1 / 16

Waste Update

Waste Update. Rail Environment Infrastructure Presentation Thursday 15th August 2013. About me. Waste Management Consultant for over 5 years Worked on a number of rail SWMP’s: Crossrail – Tottenham Court Road, Custom House & Woolwich North East Crossrail Acton Diveunder

moya
Download Presentation

Waste Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Waste Update Rail Environment Infrastructure Presentation Thursday 15th August 2013

  2. About me... • Waste Management Consultant for over 5 years • Worked on a number of rail SWMP’s: • Crossrail – Tottenham Court Road, Custom House & Woolwich • North East Crossrail • Acton Diveunder • Western Track Lowering • Reading Viaduct • LUL Projects • Pre demolition audits • Operational waste management strategies • Project work & secondment to the Environment Agency

  3. Introduction • Waste Management Plan for England 2013 • edoc • Status of devolved government SWMP’s • Bad practise • Good practise • Summary

  4. WasteManagement Plan for England 2013 • The Waste Management Plan for England is a high level document which is non – site specific. • It provides an analysis of the current waste management situation in England, and evaluates how it will support implementation of the objectives and provisions of the revised WFD. • The Plan does not introduce new waste management measures

  5. edoc • What • Will offer an alternative to paper-based system of WTN’s • Modernising waste data collection in the UK • Enhance ability to extract good quality data • Why • Storage & accurate data monitoring • Who • Any UK business involved in waste management • When • Due to be rolled out from January 2014

  6. SWMPs in England • The original red tape challenge concluded that SWMP Regulations should be scrapped • The date set for this is October 2013 (shown in a report from September 2012) • There was then a consultation to understand what the impacts will be if/when the regulations are removed • So...

  7. SWMP in Wales • Draft regulations indicate that: • No financial limit for requiring SWMP • Must be sent to relevant enforcement authority • Fees paid – value not yet determined • Councils MUST enforce the regulations • Subject to outcomes of consultation, SWMP regulations will be laid in 2014 and come into force in 2015

  8. SWMPs in Scotland & Northern Ireland • The Scottish Government have committed to a zero waste to landfill target by 2020 • The Department of the Environment Northern Ireland (DOENI) consulted on SWMP proposals in 2011 • Still no legal requirement to produce a SWMP • SWMP a useful management tool to cut • costs, reduce fly-tipping and demonstrate • your duty of care for waste

  9. Halving Waste To Landfill • Commitment launched in 2008 and completed at the end of 2012 • Over 800 companies made the commitment to reduce waste • Construction and demolition waste was reduced • Excavation waste has seen a sharp increase

  10. Bad Practise • Not recording Designing out Waste actions • Providing data in the wrong format – m or m2 of material • Using the wrong LOW/EWC codes • Not providing full details of waste carriers or waste management facilities

  11. Waste Crime • Waste operators fined for illegal asbestos storage • £80,397 • Wood recycler fined for storage permit breach • £51,500 • Prison sentence for illegal waste site owner • Suspended eight month prison sentence and 180 hours unpaid work  • Man fined for illegal waste activities •  £80,000 • Countrystylefined for waste offences •  £46,000

  12. Designing Out Waste • Focus on the first stage that waste can be reduced • Responsibility to reduce waste ultimately lies with the client to set targets and push the design team • Considering waste at design stage saves money at least twice over

  13. Design Principles • 1. Design for Reuse & Recovery • 2. Design for Off-Site Construction • 3. Design for Materials Optimisation • 4. Design for Waste Efficient Procurement • 5. Design for Deconstruction & Flexibility

  14. Good Practise • Orient Way - Reuse & Recovery • £15 million rail sidings project in East London • Layout design enabled a high rate of re-use • 1,000 tonnes of crushed concrete was reused on site • 20,000 tonnes of ballast reused • 3,250 yards of track was reused • Award from CEEQUAL for overall recycling rate of 99%

  15. Good Practise • Bond Street Monitoring - Waste Efficient Procurement • Installation of equipment in and around the station to monitor any ground movement caused by new work at the station • Company providing equipment remove long haul packaging and reuse at their depot • Packaging taken to site is returned to depot for reuse

  16. Summary • Waste Management Plan for England 2013 - does not introduce new waste management measures " lacking ambition“ • edoc – to be used by any UK business involved in waste management from January 2014 to replace paper based WTN’s • Status of devolved government SWMP’s – England: requirement to be removed; Wales requirement to be put in place; Scotland and Northern Ireland still no requirement • Bad practise • Good practise

More Related