PFRA reporting – Output from 2. test phase FD Drafting Group, Meeting 15-16 June 2011 Mette Wolstrup
Revisedstructure - a quick go through
Test phase – kick off • Email sent to MS 12.05.2011 - 4 weeks testing • Volunteer MS: AT, CZ, ES, FI, IE, PL, SE, UK
Tools and documents to be tested • Database/schemas • Database to xml conversion tool • Desktop validation tool • User Manual, v3.0 • User Guide to the reporting schema v3.0 • User Guide to reporting spatial data v3.0 • Stylesheets • Upload in cdrtest and QA's • Ressource page: http://icm.eionet.europa.eu/schemas/dir200760ec/resources/
Clarification questions • Variousclarificationquestionsonhow to interpretdifferent elements in the schema • FI: How to reportifno events in UOM?
Database • UK: Re-introduction of the asterix (*) • AT: Incorrect annotation text • IE, ES: Redundant data in database
PFRA Schema • UK: Should have a default value under each type of potential consequences. • UK/PL: How to use the two elements 'CrossBorderRelationship' and 'CrossBorderFloodLocationCode' • ES: EUSurfaceWaterBodyCode? • FI: Name of flood location shouldbeadded
PFRA Schema (2) • UK: Type of floodsontwolevels? • AT/PL: How to useflood location? • PL: Currency of damageestimates? • FI: Degree to beremoved from - Degree_TotalDamage • - Degree_TotalDamageGDP • - Degree_TotalDamageClass
APSFR • UK: Change annotation text in element 'SummaryofCoordination'? CONDITIONAL. To be provided if article 4 and/or 13.1.a have been applied and if APSFR is part of a international APSFR. Optional for article 13.1.b. Description (less than 5,000 characters) of international coordination that has taken place between relevant MSs within international RBDs or international units of management
Database to xml conversion tool AT/UK/PL: All experienced problems with the DB to xml conversion – ghost tags and mapping levels – Atkins to correct the conversion tool.
Upload files in test environment,QA's, factsheets FI: No errors in the upload work flow FI/UK: Some incorrect complex validations – will be corrected by Atkins UK: Factsheet - Suggestion to have flood type/consequence names instead of codes
Ressource page http://icm.eionet.europa.eu/schemas/dir200760ec/resources/ SE: Missing links (corrected) UK: Various comments on all 3 guidance documents – will be incorporated.
Timetable 1. and 2. test phase closed Release of final schemas and tools – 1 July 2011(tentative) 22.12.2011: Deadline for finalising PFRA 22.3.2012: Deadline for reporting PFRA
Thank you Mette Wolstrup GIS & ITATKINSArne Jacobsens Allé 17, 2300 Copenhagen S, Denmark | Tel: +45 5251 9000 | Fax: +45 5251 9001 | Direct line: +45 5251 9110 | Mobile: +45 2711 1295Email: Henrik.Kaltoft@atkinsglobal.com | Web: www.atkins.dk