1 / 16

Kriegers Flak and its way to become best practice area EOW 2009 Achim Berge wpd offshore

Kriegers Flak and its way to become best practice area EOW 2009 Achim Berge wpd offshore. ”How to find a common approach in three different countries towards three neighbouring projects, which find themselves in the focus of EU-policies”. Installation of FINO II. wpd at a glance.

montana
Download Presentation

Kriegers Flak and its way to become best practice area EOW 2009 Achim Berge wpd offshore

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kriegers Flak and its way to become best practice area EOW 2009Achim Berge wpd offshore ”How to find a common approach in three different countries towards three neighbouring projects, which find themselves in the focus of EU-policies” Installation of FINO II

  2. wpd at a glance

  3. wpd offshore References HochseeWP Nord - Baltic I, GER Kriegers Flak III, Suurhiekka , FIN see , GER (400 MW) (76 MW) DAN (455 MW) (400-600 MW) He Dreiht , GER Kriegers Flak I, GER Korsn ä s , FIN (595 MW) (329 MW) (600-800 MW) Aiolos , GER Participation in Round Kriegers Flak II, SE (1,050 MW) 3 with JV partner (640 MW) Kaikas , GER Storgrundet , SE (440 MW) (230-265 MW) Notos , GER Finngrunden , SE (250 MW) (1,300 - 1,400 MW) Calvados, F Klockt ä rnan , SE (250 MW) (660 MW) Several projects in Fecamps , F site evaluation/ early (260 MW) development stage Projects X+Y+Z, F (450+250+750MW) Several projects in site Gargano N, IT Gargano S, IT Vend é e , F evaluation (680 MW) (855 MW) (600MW) 5 projects with a total capacity of 7 projects with a total capacity of ~ 4,500 MW ~ 2,040 MW permitted and sold (net) in advanced permission process 10 projects with a total capacity of Several projects under site evaluation ~ 5,000 MW (net) in early permission stage wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  4. Kriegers Flak AreaBaltic1 + Kriegers Flak I+II+III =21+80+128+91 = 320 WTG(up to 1600 MW) together Europes largest advanced project area in terms of area, turbines and capacity developed by wpd since 2001 wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  5. Kriegers Flak development

  6. Motives & Challenges for Kriegers Flak development Motives • One of the biggest potential areas in the Baltic Sea • Few environmental issues • High wind speed above 9,5 m/s • Strategic interesting location along big transmission needs Challenges • Sea bed conditions • Far offshore – potentially high connection costs Investigations at Kriegers Flak wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  7. Kriegers Flak Interconnector • Basic idea: replacing three independent grid connections by one common solution including HVDC technology • 2003: wpd and NVE starts studies on interconnector between Germany and Sweden • 2005: wpd integrates interconnector as possible grid connection in the application of Kriegers Flak II • 2006: Vattenfall AB starts working group on the Interconnector (”Baltic Wind Link”) • 2007: Vattenfall Europe Transmission GmbH includes the Interconnector as potential solution for Kriegers Flak I • 2009: TSO ”Joint Pre-feasibility Study”, TSO application for 150 M€ EU grant map wpd study 2003 map TSO study 2009 wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  8. Motives for Kriegers Flak Interconnector Motives • Socio-economic benefit up to 100€ Mio/year • HVDC technology means less energy losses and higher capacity • Multiple connections lower the project operator’s risk of business interruption Graph from the TSO Joint Pre-feasibilty Study, presentation at EWEC March 2009 wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  9. Challenges for Kriegers Flak Interconnector • Three different national laws on transmission networks • The three different wind farm owners might have different interests • Involvement of EU could add more complexity than support • National consumer interests could become a hurdle Grid North West Europe, Svenska Kraftnät 2008 wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  10. Governmental initiatives regardingKriegers Flak • EOW December 2007: Joint declaration of ministers from Denmark, Germany and Sweden on cooperation regarding Kriegers Flak (ending up in the Nordwind project) • September 2008: EU-coordinator Adamowitsch identifies Kriegers Flak as ”best practise case” and ask for an ”European vision not accepting cheap national solutions” • January 2009: EU Recovery Plan includes proposal of 150 € Mio grant for grid connection Kriegers Flak • June 2009: EU Strategy for the Baltic Sea Region – Action Plan highlights Kriegers Flak as ”demonstration of coordinated offshore wind farm connection solutions” wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  11. Motives for governmental initiatives • Baltic Sea riparian countries already agreed on close cooperation in the Helsinki Convention (featuring HELCOM). • Kriegers Flak as lighthouse project for the benefit of the citizens and the environment • National interests might be taken care of in the best way by mutual cooperation wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  12. Preconditions for successful joint cooperation between stakeholders at Kriegers Flak • Focus on the needs of the project owners and operators because: • The wind projects are the key of the area’s development • Grid connection is the key for the wind projects’ realisation • Project owners are in charge of the projects’ timetable • Project owners are in possesion of all site related data • Project owners have ressources to be allocated with short notice • Project owners and operators need to participate in the economic benefit of joint cooperation because: • Project owners have taken the development risk • Most of the projects are still not profitable • Certain conditions (e.g. sea bed) require more ressources wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  13. How to structure further development of the interconnector and other joint efforts? • For the time being, at least five parallel working groups are discussing Kriegers Flak • Instead ONE working group with 10 members should head further development: • 3 project owners/developers • 3 TSOs • 3 governments • 1 EU representive • Sub-groups are necessary, but should be supervised by the overall working group • Initiative for restructering the work should come from the EU level • Kriegers Flak needs to have high priority at all involved organisations and levels wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  14. How to deal with three legal regimes? • Under the existing three legal regimes an interconnector is not realistic • The existing rules are the result of energy politics with clear national interests in mind • Examples for legal hurdles: • Ownership rules for transmission cables under Swedish law • Rules on grid connection of electricity under Danish law • Special rules for grid connection and sale of wind power under German law • Harmonisation is needed – but is harmonisation also wanted? wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  15. Kriegers Flak is the European Union’s idea in a nutshell • Cooperation and trade with neighboring countries gives benefits to the customers seen from a European perspective • Harmonisation of legal rules is necessary • Public and private sector have to work together • Climate change and new jobs are the major drivers European Parliament Colleagues from Deutsche Windtechnik at Thornton Banks (B), July 2008 wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

  16. Contact Achim Berge Managing Director wpd offshore GmbH Kurfürstenallee 23a DE 28211 Bremen +49 421 168 66 10 a.berge@wpd.de wpd offshore GmbH EOW 2009, 14-16 September, Stockholm

More Related