Cockcroft-Walton Status. Carlo Bemporad Angela Papa Giovanni Signorelli Peter-Raymond Kettle. Overview. Machine Production Status & Schedule C-W Area + Beam Line Status & Schedule Integration into Beam Schedule 2007. Machine Status. original Completion Date:
E N D
Cockcroft-Walton Status Carlo Bemporad Angela Papa Giovanni Signorelli Peter-Raymond Kettle MEG Review February 2007
Overview • Machine Production Status & Schedule • C-W Area + Beam Line Status & Schedule • Integration into Beam Schedule 2007 MEG Review February 2007
Machine Status • original Completion Date: • ~ mid-May 2007 • NEW Completion Date: • ~ end-February & expected • Ready for testing mid-April ~ 2007 MEG C-W. Status End 2006 MEG Review February 2007
Components Section Target Support C-W • LiF Target holder + • vacuum chamber • Bellows System with stroke of ~ 2.2m drives COBRA Insertion System to place target at centre of COBRA Magnet • Quadrupole Doublet • x-, y-Steering Magnets • beam Shutter + Slits Beam Line Components Bellows Section • Bellows system Tested ready for shipment • Beam Elements available • Power Supplies available • Beam Diagnostic Elements • ( shutter, diaphragms, x-, y-slits, quartz crystal+TV-camera) • available or almost ready MEG Review February 2007
Machine Schedule • Completion of manufacture ~ end-February 2007 • Acceptance Tests in Amersfoort NL (or PSI) • with HVEE, INFN, PSI ~ mid-April 2007 ? • Shipment to PSI ~ end-April ? • Machine Installation + • Shipment/Guarantee Test ~ mid-April to mid-May 2007 MEG Review February 2007
Cockcroft-Walton Area • C-W AREA: • Area presented Nov. 2006 at • Coordination Committee Research • Area West • Officially in Shutdown Programme • area & infrastructure planned be • installed by the end of Shutdown • beam-axis extension survey end 2006 • infrastructure groups + Health Physics • notified – need Ministry of Health • clearance for the new area + C-W • M3 shielding to be removed now to • check space • more detailed meetings still needed to • finalize all points (Interlock system) MEG Review February 2007
Constraints • Safety System + • Electrical Infrastructure • unaltered • Permanent Access from • outside E5 Shielding Wall needs modifying Approx. form C-W Area M3 Shielding Must be MODIFIED Cockcroft-Walton Area cont. E5 Zone MEG Review February 2007
C-W Area Layout Virtually all Standard Concrete Blocks Still Problematic MEG Review February 2007
C-W Area Shielding • Planned Work needed for Completion • (By mid-April) • removal of walls + measure & • layout check - freeze design • order special shielding + start • standard shielding construction • infrastructure completion: • water, compressed-air, power • Safety systems completion (Interlock) • Ministry of Health Approval • test of Safety System (Beg. April) MEG Review February 2007
Testing & Integration into Beam Schedule • Full test with LiF-target only possible when: • area + safety aspects completed • C-W beam line components magnets, vacuum chambers etc. at PSI • C-W Bellows System at PSI (will arrive soon storage arranged) • target prepared • CONSTRAINTS: • cannot be tested in parallel with Beam Commissioning • bellows system cannot be placed in zone DC insertion system needed • C-W Bellows System cannot be in place during any DS Insertion • TCs or DCs or End-Cap installation/removal !!! • Proposed Commissioning mid-April – mid-June • SEE Proposed Beam Schedule 2007 MEG Review February 2007