E N D
1. Lean Six SigmaCase Study: MRAP Matt Slides 1-5
Krista Slides 6 - 10Matt Slides 1-5
Krista Slides 6 - 10
2. 2 Why is Lean Six Sigma important? Purpose:
CPIMS To capture Lean Six Sigma Efforts and standardizing reports
Mention: CPI Conferences
Contractor: Competitive Advantages, Past PerformancePurpose:
CPIMS To capture Lean Six Sigma Efforts and standardizing reports
Mention: CPI Conferences
Contractor: Competitive Advantages, Past Performance
3. 3 Meeting Our Nations Demand Signal Problem Statement
IEDs were causing 70% of the casualties in theater.Problem Statement
IEDs were causing 70% of the casualties in theater.
4. 4 Strategic to Tactical All MRAP Players
Charleston is the HUB of the MRAP Program. All MRAP Players
Charleston is the HUB of the MRAP Program.
5. 5 Initial Surge Exceeded Existing Capacity This is NOT bad. This is to be expected, because this was the largest buildup of military vehicles since WWII.This is NOT bad. This is to be expected, because this was the largest buildup of military vehicles since WWII.
6. 6 Recipe for Success Workers are the key to success!
Even though CHS is the HUB the team didnt exclude any outside players. Most outside players moved liaisons to CHS to work directly with the program.Workers are the key to success!
Even though CHS is the HUB the team didnt exclude any outside players. Most outside players moved liaisons to CHS to work directly with the program.
7. 7 Lean Six Sigma Line Design This slide is directly showcasing 4 LSS events. The LSS team had to focus immediately on the 2 stations across the 25 lines. The first event identified was a Point-of-Use Hardware 5S Tooling events.
The 2nd constraint identified was how the GFE was delivered to the lines.
The 3rd events was TAKT boards. This goal was to standardize work processes.
The 4th events was to communicate and standardize Quality Assurance Inspections across the 25 lines and 2 shifts.This slide is directly showcasing 4 LSS events. The LSS team had to focus immediately on the 2 stations across the 25 lines. The first event identified was a Point-of-Use Hardware 5S Tooling events.
The 2nd constraint identified was how the GFE was delivered to the lines.
The 3rd events was TAKT boards. This goal was to standardize work processes.
The 4th events was to communicate and standardize Quality Assurance Inspections across the 25 lines and 2 shifts.
8. 8 Lean Six Sigma Status Total Projects Identified 57
7 Projects in progress
44 Completed
6 future events - The next steps were to hold an Executive Planning Session with mgmt to capture the focus areas.
- Through the EPS they identified over 50 projects/events which were captured on a Benefits and Efforts chart. Looking at the graph the team would want to focus on the green area representing a High Benefit and Low Effort events. The helps create a battle map.
- Utilizing LSS along with the subject matter experts Capacity exeeded demand!- The next steps were to hold an Executive Planning Session with mgmt to capture the focus areas.
- Through the EPS they identified over 50 projects/events which were captured on a Benefits and Efforts chart. Looking at the graph the team would want to focus on the green area representing a High Benefit and Low Effort events. The helps create a battle map.
- Utilizing LSS along with the subject matter experts Capacity exeeded demand!
9. 9 Lessons Learned Senior Management Engagement is Key
Inclusion of Subject Matter Expert (Worker) is critical
Quick results Challenge current conventions
Standardized Work Flow is Critical No Clichés
Add New Ideas
Parallel Progress
External Professionals
No Clichés
Add New Ideas
Parallel Progress
External Professionals
10. 10