An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SWAT Short Circuit Study Group Update May 10, 2006 Albuquerque, New Mexico

  2. Short Circuit – System Reliability • Relay Misoperations – Fail to Operate or Operate When They Shouldn’t • Equipment Damage due to Failure to Operate Relays • Circuit Breakers and Other Equipment Failure because not Properly Rated

  3. SWAT Short Circuit Working Group (SCWG) Accomplishments • Webpage setup and linked to SWAT Website • Charter (Scope) Finalized • All SWAT Transmission Owners joined • 4 meetings held since starting in January • Monthly meeting schedule • Impedance Map Plan Developed • Working on Combining First Case

  4. SWAT SCWG Webpage

  5. SWAT SCWG Webpage

  6. 4 Main Areas of Work • Impedance Maps • Annual Operating Case • Common Study Methodologies • Annual Standards Review

  7. SWAT SCWG Charter

  8. SWAT SCWG Webpage

  9. Meeting Locations • January 26, 2006 – WAPA - Phoenix • February 16, 2006 – TEP/UES – Tucson • March 16, 2006 – NPC/SPPC – Las Vegas • April 20, 2006 – SRP – Phoenix • May 18, 2006 – SWRTA – Casa Grande

  10. SWAT SCWG Webpage

  11. Impedance Maps Work • Most Impedance Maps Are Out of Date • List of Items to be Placed On Maps Developed • A Single Set of Impedance Maps to be Generated • Requested SWAT to Develop WestConnect Funding of Impedance Map Generation • Only 2 WestConnect Members not Members of SWAT SCWG

  12. SWAT Letter – 3/24/06

  13. SWAT Response – 4/16/06

  14. SWAT SCWG Webpage

  15. SWAT SCWG Participants

  16. STEP SCWG Proposal

  17. Member Programs • APS - Cape • SRP – Aspen • WAPA – PTI and Aspen • TEP/Unisource – Aspen • SWTC – Aspen • IID – Aspen • EPE – Aspen • PNM – Aspen • NPC/SPPC – Aspen

  18. SWAT SCWG Webpage

  19. DPV2 SCWG Findings • 442 of 1481 buses with 10 A or higher difference • Some Transformers not Modeled as Transformers in the DPV2 SCWG PSS/E case • Type 2 Buses in PSS/E Do Not Stay Constant

  20. DPV2 PSS/E Converted Aspen Worst Differences

  21. Combined Case • Plan Developed • Conversions Currently being Checked • Zones for Members being Developed • Equivalents to be Checked • Cases to be Combined

  22. Future Work • Combine CCPG SCWG Case • Combine STEP SCWG Case (if developed) • Develop Common Methodologies • Review of Standards • Start on next Annual Case and Impedance Maps Update (refinements)

  23. Future Refinements • Add Mutual Coupling • Add Line Charging Capacitance • Add Motors • Check Transformer, Line, Shunt, Generator, and Load Data

  24. Refinement Example: Line Charging Capacitance

  25. Potential Load Flow Help • Impedance Maps for Load Flow Operating Case • Possible WECC Evolution of Regional SCWGs • If WECC Bus Numbers Used Later, Import of More Accurate SC Case Data into Load Flow Cases