1 / 33

AA-mid demonstrator

AA-mid demonstrator. Dion Kant AAVP 2010 8 – 10 December 2010, Cambridge, UK. Outline. Project target Description of Work Project partnerships Current activities Evaluation results Conclusion. AA-mid (draft) key requirements. Requirements may still be adapted.

misae
Download Presentation

AA-mid demonstrator

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AA-mid demonstrator Dion Kant AAVP 2010 8 – 10 December 2010, Cambridge, UK.

  2. Outline • Project target • Description of Work • Project partnerships • Current activities • Evaluation results • Conclusion

  3. AA-mid (draft) key requirements Requirements may still be adapted

  4. AA-mid time line, phases and • Full project (~2000 m^2 AA) not funded today • AAVS1 = first phase • Funding for design phase within AAVS1 • 2010 to 2013 • Delivers design + small number of front end proto types • Use EMBRACE evaluation as input for design • Use EMBRACE platform as test-bed for new tile developments • New design based on EMBRACE • Site selection will be decided on later • First testing will be performed at current EMBRACE stations • Second stage testing: Use Portugal site (SKA like environment) • Second phase (AAVS2) (beyond 2013) full roll-out AA-mid demonstrator

  5. Design approach • Base new design on EMBRACE architecture and other demonstrators • Incremental approach • Level 1 topics (should) • Level 2 topics (may) • Main enhancements are (level 1 topics): • Introduce dual polarisation signal processing • Reduce power consumption per signal path • Improve tile control system • Reduce system noise • Second generation beam former chip (4-bit phase control) • Improve mechanical design, this includes housing & radome • Improve design for manufacturability

  6. Design approach level 2 topics • Investigate LNA above ground plane (integrated on feed board). Main goal is to be able to use FR4 for feed board (element cost reduction) • Investigate balanced LNA approach • Improve station processing bandwidth • Input bandwidth (250 MHz per channel) • Output bandwidth >2x250 MHz • As a fall back current EMBRACE processing hardware will be used • Investigate non-continues Unit/substation approach; • Obtain better EM model of tile to predict radiation pattern including polarisation behavior. • ….

  7. Non-continues substations • XX “tiles” in a substation. • Every substation slightly tilted. • Substation closed by EPS wall en top. • Passive cooling by ground connection through poles. • SKA station formed by multiple substations. • Walkable spaces between substations. • 56m diameter 288.000 antenna elements 7

  8. Design approach level 2 topics Topics to be solved : • Need software development partnership • Need correlator suitable for 15x2x1GS/s inputs • … Can survive with current EMBRACE system in first phase of the project

  9. Project partnerships • Established members: • OPAR, France: Part of system design, beam former chip design, EMBRACE evaluation; • ASTRON, the Netherlands: Part of system design, focus on level 1 front-end topics, industrialisation and EMBRACE evaluation • … • Members (becoming established): • Italy, INAF: Possible topics: Receiver, LO system, … • UK Several Institutes: Antenna design alternatives including electronic integration and testing, Digital processing, … • Germany, MPIfR: Signal distribution and multiplexing, digital processing; • Portugal, Preparation for Portugal station roll out and site development • France, AD converter including poly phase filter bank integration • …

  10. Octa boards Center board Connection boards Aluminum ground plane Current Activities and Progress • First AAmid proto type tile underway

  11. Current Activities and Progress • First AAmid proto type tile underway Bottom view Octa concept

  12. AAmid Octa Concept; 3D bottom view Current Activities and Progress

  13. Improved element mechanics Multiple vivaldiantennas in one sheet Plastic support to keep tops in place LNA close to pick-up point SKA Station Design

  14. Aluminum Large Plates to decrease assembly time Also expandable (connectable) in other direction Metal-Metal joining by clinching SKA Station Design

  15. EM analysis of non-continues substations • XX “tiles” in a substation. • Every substation slightly tilted. • Substation closed by EPS wall en top. • Passive cooling by ground connection through poles. • SKA station formed by multiple substations. • Walkable spaces between substations. • 56m diameter 288.000 antenna elements 15

  16. EM analysis of non-continues substations Vacuum formed “tile” bottom for six modules (approx. 1.5 x 2m) Placement in field by forklift or crane, like LOFAR HBA.

  17. Small tile: Simulate and measure

  18. Good resemblance model and measurements Active reflection coefficients 3 = Central 1 = Edge

  19. Good resemblance model and measurements Measured and simulated phases

  20. Current Activities and Progress • EMBRACE Evaluation and test-bed development

  21. Current Activities and Progress Status Nançay Station • ~ 62 m2 area 56 Tiles • 4032 Vivaldi elements (single linear polarisation) • Currently 48 tiles cabled up end-to-end • Grouped into tilesets of 4 tiles • 64 tiles to be installed by end 2010 • Ultimately, 80 tiles in early 2011

  22. Current Activities and Progress Status Westerbork Station • 64 Tiles, (~70 m^2) • 25 Tiles online in a 3x3 and 4x4 array configuration • Ultimately 144 Tiles (160 m^2) in 2011

  23. Digital beam former details

  24. Modified architecture to more generic one • Full data rate can be exploited: • 2x62 Ebeamlets per CDO output; e.g. two beams of 12 MHz each • Digital beam former software less complex (can use Matrix formalism now) • Increased update rate digital beam weights

  25. Current Activities and Progress EMBRACE station experiment objectives and results • Detection of GPS satellite signals • Scanned Beam Pattern on Afristar • Redundant base line experiments on Afristar • Solar Fringes and system noise verification • Fringes of Cas A and Cygnus • RECENT RESULT: Detection of pulsar Plan • Simultaneous detection of two pulsars within one FoV • Simultaneous detection of two widely separated pulsars using independent FoVs • Detection of HI • Simultaneous detection of HI and pulsars • Beam swapping with beams on Cas A and Cygnus • Correlate with WSRT dish • RECENT RESULT: Detection of pulsar

  26. Drift scan of GPS satellite • Strong carrier at 1227MHz • Subband statistics • Pointing offset between tilesets

  27. Early highlights: solar fringes • Interferometric measurement with 10 tiles • two E-W ULAs • frequency: 1179 MHz • integration: 10 s • bandwidth: 195 kHz • Initial performance est. • A/T = 4.7·10-3 (to sun) • Tsys = 103 – 117 K (to zenith)

  28. Early highlights: instrument quality • Redundant baselines produce redundant visibilities

  29. Scanned Tile Beam pattern measured on Afristar satellite Model Measurement

  30. Fringes of Cas A! • Experimental settings • 3x3 array • 1254 MHz • 30 s integration • 195 kHz bandwidth • Initial conclusions • Confirms A/T • Correlation offsets

  31. Pulsar detection Setup details

  32. EMBRACE first pulsar result

  33. Conclusion • AA-mid is ramping up • EMBRACE Pulsar Detection demonstrates first L-band AA detection ever! It demonstrates: • Complete data path and processing is under control • Hierarchical beam forming is working • and much more to come Thank you

More Related