1 / 10

HDM-4 Introduction to Program Analysis

HDM-4 Introduction to Program Analysis. Objective. To Prioritize candidate road sections in each year within the budget constraints. Procedure. Select road sections Determine maintenance / improvement options Specify the budget limits and budget periods Optimize using selected objective

minerl
Download Presentation

HDM-4 Introduction to Program Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HDM-4Introduction to Program Analysis

  2. Objective • To Prioritize candidate road sections in each year within the budget constraints.

  3. Procedure • Select road sections • Determine maintenance / improvement options • Specify the budget limits and budget periods • Optimize using selected objective • Produce the final list of projects for the budget period

  4. Multi-year Program • Method: • Life cycle analysis • Budget period analysis • Objective function: • Maximize NPV • Maximize road network condition

  5. Budget allocation • Routine maintenance costs are based on road lengths. • Recurrent costs are based on pavement surface condition. • Periodic maintenance are based on economic indicators. • Improvement needs are based also on economic indicators.

  6. Budgeting Procedure • When sufficient budget is available: • Select all independent projects with NPV>0 • Select mutually exclusive project alternative with the highest NPV. • When there is budget constraints: • Select the independent project using the highest NPV/Cost ratio • Select mutually exclusive projects using the incremental NPV/Cost

  7. Prioritization Project Cost NPV NPV/Cost Rank A 150,000 35,000 0.233 2 B 150,000 45,000 0.300 1 C 200,000 40,000 0.200 3 D 250,000 37,000 0.150 6 E 500,000 70,000 0.140 7 F 500,000 77,000 0.154 5 G 500,000 78,000 0.156 4

  8. Incremental Analysis Project Cost NPV NPV/Cost Rank A 20,000 4,869 0.2435 2 B 30,000 240 0.0080 8 C 20,000 5,184 0.2592 1 D 20,000 210 0.0105 7 E 40,000 6,401 0.1600 4 F 35,000 4,497 0.1285 5 G 20,000 1,200 0.0600 6 H1 80,000 15,000 0.1875 3 H2 100,000 16,829 0.1683

  9. Definition • Program analysis is concerned with the preparation of single or multi-year work program for the road network by maximizing the economic return (INPV/Cost) subject to budgetary constraints.

  10. Thank You

More Related