Pertemuan 05 PERALATAN PENGANGKUT

Matakuliah : S0412/ Pemindahan Tanah Mekanis / Alat-Alat Berat Tahun : Pebruari 2006 Versi : 01/00. Pertemuan 05 PERALATAN PENGANGKUT. Learning Outcomes. Pada akhir pertemuan ini, diharapkan mahasiswa akan mampu :

mizell
Download Presentation

Pertemuan 05 PERALATAN PENGANGKUT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Matakuliah : S0412/ Pemindahan Tanah Mekanis / Alat-Alat Berat Tahun : Pebruari 2006 Versi : 01/00 Pertemuan 05PERALATAN PENGANGKUT

  2. Learning Outcomes Pada akhir pertemuan ini, diharapkan mahasiswa akan mampu : • Mahasiswa dapat mengkategorikan alat-alat berat yang digunakan dalam pekerjaan pengangkutan terkait fungsi dan spesifikasinya (C5)

  3. Outline Materi 4.1. Truk 4.2. Dimensi Truk 4.3. Cara Kerja Truk

  4. 4.1. Truk

  5. 4.1. Truk Perhitungan Produksi Dump Truck : Produksi per-jam dari sejumlah dump truck yang bekerja pada pekerjaan yang secara simultan dapat dihitung sbb : C x 60 x Et P = ---------------------- x M Cmt Dimana :

  6. 4.1. Truk Dimana : P = Produksi perjam [m3/jam] C = Produksi persiklus Et = Efisiensi kerja Dump Truck Cmt = Waktu siklus dump truck [ min ] M = Jumlah Dump Truck yang bekerja n = Jumlah siklus dari loader untuk mengisi DT q1 = Kapasitas bucket K = Faktor Bucket Es = Faktor Efisiensi dari loader Cms = Waktu Siklus dari Loader

  7. 4.1. Truk Kombinasi kerja DT dan Loader : C x 60 x Et 60 x q1 x K x Es P = ---------------------- x M = ------------------- Cmt Cms Dalam hal ini, sebaiknya DT dan Loader diguakan bersamaan dalam suatu kombinasi , dimana kapasitas operasinya sama.

  8. 4.1. Truk • Waktu Siklus : • Cmt = n. Cms + D/V1 + t1 + D/v2 + t2 • Wkt. muat + wkt. Angkut + wkt.bongkar muat+wkt. Kembali+ wkt. Muat kembali Dimana : n = C1 / q1 x K n = jumlah siklus yang dibutuhakn loader mengisi DT C1 = Kapasitas rata-rata DT [ m3 cu yd] D = Jarak angkut DT [ m, yd ] V1 = Kec. Rata-rata truck bermuatan [ m/min.yd/min ] V2 = Kec. Rata-rata truck kosong [ m/min.yd/min ] t1 = Waktu buang + waktu std by sp. Pembuangan mulai [ min ] T2 = waktu untuk posisi pengisian dan untuk loader mengisi [min]

  9. 4.2. Dimensi Truk • Pemilihan Dump Truck  disesuaikan dengan loader / pemuat, dengan perbandingan muatan loader dan kapasitas Dump Truck 1 : 4-5 , dimana 1 loader melayani 4-5 dump truck [ mempengaruhi waktu muatan ] • Waktu siklus  • Waktu muat • Waktu Angkut • Waktu Bongkar Muat • Waktu untuk kembali • Waktu mengambil posisi untuk memuat kembali

  10. 4.3. Cara Kerja Truk • Jenis – jenis Dump truck : • Side Dump Truck • Rear Dump Truck • Rear & Side Dump Truck • Syarat utama Dump truck agar bekerja efektif : • Jalan kerja yang keras • Jika pada jalan yang relatif tidak rata dapat didesain khusus “ cross country ability “