An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design-Build Project Request for Qualification and Proposal: Pre-Submittal Conference November 12, 2013 Madison County 16 E 9th StreetAnderson, Indiana 46016PROJECTSWork Release / Offices Building #1(Bil#2) Work Release / Offices Building #2 (Gil#2)Parking Lot and Drive #3 Work Release / Office Building Projects

  2. Overview: The Project Single Step Design-Build delivery for the re-model of the Work Release / Offices Building #1 & 2 Scope: Approximately 4,500 sq. ft. each Location: Madison County Juvenile Campus Work Release / Office Building Projects

  3. Project Location Madison County Juvenile Campus Work Release / Office Building Projects

  4. A-BIL#2 B-GIL#2 Project Location Madison County Juvenile Campus Work Release / Office Building Projects

  5. New Drive for Bus Access New Parking Lot Project Location Madison County Juvenile Campus Work Release / Office Building Projects

  6. Overview: Request for Qualification • To obtain RFQ: • Send e-mail to bills@PMSIcorp.com • You will receive download instructions • All information available on: Drop Box/ Madison County Work Release • Copy available at this Pre-Submittal Conference • Verified Statements of Qualification/RFP due: • December 13, 2013 / 3:00 PM (EDT) Work Release / Office Building Projects

  7. Overview: Request for Qualification • Process to follow Indiana Public Works Design-Build Law[IC 5-30] • Project is not subject to Common Wage Rates • Caveats: • Madison County is not responsible for any expenses incurred by a Design-Builder in preparing and submitting information in response to this “Request for Qualification/ RFP.” • Madison County reserves the right to terminate the process at any time prior to execution of an agreement between Owner and Design-Builder without obligation to the Design-Builder. Work Release / Office Building Projects

  8. Overview: Request for Qualification • A Technical Review Committee has been formed: • Dan Dykes Madison County Administrator • Rick Gardner Madison County Council • Charles Lester PE Madison County Engineer • Ann Roberts Madison County Community Justice Center • Bill Shepler PE DBIA PMSI – Owner’s Project Leader/Criteria Developer Work Release / Office Building Projects

  9. Communications During Selection • All communications during selection through Owner’s Project Leader: William Shepler, PE DBIA PMSI P.O. Box 900 Noblesville, Indiana 46061 (317) 432-6920 cell (765) 534-0254 fax bills@PMSIcorp.come-mail • Unauthorized contact with TRC members or county officials by Design-Builders during selection may result in disqualification. Work Release / Office Building Projects

  10. Project Budget Construction $300,000 to $350,000Includes Design-Builder’s Fees Work Release / Office Building Projects

  11. Schedule Work Release / Office Building Projects

  12. Schedule Work Release / Office Building Projects

  13. Schedule Work Release / Office Building Projects

  14. Project Completion Schedule Will be determined by selected Design-Builder’s proposal Work Release / Office Building Projects

  15. Evaluation Criteria How the Technical Review Committee will score RFQ/ RFP Work Release / Office Building Projects

  16. Required CriteriaMinimum Criteria – Pass/Fail Indicate compliance with RFQ/RFP checklist Design-Builders Team Information Adequate Financial Standing and Bonding Capacity Certificate of Insurance with Safety Record within Industry Average Ability to provide necessary licenses and registrations to Design-Build the project No record of unacceptable non-performance Work Release / Office Building Projects

  17. Weighted Evaluation Criteria Work Release / Office Building Projects

  18. Weighted Criteria: Scoring Example Work Release / Office Building Projects

  19. Submission Requirements Work Release / Office Building Projects

  20. Submission Requirements Work Release / Office Building Projects

  21. Drop Box/ Madison County Work Release • FOLDER TO BE USED DURING PROJECTS: • Design Builders Record Documents • Design-Builders Application for Payments • Design-Builders Monthly Reports • Design-Builders RFI or RFP's • Design-Builders Schedule • Design-Builders Submittals • Design-Builders Contract-Contract form • “FOLDERS” are here for informational • purposes only Work Release / Office Building Projects

  22. Drop Box/ Madison County Work Release FOLDER TO BE USED DURING SUBMITTAL: Existing Facilities-Design documents of existing facilities Minutes of TRC Owners RFQ-RFP: Addenda to Owners RFQ-RFP Editable Documents for RFP Draft- Madison County Work Release Office Projects A- BIL2-Design-Build Document B-GIL2-Design-Build Document Photos Consideration in using Drop Box Copy out of box- Open and Save to your computer! Leave Original in Folder! Do not add or alter information in “Folders” Work Release / Office Building Projects

  23. Q+A Questions from Design-Builders Informal answers today. Official answers will be in the form of an addendum to the RFQ/RFP. Work Release / Office Building Projects

  24. Thank You. Work Release / Office Building Projects