Instrument Readiness Review at NSLS II 2018 Accelerator Safety Workshop; SLAC Andrew Ackerman NSLS II ESH August, 2018
Outline • Instruments (Beamlines) • Instrument Readiness Review process • Experience
NSLS II • Accelerator Ready Review • ARRs • (FY14) • Commissioning: linac, booster, storage ring • Routine Ops • User Science
NSLS II Beamline (An Instrument)Integrated In-situ and Resonant Hard X-ray Studies (ISR) • ISR In Vacuum Undulator (IVU-23); long straight IVU-23 HFM 3 endstations DCM SSA DPP VFM DHRM KB
NSLS II BeamlineISR Instrument Layout Four hutches: two for optics, two for User data collection FOE Hutch C SOE Hutch D Beamline Layout cryo-cooler photon shutter photon shutter magnet diffracto-meter 6-circle diffracto-meter KB mirrors DHRM & SSA base diffracto-meter DCM HFM DPP VFM VFM VFM shielded beam transport shielded beam transport distance from center of straight (mm)
NSLS II Sources 3PW Assembly EPU57 EPU105
Beamline Hazard Analysis • Standard accelerator risks: • Electrical power • Fire • Pressure safety • Cryogens (LN2 & LHe) • Lead • Radiation • Bremsstrahlung – primary (ray trace) & secondary (Fluka); High energy, low power • Synchrotron – secondary (STAC 8); heat load (equipment & shield protection); low energy, high power
NSLS IIBeamline Instrument Readiness • Readiness “Systems and procedures established to address credited controls, documentation requirements, and personnel qualification“ ―Accelerator Safety Order • Ready to commission • Technical • Safe photon beam generation and delivery into the experiment endstation. • Science • Optimize performance • ‘Friendly’ Users • Beamline Instrument Readiness Review (IRR) – Technical Commissioning start • Point in time; Scope definition important Ready for User operations – separate process; procedure: review system • Beamline space – annual review; BNL electronic system • User science – beam time cycle review; another BNL electronic system
Building a BeamlineAn Extended Project (years) • Design & Plan • Science • Hazard control • Procure • Install • Travelers – checklists – meet specs • Integrated testing (no beam) • Assign and qualify staff • Role • Procedures • Instrument Readiness Review • ~ 6 weeks Getting Ready • Instrument Readiness Plan • Organize • Define: • Scope • Basis • System specific • Actions & documents • ~40 criteria • Status tracking • Declare ready – signatures • Lines of Inquiry (LOI) for the review IRP
Instrument Readiness Plan (IRP) CriteriaDesign and Plan • Functional description (scope definition) • Design • Source, Front End, & Beamline components • Radiation Safety components • Top-Off Safety System (TOSS) • Bremsstrahlung & Synchrotron Ray traces • Secondary radiation scatter analysis (FLUKA & STAC 8) • Plan • NEPA evaluation • Un-reviewed Safety Issue (USI) resolution • Legacy open action item resolution • Instrument specific procedures • Commissioning plan • Radiation survey plan
Instrument Readiness Plan (IRP) CriteriaInstall and test • Radiation safety components • Shielding, masks, labyrinths, shutters … • Area Radiation Monitors (ARMs) • Personnel Protection System (PPS) interlocks • O2 Sensors • Hutch structures (life safety) • Electrical power distribution • Utilities (water, LN2, LHe) • Beam transport components • Equipment Protection System (EPS) • Controls • Vacuum Safety Critical Other
Instrument Readiness Plan (IRP) CriteriaAssign and qualify staff • Assign roles and Job Training Assessments • Lead Beamline Scientist • Authorized Beamline Staff • Cognizant Space Manager • Beamline Support Staff • Assign procedure training • Read and sign • Demonstration
Review Team Charge • 7 person team – BNL & NSLS II • Web page • Team collects information: • Interview staff • Read documents • Inspect the instrument • Team provides: • Review details (staff, document, topics) • Observations (noteworthy practices; suggested improvements) • Findings (pre & post) (tracked to closure) • “Recommended” Corrective Actions Pre-start means (Required for safe beam operation)
Experience 16
Beamline IRRs • 09/14: CSX 1&2 • XPD • 10/14: HXNSRX • IXSCHX • FY 16 • 10/15: LIX • 03/16: FMX/AMX • 04/16: ISS • 06/16: ISR • XFP • ESM • 08/16: TES • CMS • FY 17 • 10/16: SMI • 11/16: SIX • NYX • 07/17: R&D • BMM • 09/17: XFM • QAS • FY 18 • 10/17: FXI • 02/18 SST 1&2 • 03/18: PDF 27 Total 8/07/18
Subscription Rates (2018-1) 2.4 2.3 2.8 2.0 1.0 2.3 1.4 1.2 1.5 1.4 1.1 1.0 1.0 1.2 1.8 1.0 2.0 3.3 1.9 Proposal subscription rate = proposals submitted / proposals allocated
NSLS-II Facility Users (as of April 24, 2018) FY15 • unique users: 110 • 100% were first-time users FY16 • unique users: 477 • 83% were first-time users FY17 • unique users: 1037 • 69% were first-time users FY18* (as of 24-April-2018) • unique users: 987 • 48% were first-time users Users
NSLS-II Publications (as of May 10, 2018)
ExperienceNSLS II Beamline IRR The IRR is a big effort (Beamline and Accelerator staff) • Intended • Significant risks (personnel and project) • $10 – 15M instrument • High expectations – Users are coming • NOT an agile process – 6 to 8 weeks preparation • Weekly status meetings (needed, but not popular) ~ 45 managers / engineers / scientists • Varied documents to complete, file, and post on web (some) • ~ 40 criteria – signatures • Report and follow up
ExperienceNSLS II Beamline IRR It is hard to be ready on time • Must schedule a date in advance – deadline • Project deliverables / milestones • Best = source to end-station • In practice – Source & FE ready first – split into two IRRs • Science wants review once something is ready (adjust scope) • Biggest challenges • Vendor supplied items • Lead shielding components • Optics • PPS design / installation • Radiation safety analysis (ray traces and scatter) • All documentation (one week in advance) • Ray traces • Final layout capturing all radiation safety components • Mechanical survey reports • Discrepancy reports • Adjust scope to meet date: something is ready • Self-identified pre-start – we’re almost ready
ExperienceNSLS II IRR Readiness brings resources that leave after the review. Strategy • Clear IRP criteria definition = difficult; important • Multiple instruments reviewed together = stress installation resources • Review team selection • NSLS II / BNL • BNL SMEs; NSLS II scientist, ESH, QA • Added BNL review team leader (2017); new eyes and perspective • PPS, EPS, Controls – unique for reviewers • Review meeting time? ~ 1.5 days / instrument • Walkthrough is productive – seeing stimulates conversation • Tailored Review Plan: • IRR threshold? Equipment Readiness Review (ERR)?
ExperienceNSLS II Beamline IRR Findings • Configuration control • Labeling, photos, checklist • Utility mechanical support and labeling • Bump and trip hazards • Documentation for pressure testing. Utilities, windows (Kapton, diamond, Be) • Hutch Personnel Protection System (PPS) hardware field location • Forced search buttons locations & emergency stops • Installation sequence forces early decisions