MicroSCADA Proin demandingIndustrial Applications John Tsao Eric Chuang Anders Brokvist
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
About Nanya Technology Corp. • Founded on March 4, 1995 • Main shareholder: Nanya Plastics Corporations of the Formosa Plastics Group • Headquarters in Taoyuan, Taiwan • 5,275 employees (Oct 2007)
About Nanya Technology Corp. • Conduct research and development, design, manufacturing and sales of DRAM products • Two factories producing 8-inch (200mm) wafers and one factory producing 12-inch (300mm) wafers
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
NTC Fab 3 • 12-inch wafers with 70 and 60nm technology • Planned max. capacity/month 62,000 wafers • Constructed in two phases: • Fab 3A: 70nm 30,000 wafers/month • Fab 3B: 60nm
NTC Fab 3A (phase 1) • Milestones: • 3 / 2006 : Ground-breaking ceremony • 3 / 2007: Clean room construction • 5 / 2007: Equipment move-in • 10 / 2007: Successful Pilot run • 3Q / 2007: 70nm wafers production started Customer: NanYa Technology Corporation (NTC) Year of commissioning: 2007
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
MicroSCADA Installation Customer’s need • EPC contractor NanYa Switchgear Unit builds six (6)new “Fab3A” substations • Reliable partner for SA to support the project from tender clarification to turnkey implementation ABB’s response • SAS650 IEC61850-based system with fully redundant hot-standby station servers • Various ABB IEDs (REX521 * 197 pcs, REF541 * 66 pcs, RET541 * 13 pcs, & REB670 * 3 pcs) integrated in MicroSCADA Pro HMI with new GUI • Integration of 3rd party meters & D-UPS, DC charger, MIMIC controllers via MODbus and Allen- Bradley PLCs via OPC connection Customer’s benefits • Close cooperation resulting in optimized solution • Safeguarded investment and optimized life cycle cost through future-proof IEC61850 based systems • Excellent local competence and support Customer: NanYa Technology Corporation (NTC) Year of commissioning: 2007
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
System Layout • System level
System Layout • System level • 2 pcs Hot Standby Servers • 4 pcs Workstations • 7 pcs Front-end computers: • 3 pcs with local database & workplace (Mirroring to Servers) • 4 pcs without local database (“COM530”) • Front-ends contain IEC61850 OPC Server and External OPC DA Clients • Redundant Ethernet (Tree)
System Layout • Substation level
System Components • Server computers: IBM eServer X236 • Xeon 3.2GHz*2 CPU • 4GB RAM • 4*80GB SCSI RAID • Matrox P650 VGA Dual Graphics card • Windows 2003 Server • SYS 600 9.2 • Front-end computers: Advantech IPC-610 • Pentium P4 3.0GHz, 2GB RAM • Windows XP Pro • SYS 600 9.2
System Components • Ethernet switches: Ruggedcom RSG-2100 (28 pcs) • Serial Device Servers: Moxa Nport 16-port (7 pcs) • For Modbus, RP570 protocols • Meinberg Lantime GPS receiver • Report printer • Event printer
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Process Devices • Applications • Engineering
Process Devices ABB IED’s: • REX 521 (197 pcs) • REF 541 (66 pcs) • RET 541 (13 pcs) • REB 670 (3 pcs) 3rd party devices: • RTU 211 (7 pcs, General I/O) • Allen Bradley PLC (Generator controller) • Modicon PLC (DUPS controller) • Siemens S7 PLC (Mimic controller) • Siemens P650 (Meters)
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Devices • Applications • Engineering
Applications • Connected to FMCS (Facility Maintenance Control System) using OPC DA Server • DUPS interface (Dynamic Uninterruptible Power Supply) • Mimic controller • Generator controller interface (Synchronization control) • Internal billing function • Geographical layouts • System supervision
Applications • DUPS interface (Dynamic Uninterruptible Power Supply) • Modbus interface to Modicon PLC
Applications • DUPS interface (Dynamic Uninterruptible Power Supply)
Applications • Mimic controller • Control room mimic controlled from MicroSCADA • Using Siemens S7 PLC connected on Modbus
Applications • Generator controller • Connection realized by using AB RSLinx as OPC Server SYS 600 OPC DA Client Front-end computer RSLinx OPC DA Server Ethernet Allen-Bradley PLC SLC503 Allen-Bradley PLC SLC503 Redundant PLC
Applications • Internal billing function • Creates energy consumption reports • Exports information to MS Excel
Applications • Geographical layouts • Helps operators locate alarms in factory
Applications • System supervision – main system devices
Applications • System supervision – IED displays
Applications • System supervision • IED supervision uses two signals: 1. System – SPA-ZC40x adapter using “Device connection status” item 2. SPA-ZC40x – IED using “ComStatus\stVal” (SPS)
Contents • About Nanya Technology Corporation (NTC) • NTC Fab 3 • MicroSCADA Pro Installation • System Layout & Components • Devices • Applications • Engineering
Engineering • Engineering tools: • CET for SPA-ZC40x • CET for IEC 61850 OPC Server • SCL Importer • OPC PO list • External OPC DA Client Conf. Tool • Object Navigator • Display Builder
Engineering Problems encountered in MicroSCADA • Trends with Chinese OX characters crashes Trend Basket • Busbar coloring not support multiple displays • SCL Importer OX texts for protection signals • Device naming (IEC61346) used in SCL not accepted by customer Problems encountered with adapters SPA-ZC40x • MMI alarms not in connectivity packages, requires manual entering • Supervision signals not in connectivity packages, requires manual entering • Time synch problem with OPC Server-> SPA-ZC40x, required update of firmware
Engineering Lessons learned: • Complete SPA-ZC40x configuration before downloading to all adapters • We downloaded new configurations (and firmware) several times (to over 250 adapters)! • IED time synchronization to be done directly from GPS receiver • IEDs are now synchronized from Front-end OPC Server • Consider to have one large Ethernet network for whole system • Now the process devices are on a separate network