Chilled Engineering Systems “Helping You Be Cool”. Ice Pond Refrigeration System. Derek Britten Roger Connolly Ben Francis Adam Trudeau Steve Vines. Final Presentation to the Mechanical Engineering Faculty, Students, Clients and Guests April 7, 2005. CO 2 Emissions Reductions.
E N D
Chilled Engineering Systems“Helping You Be Cool” Ice Pond Refrigeration System Derek Britten Roger Connolly Ben Francis Adam Trudeau Steve Vines Final Presentation to the Mechanical Engineering Faculty, Students, Clients and Guests April 7, 2005
CO2 Emissions Reductions • 2002 world FF emissions • 24.5 billion metric tonnes • 0.703 kg of CO2 emitted per KWh of energy produced • Environmental stewardship • “One Tonne Challenge” www.ge-at.iastate.edu
System Overview • Evaluate the effectiveness of an ice pond system • Under development in Norway, Japan • Potential to save energy and lower emissions • Kyoto Protocol • System was created to compare results to vapor compression system
Ice Reservoir Heat Exchanger & Support Reservoir Cover Fan Coil Unit (FCU) System Components
Selected Pond • 12 foot diameter • 3 feet high • 8 tonnes of ice • Double liner • Water tight vinyl • Protective tarp
Selected HX Support • 1” x 4” wood planks • 2” x 4” wood spacers • ¼” steel flat bars • Ice block support
Selected Heat Exchanger • 1” M copper piping • 6” pipe spacing • Length = 51.7m • 20% PG mix
FCU SelectionSystem Balancing • Load Selection • Cooling Load: 12000Btu/hr per 500ft2(USDOE 2004) • ½ HVAC Lab ≈ 300ft2 2110W • Qin = 2000W • Trane FCU vs. CES HX
FCU SelectionModel Chosen 4 pass, 2 row horizontal FCU
Ice Pond Cover • Design: • Self weight • 1.8kPa snow load • Result: • No significant snow accumulation • Withstood all environmental conditions
Insulation • Heat transfer major concern • Ice preservation during summer • All reservoir components will be insulated • Sub-floor • Reservoir wall • Protective cover • Pipes and hoses
Ice Making • Began Feb. 17 • Delayed due to warm temps - highs of 7°C • Slow initial production rates
Ice farms employed Feb. 21 – Production rate increased 2 - 3x Ice making completed in two weeks Ice Making
Finished Product • Core sample showing layers
Measurements • ΔT across pool inlet and outlet • ΔT across FCU inlet and outlet • Control volume temperature • Power consumed by system Q = mcpΔT
Measurements • 10 thermocouples located throughout system
Closed Loop Testing • 3 short 2 hour tests • One 24 hour test • Test with maximum flow rate = 2.3gpm & 2100W heat input
Closed Loop Testing • 24 hours • Average FCU cooling rate = 1660W • Average pool cooling rate = 1989W • Average COP = 7.22 • Average system efficiency = 83.68% • Estimated 400 kg of ice melted • Average control volume temp = 20.94°C
Open Loop • Converted system to open loop – bypassed heat exchanger due to mild temperatures • Compare systems • Flow rate increased • 2.9gpm • Less head loss • Less viscous
Open Loop Testing • Same 2 hour tests as closed loop • One 2 hour test at maximum flow rate • One 24 hour test • Test with maximum flow rate = 2.9gpm & 2500W heat input
Open Loop Testing • 24 hours • Average FCU cooling rate = 2264W • Average pool cooling rate = 2892W • Average COP = 9.84 • Average system efficiency = 78.45% • Estimated 815 kg of ice melted • Average control volume temp = 19.35°C
Conclusions • All tests had a COP > 5 • Little to no transient operating zone – reached steady state quickly • More melt water = less performance • Open loop is better than closed loop • ΔT between working fluid and air • Mass flow rate • Cp of working fluid Q = mcpΔT
Conclusions • Need a powerful system for low temperatures • No energy consumed for ice making • System efficiency high because of cool ambient temperatures during testing
Budget Estimated Budget: $5000.00 Actual Costs
CO2 Emissions Reductions • Environmental stewardship • “One Tonne Challenge” • OUR SYSTEM • Reduced by 3x! www.ge-at.iastate.edu
Recommendations • Full scale model • Melt water • No heat exchanger • Increase space between pool inlet & outlet • Colder outlet temperatures • Higher flow rates • Turbulent instead of laminar flow • Increases rate of heat transfer • More durable reservoir • Not dependent on vinyl liner • Automated ice making system
Special Thanks To: • Mr. Richard Rachals • Dr. Murat Koksal • Albert Murphy • Greg Jollimore • Dr. Peter Allen • Import Tool Corporation • Jeff MacNeil of Trane • Mike Trudeau of HCDJ