successful LNG Project GasTech 2008 - Henry AldorfRegional Vice-President Business Development- Bonifacio MonsuyDeputy Managing Director EG LNG- Al PaceProject Director

  3. What Makes a Successful Project? - Project Development- Entrepreneurial Company- Health, Environmental, Safety, Security- Cost- Quality – Conformance to Requirements- Schedule- National Content

  4. EG LNG Train 1 Successes - Project Developed in Record Time: August 2002 Recommend LNG Plant June 2004 EPC Contract Notice to Proceed - EG LNG: Formed Ahead of Schedule - Safety OSHA Recordable Rate 0.67 8.7 Million Hours without Lost Time Incident

  5. EG LNG Train 1 Successes • Cost: Within Budget • Quality: Exceeded Nameplate Capacity in Plant Performance Test • Schedule: First LNG Shipment 5 Months Ahead • National Content: Exceeded Goals

  6. Project Development -How We Did it Highly Experienced Team- E.G. Government Placed Priority on Project- Shareholders Aligned- Synergy Between Gas Supplier & Train 1- Self Financed- Lessons Learned From Ongoing Operations- All Offtake to One Entity

  7. Entrepreneurial Company Building Why It Was Successful - Staffed with Senior People - Managed Against a Business Plan - Excellent E.G. Government Cooperation - Local Business Entities Assistance - Immediate Start with National Staffing - Cost Control Like a Project - Managed to a Schedule

  8. Project Execution Model Setting Up For Success Proven General Contractor- Proven Technology- Proven Vendors and Subcontractors- Serial No. 8- Lump Sum Turn Key- Incentives for: Safety, Schedule, National Content, Plant Production

  9. Project Execution Model Health Environmental Safety (HES) - Management Commitment and Strong Participation - Created Culture of Safety First - Agreed Safety Procedures Before Mobilization - More “Boots on the Ground” - Safety Incentives - All Incidents Reported & Investigated, Even Property Damage

  10. Project Execution Model Project Management Fundamentals - Highly Experienced TeamBoth Owner & Contractor Experience - Owner’s PMT Resided with ContractorCenter of Gravity Shift - Created a One Team Environment

  11. Project Execution Model Engineering - Minimized Change from the FEED (AFE) Basis- Owner’s PMT did not Question the Need for a Quick Response- Owner Used a Variety of Subject Matter Experts

  12. Project Execution Model Procurement Long Lead Orders Before Financial Investment Decision- International Procurement- Project Specific Construction Jetty- Considerable Owner Inspection (In Addition to Contractor’s Inspection)

  13. Project Execution Model Craft Training - Built Dedicated Facilities - Brought in Professional Instructors (Spanish Speaking) - Dove-Tailed Training Schedule with Construction Staffing Plan

  14. Project Execution Model Craft Training

  15. Project Execution Model Construction Construction Participation in Design for Constructability - Very Effective Early Works Program at Site - Strong Early Focus on Engineering & Procurement Schedules Ensured Materials & Equipment On Site When Needed

  16. Project Execution Model Project Controls - Assumed from Day 1 that Money Would be Tight - Very Strong Emphasis on Owner’s Cost Forecasting- Schedule – Sense of Urgency from Day 1 + Incentives

  17. Closing Comments - A Great Team Effort - Highly Motivated, Creative, Experienced Personnel - Fundamentals Still Apply

  18. Aerial Photo of EG LNG Train 1

More Related