1 / 5

SDC Update

SDC Update. October 5, 2011. SDC/OB2 Migration. Major Accomplishments Charter in final draft, established CTS core team, defined communication strategy for OB2 customers OB2 core: Network upgrade completed

milica
Download Presentation

SDC Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SDC Update October 5, 2011

  2. SDC/OB2 Migration • Major Accomplishments • Charter in final draft, established CTS core team, defined communication strategy for OB2 customers • OB2 core: Network upgrade completed • SDC core: Most network equipment has arrived; structured cable design approved; project on schedule • Facility: First enclosures being installed (for core); DCIM tool received; resolved several physical security issues • DSHS Core Redesign: CTS/DSHS team completed conceptual design – could be used as framework for planning other agency moves

  3. SDC/OB2 Migration • Major Activities Planned Next Month • Gain approval for updated project charter • Complete overall SDC/OB2 Migration task plan and schedule • SDC Core: Take delivery of equipment for structured cable project • Facility: Complete enclosure install (for core); install and configure DCIM tool; continue verification of video surveillance system • OB2 Move: Begin enclosure planning using DCIM tool; inventory A La Carte 1

  4. Private Cloud Procurement • Completed • Procurement consultant (TPI) started Sep 13th • Completed Milestone #1: Project planning and kickoff with CTS procurement team • Identified participating agencies and scheduled requirements workshops (four half-day sessions) • For October • Complete three of four requirements workshops • Draft RFP requirements and evaluation requirements

  5. Business Plan Update • Collaboration between OCIO and CTS • OCIO taking the lead in developing financial analysis model • Meeting twice a week to complete work on defining the model and updating numbers

More Related