PROJECT MANAGEMENT. CPM/PERT The Mountain Group. Objectives. Describe how CPM/PERT have developed and merged together to provide a useful technique for managing projects. Gain a better understanding of simple CPM/PERT diagrams and calculations.

more
Download Presentation

PROJECT MANAGEMENT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROJECT MANAGEMENT CPM/PERT The Mountain Group

  2. Objectives • Describe how CPM/PERT have developed and merged together to provide a useful technique for managing projects. • Gain a better understanding of simple CPM/PERT diagrams and calculations. • To be able to use POM for Windows, for quicker more accurate calculations.

  3. History • Developed in 1950’s • CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile

  4. CPM - Critical Path Method • Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction • Single estimate of activity time • Deterministic activity times

  5. PERT - Project Evaluation & Review Techniques • Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction • Multiple time estimates • Probabilistic activity times

  6. CPM/PERT • Overtime CPM and PERT became one technique • ADVANTAGES: • precedence relationships • large projects • more efficient

  7. The Project Network • Use of nodes and arrows • Arrows  • An arrow leads from tail to head directionally • Nodes  • A node is represented by a circle

  8. Activity on Node A completion of an activity is represented by a node Arrows represent order of events Activity on Arrow An arrow represents a task, while a node is the completion of a task Activity on Node & Activity on Arrow

  9. Dummy Activity • Shows precedence relationships • represented by dashed arrows • no passage of time

  10. Constructing a Network • Diagram on page 817 of the text

  11. Critical Path • Longest path through a network • minimum project completion time

  12. Earliest start time Earliest finish time Formulas Latest start time Latest finish time Formulas Activity Scheduling

  13. Activity Slack • Definition: Slack is the amount of time an activity can be delayed without delaying the project • Formula

  14. Benefits of CPM/PERT • Useful at many stages of project management • Mathematically simple • Give critical path and slack time • Provide project documentation • Useful in monitoring costs

  15. Limitations to CPM/PERT • Clearly defined, independent and stable activities • Specified precedence relationships • Subjective time estimates • Over emphasis on critical paths

  16. Questions Answered by CPM & PERT • Completion date? • On Schedule? • Within Budget? • Critical Activities? • How can the project be finished early at the least cost?

  17. ANY QUESTIONS???