Integration of Software Cost Estimates Across COCOMO, SEER-SEM, and PRICE-S models

Integration of Software Cost Estimates Across COCOMO, SEER-SEM, and PRICE-S models. Tom Harwick, Engineering Specialist Northrop Grumman Corporation Integrated Systems October 26-29, 2004. 19th International Forum on COCOMO and Software Cost Modeling. Outline.

Download Presentation

Integration of Software Cost Estimates Across COCOMO, SEER-SEM, and PRICE-S models

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integration of Software Cost EstimatesAcross COCOMO, SEER-SEM, and PRICE-S models Tom Harwick, Engineering Specialist Northrop Grumman Corporation Integrated Systems October 26-29, 2004 19th International Forum on COCOMO and Software Cost Modeling

  2. 19th International Forum on COCOMO and Software Cost Modeling Outline • Need for Inter-Model Estimate Integration • Model Analysis • Model Comparisons & Sensitivity Analysis • Economic Properties • Baseline Example • COCOMO • SEER-SEM • PRICE-S • Summary 19th International Forum on COCOMO and Software Cost Modeling

  3. 19th International Forum on COCOMO and Software Cost Modeling Need for Inter-Model Estimate Integration • Communication of overall Software Cost Estimate to the Customer • Minimize Program Cost Risk • Integration of Software Estimates Across Vendors • Various Software Cost Models • Sizing Definitions • Selection of Cost Driver Settings • Vendors have different Statement Of Work (SOW) 19th International Forum on COCOMO and Software Cost Modeling

  4. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis • Approach • Understand Properties of Each Cost Model • Sizing and Sizing Normalization • Productivity Cost Drivers • Team & Process • Market – Customer(s) • Complexity, Operating Environment • Model Scope Differences 19th International Forum on COCOMO and Software Cost Modeling

  5. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Cost Drivers by Cost Model 19th International Forum on COCOMO and Software Cost Modeling

  6. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Concept of “Ceterus Parabus” Methodology to Extract Cost Driver Information Cost Slope = delta Cost/delta (Analyst Experience) Range = Cost/(Analyst Experience) Parameter (e.g. Analyst Experience) Other parameters held constant 19th International Forum on COCOMO and Software Cost Modeling

  7. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Major COCOMO Cost Drivers 19th International Forum on COCOMO and Software Cost Modeling

  8. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Major SEER-SEM Cost Drivers 19th International Forum on COCOMO and Software Cost Modeling

  9. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Major PRICE-S Cost Drivers 19th International Forum on COCOMO and Software Cost Modeling

  10. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Team & Process 19th International Forum on COCOMO and Software Cost Modeling

  11. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Market 19th International Forum on COCOMO and Software Cost Modeling

  12. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Complexity 19th International Forum on COCOMO and Software Cost Modeling

  13. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Scope Did not find many data points in the COCOMO I database that suggest a System Integration on the scale of our (next) Baseline example (3-4 Million SLOCs). Has COCOMO II been able to collect sufficient data to develop a (large scale) System Integration factor? 19th International Forum on COCOMO and Software Cost Modeling

  14. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Economic Properties(Models Exponents Indicate Diseconomies of Scale for Large Projects) 19th International Forum on COCOMO and Software Cost Modeling

  15. 19th International Forum on COCOMO and Software Cost Modeling Model Analysis - Economic Properties All Software Cost Models show a Schedule Compression penalty. 19th International Forum on COCOMO and Software Cost Modeling

  16. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example • Illustrate Software Cost Estimation & Integration • Baseline • SEER-SEM – Sensor Software • PRICE-S – Air Vehicle Software • COCOMO – Control Station • Sizing Assumptions and Scenarios • Equivalent New SLOC • Productivity Range • Hours/ SLOC • Estimating Ranges using Monte Carlo • Hours = (SLOC) X (Hours/SLOC) 19th International Forum on COCOMO and Software Cost Modeling

  17. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example - Sizing Scenarios (Equivalent New SLOC) 19th International Forum on COCOMO and Software Cost Modeling

  18. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example – Productivity Ranges- Productivity (Hours/SLOC) COCOMO Assumptions: 19th International Forum on COCOMO and Software Cost Modeling

  19. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example – Results 19th International Forum on COCOMO and Software Cost Modeling

  20. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example – Air Vehicle, Hours = (Hours/SLOC) X SLOC 19th International Forum on COCOMO and Software Cost Modeling

  21. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example – Sensor, Hours = (Hours/SLOC) X SLOC 19th International Forum on COCOMO and Software Cost Modeling

  22. 19th International Forum on COCOMO and Software Cost Modeling Baseline Example–Control Station,Hours=(Hours/SLOC)X SLOC 19th International Forum on COCOMO and Software Cost Modeling

  23. 19th International Forum on COCOMO and Software Cost Modeling Summary • Identified Major “local domain” Cost Drivers • COCOMO II, SEER-SEM, PRICE-S • Examined Economic Properties • Diseconomies of Scale, Schedule Compression • Productivity Ranges • Scenario Analysis using top 2-3 Cost Drivers • Illustrated Software Cost Estimation & Integration • Model Integration using Monte Carlo Probability Curves • Scenarios for Sizing • Model Output for Productivity 19th International Forum on COCOMO and Software Cost Modeling

  24. 19th International Forum on COCOMO and Software Cost Modeling Object Oriented Analysis (OOA) • OOA • Unified Modeling Language (UML) • Several Standard Diagrams • Starts with “Use Case” (users view of the world) • Develops charts including: • Use Case (Actors use of information in the system) • Collaboration Diagrams (provide details of each Use Case) • Class Diagram • Specify Blueprints (for objects) • Attributes and Methods • Relationship between Classes • Objects are linked across a design • Object Interfaces • Encapsulates Local Variables within a “Black Box” • Inheritance of Classes 19th International Forum on COCOMO and Software Cost Modeling

  25. 19th International Forum on COCOMO and Software Cost Modeling Snapshot of Unified Modeling Language (UML)– From Use Case, Flow of Information, to Class Diagrams of Systems 19th International Forum on COCOMO and Software Cost Modeling

  26. 19th International Forum on COCOMO and Software Cost Modeling Object Oriented Analysis (OOA) Benefits • Object Oriented Analysis with Unified Modeling Language • Overall Project Cost Savings • Similar to System Engineering impact: • Mitigate Risk, Cost, Schedule Impacts • Decreases Defects • May increase Design work • But Avoids excessive re-work • Facilitates Integrate and Test • Better designed Interfaces • Promotes System Integration • If compatible UML used on all vendor designs • Helps Customer Understand Product Purchased • Sooner, Decrease Requirements Volatility • Need Data to Measure impact of OOA (UML) 19th International Forum on COCOMO and Software Cost Modeling

  27. 19th International Forum on COCOMO and Software Cost Modeling References • Models: • Price Systems, PRICE-S model, Los Angeles, California, 1996. • Galorath Associates, SEER-SEM, Los Angeles, California, 1996. • USC Associates, COCOMO II.1999, Los Angeles, California, 2004. • Books: • 1. Boehm, Reifer, et al., Software Cost Estimation with COCOMO II, Prentice-Hall, New Jersey, 2000. • 2. Boehm, Barry W., Software Engineering Economics, Prentice-Hall, New Jersey, 1981. • 3. Deming, W. Edward, Out of the Crisis, Massachusetts Institute of Technology, Cambridge, 1982. • 4. Cs3 Inc., Objected Oriented Analysis Using the Unified Modeling Language, (UML), Los Angeles, CA, 2000-2003. 19th International Forum on COCOMO and Software Cost Modeling