1 / 8

EENP2 The Europe Egypt Network for Particle Physics WP3 status report

EENP2 The Europe Egypt Network for Particle Physics WP3 status report. Igor Semeniouk LLR, CNRS, Ecole Polytechnique 4th Egyptian School on High Energy Physics 26th April – 5th May 2014 The British University in Egypt and Ain Shams University. 2013 Training.

misu
Download Presentation

EENP2 The Europe Egypt Network for Particle Physics WP3 status report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EENP2 The Europe Egypt Network for Particle Physics WP3 status report Igor Semeniouk LLR, CNRS, Ecole Polytechnique 4th Egyptian School on High Energy Physics 26th April – 5th May 2014 The British University in Egypt and Ain Shams University

  2. 2013 Training • 2 engineers working in LLR and Bari • Basic grid installation • EMI middleware Installation: EMI3 and EPEL,SL6 • YAIM configuration for UI, WN, CREAM, BDII-top, BDII-site, SE_HEAD, SE_DISK • Site Monitoring • Very productive and passed good.

  3. Minimal GRID Site wn NFS /vohomes wn SE_disk wn CE NFS server Improve LRMS stability SE_head (mysql) SiteBDII

  4. Training in LLR • 2 engineers from ASRT work at LLR in Mars – April (additional points on grid and cloud) • In general going will but we have some issue • Certificates problem • LLR starting to move the grid machines to new computing room and run in reduces configuration • LAL also move machines to new building, now access to the Cloud resources • Ne tested installation on DPM and XRD, fix some issues with CE and WN • Mohamed started to for with YAIM playbook (tool for automatic installation of grid machines)

  5. Site at ASRT • The big success of WP3 • We Have first WLCG site installed and registered in GOCDB. • Good work of engineers from ASRT • Now we very close to start installation on other site and add special monitoring and grid submission tools • Basic grid training can be done in Egypt

  6. CMS Tier-N centres • Analyses, MC production, user support • Utilisation local + Common • Nominal T2 : CPU: 0.9MSI2K, Disques: 0.2Po, WAN:>1Gbps

  7. WLCG working group • Good work of engineers from ASRT • We need to create Egyptian WLCG working group with physicists and engineers working on the Grid • Provide requirements to the engineers : cpu, disk, physics channels data for transfers to the site • Communicate with WLCG and CERN experiments • accelerate grid installations • Teaching of young physicians in specific analysis tools

  8. Questions ?