The Yakima Air Terminal has received an $11,000,000 grant. The grant is to: • Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways; • Resurface airfield pavement between the north taxiway edge line to the non-movement line; • Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator; • Replace all existing directional and hold short signs; and • Correct several markings not meeting FAA standards. Project Overview
Expected construction START DATE September 8, 2014: • Phase 1: September 8, 2014 – October 3, 2014 • Phase 2: October 4, 2014 – October 17, 2014 • Phase 3: October 18, 2014 – October 31, 2014 • Inclement Weather Shutdown • Phase 4: April 20, 2015 – May 10, 2015 • Phase 5: May 11, 2015 – May 31, 2015 • Phase 6 / 7: June 1, 2015 – June 30, 2015 Project Schedule
Phase 1: September 8, 2014 – October 3, 2014 • Ramp Closures. • McCormick West, and Plath Hangar. • Partial Ramp Closures. • Fuel Tank/House and McCormick Air Center. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 2: October 4, 2014 – October 17, 2014 • Ramp Closures. • Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building. • Partial Ramp Closures. • McCormick Air Center and Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 3: October 18, 2014 – October 31, 2014 • Ramp Closures. • GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp. • Partial Ramp Closures. • Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 4: April 20, 2015 – May 10, 2015 • Ramp Closures. • East Terminal Apron Ramp. • Partial Ramp Closures. • East Itinerant Ramp. • Runway 4/22 and Bravo Taxiway Closed. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 5: May 11, 2015 – May 31, 2015 • Ramp Closures. • No Ramps Closed. • Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 6: June 1, 2015 – June 30, 2015 • Partial Ramp closures denoted by barricades. • Runway 4/22 closed intermittently. • On-going construction activity and vehicle traffic on service roads and taxiways. Impacts
Phase 7: June 1, 2015 – June 30, 2015 • Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
If at all possible, avoid construction areas. • Please plan all operations around construction to the maximum extent possible. • If there are known operations that will be impacted by the proposed schedule, please let us know. • The Airport Management will provide NOTAMs. • Do not travel (plane or car) across barricades delineating closed pavement. • Do not provide direction to the contractor unless there is an emergency. Operations During Construction