110 likes | 122 Views
Detailed discussion on 2015 consolidation activities, power supply requirements, CLOUD project progress, work unit proposals, and future steps.
E N D
IntroductionEast Area meeting 7 May 2015 Lau Gatignon
Outline • Consolidation in 2015 • List of magnets • CLOUD after LS2 • Consolidation Work Unit Proposals • How to go from here • Documentation East Area Consolidation meeting
Consolidation activities in 2015 East Area Consolidation meeting
List of magnets (excl. T11) T11 T10 BN T9 T8 (F61) T8South PSring T8 T11 is listed in separate tables in the document (no ambiguity) East Area Consolidation meeting
POWER SUPPLY REQUIREMENTS PRIMARY BEAMS The rectifiers refer to the old typesand must be replaced East Area Consolidation meeting
Preliminary POWER SUPPLY REQUIREMENTS SECONDARY BEAMS All existing in present T9, T10, T11. Spectrometers (existing!) to be added Detailed attribution remains to be optimised! *) Could be connected in series East Area Consolidation meeting
Nominal Currents East Area Consolidation meeting
CLOUD after LS2 • CLOUD is progressing with the estimate of the cost of moving to the new location (as part of the balance between T11’ and T9B) • In case CLOUD stays in T11, the wall on the T10 side can be modified. East Area Consolidation meeting
Consolidation Work Unit Proposal • Formal procedure for new consolidation activities • This is required to get approval and definition of prioritiesFor 2015 this should be ok as it is in our case • See presentation by S.Evrard East Area Consolidation meeting
How to go from here • All groups to give their comments and corrections to the documentation, as well as revised cost estimates, budget profile and risk analysis asap • CV estimates depend on revised numbers from EPC and MSC for pulsed magnets. East Area Consolidation meeting
Documentation East Area Consolidation meeting