Introduction and News

Introduction and News. Karl Gill. Introduction. Today’s agenda N ews AOB Hypernews , Calendar 2012. Today’s agenda. Reports recent developments throughout the project. News. A few p oints not covered elsewhere in the meeting Phase 1 MB Decisions taken so far in 2012 TDR Cost book

munin
Download Presentation

Introduction and News

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction and News Karl Gill

  2. Introduction • Today’s agenda • News • AOB • Hypernews, Calendar 2012

  3. Today’s agenda • Reports recent developments throughout the project

  4. News • A few points not covered elsewhere in the meeting • Phase 1 MB Decisions taken so far in 2012 • TDR • Cost book • Planning and schedule

  5. News: Phase 1 MB • (Phase 1 MB members in spare slide) • Main points since last CMS upgrade week. • Proposed a TDR outline, chapter editors (backup slide) • agreed to aim for a first draft by end 2011. • Reviewed the cost book • Provided a draft sharing between agencies and spending profile to October RRB • https://indico.cern.ch/conferenceDisplay.py?confId=149413 • figures for contributions a mix of target/proposed/confirmed funds • Endorsed the project to install a “pilot blade system” in LS1 • With Karl Ecklund as overall responsible and Simon Kwan coordinating hardware and integration in FPIX • Agreed on target for installation ahead of LS2 in an extended winter stop • Agreed on strategy for ROC developments for 2016 detector • Ongoing discussion on what is the best upgrade path beyond the initial Phase 1 detector • Several points to settle before the TDR • Strategy for FED upgrades, power supply replacements, scope of pre-installation tests • Identified parts that could be purchased with the first funds • e.g. sensors, optical link parts • Welcomed Finland and France as full members of the project

  6. News: New partners • Finland • L3 half barrel with CERN and Taiwan • Aiming to make bump-bonding with VTTas commercial partner • France • Contribute to the CO2 cooling • Also interest and experience in DAQ, backend electronics • Also, UK working on a phase 1 proposal • Particular interest in DAQ

  7. News: Costs and Sharing • Pixel phase 1 cost estimate made already in 2010 • Envelope remains fixed for time-being at 17.4MCHF • Salvatore Costa maintains trace of costs in the ‘cost book’ • Spreadsheet list of main parts and main sub-parts • Figures based on quotes or input from experts • Sharing and spending profile included • Working with agency representatives in Phase 1 MB to match costs and sharing with the proposed financial contributions • Aiming to be finalized and published in the TDR. • Chapter drafted

  8. News: Schedule and Planning • A first CMS-wide Phase 1 plan is an objective for this week • We have our draft plan targeting 2016/17 installation

  9. Schedule and Planning (cont.) • Work-breakdown • List of main tasks has been drafted by Aaron Dominguez and Phase 1 Coordinators • One of our objectives this week is to progress further on this • Next steps: • Review/re-iterate milestone plan and main tasks • Include resources and tracking • Link with cost book and spending profile • Formal review, along with the TDR

  10. News: TDR situation • First chapter outlines received and collated • Identified overlaps etc. and points we would like to consider adding • Outline is in DocDB: • https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=5669 • Your feedback is very welcome

  11. AOB Hypernews CMS and TK Calendar 2012

  12. Hypernews • Two new hypernews were created for Phase 1 • Pixels Phase 1 Upgrade • Pixels Phase 1 Upgrade Module • Also working on improving communication via TK web pages as part of wider refurbishment of CMS web pages. • Again, your feedback is very welcome

  13. AOB: Regular Meetings and Calendar 2012 Meet outside CERN TBC (Grindelwald?) https://cms-docdb.cern.ch/cgi-bin/DocDB/ShowDocument?docid=3046

  14. Spare Phase 1 MB members/contacts

  15. Phase 1 MB Membership • Chair/Project Leader: R. Horisberger • Austria: Josef Hrubec • CERN: DuccioAbbaneo • Finland: Paula Eerola • France: Didier Contardo • Germany BMBF: Lutz Feld • Germany DESY: GuenterEckerlin • Italy: Gian-Mario Bilei • Switz. – ETHZ: Rainer Wallny • Switz. – PSI: Roland Horisberger • Taiwan: George W.-S. Hou • UK: Geoff Hall (observer) • USA - NSF: Will Johns • USA – DOE: DaniellaBortoletto • USA – other programmes: Alice Bean. • Ex-officio members: • FPIX coordinator: Simon Kwan • BPIX coordinator: Wolfram Erdmann • CSI coordinator: Nicola Bacchetta • TK PM: Karl Gill • TK dep PM: Frank Hartmann • TK dep PM: Aaron Dominguez • TK Res. Manager: Salvatore Costa • TK TIB chair: Didier Contardo • CMS Tech Coordinator: Austin Ball KG, FH, AD: Phase 1 MB #2