2. Present Power Scenario
3. Future Forecast
5. India's Nuclear Power Programme Closed Fuel Cycle
First Stage Uranium ( Natural , Imported Enriched )
(PHWRs & LWRs)
Second Stage Plutonium (Reprocessed Spent Fuel)
(FBRs)
Third Stage Uranium 233 (Converted from Th-232)
(AHWR & future)
6. Present Status Seventeen Reactors 2 BWRs & 15 PHWRs with total
Capacity of 4120 MW in operation
One Reactor made Critical in November 2009
Five Reactors 3 PHWRs, 2 PWRs & One FBR with Capacity of 3160 MW under construction
Future plans
XI Five Year Plan 8x700 MWe PHWRs
2007 -2012 3x500 MWe FBRs
1x300 MWe AHWR
Augmentation plans 25-30 1000 MWe & Higher
(addtionality ) by 2030 LWRs
9. Imported LWRs with Fuel Imported LWRs with imported fuel – additional generation to meet energy requirements
Commissioning of 2 units of VVER Type reactors at Kudankulam is in progress
Pre – project activities for new LWRs in progress.
Clusters of 6 to 8 LWRs at one Site with gradual increase in localization
Simultaneous construction at many Sites
6 or more Reactors per Site.
Start Construction for twin Units
Second twin Unit s after around 3 years .
10. LWR Sites Presently 5 Sites identified for LWRs
Multi technology NPP approach
Division of Scope for cost optimisation
Gradual increase in localisation
Gradual Technology absorption
Construction, Commissioning & Operation by NPCIL
12. NPCIL to construct, commission and operate
Unit Energy cost the basis of negotiations
EPC of BOP by NPCIL
Localization from Indian market for sourcing components and manpower
Lifetime fuel supply commitments
13. Assimilation and Review of Technology Different technology such as VVER, EPR, ABWR,
ESBWR, AP1000
Technology Assimilation by NPCIL and Indian Regulators
Licencibility in country of Origin.
Licencibility in India.
14. Resource Management Supply Chain Management
Identification of Critical Components
Localization
Vendor qualification
Quality of supplies
Delivery Schedule
Risk Management
Service and Support during erection and thereafter.
Preservation and Storage
15. Construction Support Review of Port Infrastructure for Heavy Equipment
Suitable Jetty for unloading at Site.
Strengthening of bridges, roads & culverts for movement of Over Dimensional Consignment from Indian Manufacturers.
Material Handling Equipment for loading/Unloading
16. PRE PROJECT ACTIVITIES Land Acquisition
Geo Technical investigation
Evaluation of Seismic Potential.
Statutatory Clearances from Ministry of Environment and Forests (MOEF).
Site Clearance from AERB
Establishment of other Infrastructure Facilities.
17. Construction and Erection Transportation
Availability of large capacity Cranes to meet varied needs of different Plant Designs.
Strategy for Meeting Shorter Construction Targets including Modularization & Automation
Equipments , tooling and Machinery to meet the Specific requirement of NSS Welding at Site.
Special Equipment for Non Destructive Testing
Construction Interface management
18. Human Resources Development of Human Resources for Pre project activities, Construction, Erection, Commissioning, Operation
Absence of operating experience of New LWR’S
Imparting specialized training for Modular Construction and Automation.
Early availability of Training Simulator.
Training and qualification of Operating Personnel.
Building a strong safety culture. IAEA, WANO
19. Commissioning Trained Human Resources.
Commissioning organization and Procedures.
Interface with Designer and Regulators.
Quality Assurance
Pre Service Inspection