June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2 : Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve)
E N D
June 27-July2: Remove Shield Wall (3.5 days, Riggers) • June 27 – July 2: Remove Vacuum pipe spool pieces. • July 3: Pull East Poletip • July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) • June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables. • June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities. • July 20 – Aug. 24: EEMC electronics maintenance. • July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform. • July 30 – Aug. 14: Remove SSD, SVT, all utilities on cone, and reassemble cone. • Aug. 1 – 15: Install new BEMC PMT comm./controls system. • Aug. 16-21: Reinstall cone, reinstall FTPCs, & remove rails. Remove installation platform. • Aug. 22 – 27: Disconnect utilities. • Aug. 28 - 29: Roll STAR back into IR. • Aug. 30 – Sept. 10: Install Utilities. Draft STAR Shutdown Schedule/Plan July 2007 August 2007 Summer Sunday
September 2007 • Sept. 6 – 18: Beam Pipe Bakeout • Sept. 11th: STAR in IR with utilities connected. • Sept. 11 – Oct. 12: TPC Electronics maintenance. • October 1st: TOF Trays arrive at BNL for installation. • Oct. 15 – 18: SGIS Certification. • Oct. 17th: West Poletip installed. • Oct. 24: East Poletip installed. • Oct. 25 – 30: Magnet testing. • Nov. 1st: Collider Cooldown Begins. • Nov. 1 – 2: Install BBCs. • Nov. 7th: Lose access to IR for Collider Commissioning. • Still Open: • * When/where best to install TOF trays? Best locations 2, 4, 7, & 10:00. • * Details/plan for the TOF water system? October 2007 Collider Cooldown Begins