A New Building Data Center Upgrade capacity and technology step. 2011 – May t he 4 th – Hepix spring meeting Darmstadt (de) Pascal Trouvé (Facility Manager CC IN2P3). Summary :. Latest improvements of the current computing room New computing room - Project scope
E N D
A New Building Data Center Upgrade capacity and technology step 2011 – May the 4 th– Hepix spring meeting Darmstadt (de) Pascal Trouvé (Facility Manager CC IN2P3)
Summary : • Latest improvements of the current computing room • New computing room - Project scope • New Building – New architecture • Technical commissioning • Virtual tour • Technical data & figures • On going projects • Technical infrastructures phase II • Electrical power supply challenge • Future development project Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Latest improvements of the computing room • POWER • New transformers have been installed (01/2010) : 3 X 1 MVA • Diesel generator (1.1 MVA) • Second electrical low voltage master distribution panel installed (one dedicated for Operation power [racks and cooling], one dedicated to infrastructure power) • Reactive energy compensation panel ( 4 capacitors banks) - savings • 4 Power distribution panels replaced + Source Transfer Switch for critical Network racks installed • News batteries farm – sealed lead battery – cell watch system Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011v
Last improvements of the computing room • COOLING : • A third cooling unit (600 kW) has been installed on roof top,1800 kW available • Cooling capacity is now maximum complying with environmental regulation • HAZARDS • News fire safety detection system and monitoring ( SSI/CMSI) • New extinguishers fleet and reviewed lay out • INFRASTRUCTURE • High density confined racks standardization • InRow air-conditioning racks • PDUs suited to equipment specifications, and monitored Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
IMPROVMENT INPUTS • POWER • No power distribution problems occurred over the last year • Better batteries back up capacity coupled with the GE • COOLING • Still not fully redundant (short of 1600 kW) on the existing computing room • No cooling issues over the last summer, redundancy will be reached with the new computing room commissioning • HAZARDS • Better fire safety with modern fire detection system • Decrease of battery’s Hydrogen Hazard with sealed technology • INFRASTRUCTURE • Better global efficiency and sustainability • Higher general density Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Power exemplification New aeros on roof top 2 New chillers unit Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Confinement and Water cooled racks confinement All the new hardware is installed in “confined racks”, including disks InRaws cooled racks Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Project scope New computing room • The identified needs : • ~ 60 users groups increased demand • Meet LHC’s requirements • To meet the planned upgrade of LHC • Important identified request for « astroparticules” research activity Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Project scope - Evolution plan – new Target plan: 2011 50 racks 0.6 MW 2015 125 racks 1.5 MW 2019 216 racks 3.2 MW Total power 3 MW Total power 6 MW Total power 9 MW The new computing room is an extension of the existing computing room (3 MW power + cooling in 2011) Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
A careful hardware selection DELL 1U 1950b 3 GHz 16 GB Blades DELL E5540 (2.53 Ghz) 48 GB IBM iDataplex Intel 5430 LV – 2.66 GHz – 50 W 16 GB Dell C6100 X5650 – 2.66 GHz 72 GB Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
New Building – New architecture Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011
Chilled water tank 30 m3 Chillerunits Special construction design – heavy load roof structure Cold Water pumps stations Heavy duty Elevator 3 tons load Dominique Boutigny
Infrastructure design scope Fully confined architecture All the water pipes, electrical distribution and other services are routed from the ceiling Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmsatdt - Mai 4 th 2011
New computing room • 3 levels of 850 Sq. Meters each [ machine room for 850 sq. meters and 2 technical levels including the roof top] + heavy load elevator • We adopted a simplified “Design and build procedure” (single company contracted) delivered the building within18 months • Due to budget constraints the new computer room start with a limited technical infrastructure, but has a modular design that allowed scalable upgrades • First years, room dedicated to worker nodes only • Chilled water and electricity distribution and back up, technical rooms are designed for the 2019 target value Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011
The New Data Center Building Setting up of a new building live ! • 12 months construction work • >= 630 tons of concrete • >= 70 tons of steel framework Building work started end of April 2010 Targeted delivery date targeted February 1st 2011 Final delivery date : March 14 th 2011 Technical commissioning : undergoing Go live production ~ Mai 24 th 2011 Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Virtual Tour Computing room phase I 24 APC racks : InRaw 20 KW each Confined + workers + 2 Penduit racks with Nexus + switch Cisco To be completed by end of year : 26 APC racks InRaw 20 KW and fully confined area Still 600 sqr meters available …… Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Technical equipment and installation on roof top • 2 Chillers units 800 KW each • Chilled water tank 30 tons – 30 min back up • Insulated piping and electrical tracing • Spare place for future upgrades Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011
Power Distribution • 2 UPS Galaxy 7000 – 600 KVa • Main Switch board 2 MW • Redundant Air cooling unit • Fire protection • “Vesda” permanent detection • Conventional fire detection system level one • Sprinkler (automatic water extinguisher system) level 2 • Monitoring Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstdt - Mai 4 th 2011
Power distribution structure Cellules HTA N 630 kVA N 1 000 kVA N+1 800 kVA N+1 1 000 kVA TGBT Workers 2 400 kVA TGBT UPS critiques + services 2 500 kVA TGBT UPS critiques 400 kVA N 600 kVA N+1 600 kVA N 200 kVA N Modules clim N Modules clim Critiques N x (1+1/5) Modules clim Services N Modules clim N+1 800 kW N N N N Workers Services 574 kW HQ 600 kW HQ N+1 800 kW Critics 115 kW HQ Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
On going projects Phase II • Additional Equipment & facilities • Additional power transformer • Third chiller unit 400 KW • Second Batteries farm • Piping and water pumps • Additional power switch boards Project launched to be delivered by end of October 2011 A “ready to plug in” for 50 more racks units …… Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Main Electrical Supply redundancy project On going projects Final decision taken to face a new challenge In the first phase the electrical redundancy will be minimal 2011 - 1,7/ 6 MW 2013 – 1,95/ 4 MW 1,95 MW will be backed up by the power supplier 2016 -2019 - 4 / 9MW 4 MW will be guaranteed by the power supplier Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 4 th 2011
Future Development project An office space was part of the original extension project but dropped due to budget limitation Project Re-formatted with new functionalities added Multimedia center Amphitheatre accessible to the public A “Hub” for fundamental research, University and public information Dedicated Training center Outreach center Very well perceived by the Region and the city community (Grand Lyon) Pascal.trouve@cc.inp3.fr Hepix Spring Meeting - Darmstadt - Mai 5 th 2011