Changes to the 2010 AISC Seismic Provisions

Changes to the 2010 AISC Seismic Provisions. James O. Malley Senior Principal, Degenkolb Engineers and Chair, AISC TC9. TC 9 – “The Hardest Working Committee in Show Biz”. Tom Sabol Bahram Shahrooz Bob Shaw* Lee Shoemaker Kurt Swensson Robert Tremblay (‘10)

myron
Download Presentation

Changes to the 2010 AISC Seismic Provisions

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Changes to the 2010 AISCSeismic Provisions James O. Malley Senior Principal, Degenkolb Engineers and Chair, AISC TC9

  2. TC 9 – “The Hardest Working Committee in Show Biz” • Tom Sabol • BahramShahrooz • Bob Shaw* • Lee Shoemaker • Kurt Swensson • Robert Tremblay (‘10) • Jamie Winans (’10) • Cindi Duncan ** • Plus Corresponding Members • * SC Chair • ** Secretary • RoyBecker (‘05) • Michel Bruneau (‘10) • Greg Deierlein • Rick Drake • Mike Engelhardt • Roger Ferch (‘05) • Tim Fraser* • Subhash Goel • Jerry Hajjar (‘10)* • Ron Hamburger (‘10) • Jim Harris • Pat Hassett (’10) • John Hooper (‘10) • Brian Knight (‘10) • Keith Landwehr (‘10) • Roberto Leon • Bob Lyons (‘05) • SanjMalushte • Bonnie Manley (‘10)* • Hank Martin (‘05)* • Clarkson Pinkham • John Rolfes (‘10) • Rafael Sabelli* • Mark Saunders*

  3. AISC 341 (2005 and 2010) • AISC 341-05 was now included by reference in 2006 and 2009 IBC. Same for AISC 360. • AISC 360-10 and 341-10 are included by reference in 2012 IBC. • Both the 2005 and 2010 Provisions will be summarized together to highlight update of “newest attractions” • Presentation based on order of 2005 Edition • Focus of discussion on 2010 changes

  4. Overall Philosophy of AISC 341 • Identify Target Yield Mechanism for Each SLRS • Designate Deformation-Controlled Elements (Structural Fuse): Design for Reduced Seismic Forces Ductility Design Is Relatively Straightforward (Prescriptive) • Design Remaining Elements as Force-Controlled: Design for Forces to Remain “Essentially Elastic at Capacity of Fuses Use Either “Local” or “Global” Approach Capacity Design Requires Good Judgment and Experience Credit: C. M. Uang

  5. It’s This Simple… Target Yield Mechanisms Flexural Yielding Tensile Yielding/Buckling Shear Yielding Target Mechanism Plus Ductility Requirements Plus Capacity Design Requirements Equals…

  6. Major Elements of 2005 Seismic Provisions • Part I covers all Major Seismic Systems • Focus on SDC D, E and F • Coordinated with ASCE 7-05 • Incorporate Post-Northridge Findings • FEMA/SAC Project Results (FEMA 350 Series) as Well as Other Efforts • Composite Provisions from NEHRP Included (Part II) • Note that Both Parts are in the “Unified” Format similar to the Main AISC Specification • Both LRFD and ASD included in one set of provisions

  7. Summary of Major Changes in AISC 341-10 • Re-organized to be More Consistent with AISC 360-10 • Format for Various Systems Have Been Standardized • Incorporates AWS D1.8 • Puts Composite Construction on the Same Footing as Steel (No more Parts I and II) • Adds Two New Cantilever Column Systems • Developing design/analysis provisions explicitly follow capacity design approach for ALL systems • Updates to member and system requirements • Coordinated with ASCE 7-10. To be included in 2012 IBC

  8. Document Re-organization • A. General Requirements • A1. Scope (I-1, II-1) • A2. References (I-2, II-2) • A3. Materials (I-6, I-7, II-5) • A4. Structural Design Drawings and Specifications (I-5, II-18) • B. General Design Requirements • B1. General Seismic Design Requirements (I-3) • B2. Loads and Load Combinations (I-4, II-4) • B3. Design Basis (I-3) • B4. System Type

  9. Document Re-Organization (Con’t.) • C. Analysis • C1. General Requirements • C2. Additional Requirements • C3. Nonlinear Analysis • D. General Member and Connection Design Requirements • D1. Member Requirements (I6-I9, II8) • D2. Connections (I7, I8, II-7) • D3 Deformation Compatibility of Non-SFRS Members and Connections • D4. H-Piles (I-8)

  10. Document Re-Organization (Con’t.) • E. Moment-Frame Systems • E1. Ordinary Moment Frames (I-11) • E2. Intermediate Moment Frames (I-10) • E3. Special Moment Frames (I-9) • E4. Special Truss Moment Frames (I-12) • E5. Ordinary Cantilever Column Systems • E6. Special Cantilever Column Systems

  11. Document Re-Organization (Con’t.) • F. Braced-Frame and Shear-Wall Systems • F1. Ordinary Concentrically Braced Frames (I-14) • F2. Special Concentrically Braced Frames (I-13) • F3. Eccentrically Braced Frames (I-15) • F4. Buckling-Restrained Braced Frames (I-16) • F5. Special Plate Shear Walls (I-17) • G. Composite Moment Frame Systems • G1. Composite Ordinary Moment Frames (II-11) • G2. Composite Intermediate Moment Frames (II-10) • G3. Composite Special Moment Frames (II-9) • G4. Composite Partially Restrained Moment Frames (II-8)

  12. Document Re-Organization (Con’t.) • H. Composite Braced Frame and Shear-Wall Systems • H1. Composite Ordinary Braced Frames (I-13) • H2. Composite Special Concentrically Braced Frames (II-12) • H3. Composite Eccentrically Braced Frames (II-14) • H4. Composite Ordinary Shear Walls (II-15) • H5. Composite Special Shear Walls (II-16) • H6. Composite Special Plate Shear Walls (I-17) • I. Fabrication and Erection • I1. Shop and Erection Drawings (I5, App. W, II-18) • I2. Fabrication and Erection (I7)

  13. Document Re-Organization (Con’t.) • J. Quality Control and Quality Assurance • J1. Scope (I-18, App Q, II-19) • J2. Fabricator and Erector Documents (App. Q) • J3. Quality Assurance Agency Documents (App. Q) • J4. Inspection and Nondestructive Testing Personnel (App. Q) • J5. Inspection Tasks (App. Q) • J6. Welding Inspection and Nondestructive Testing (App. Q) • J7. Inspection of High-Strength Bolting (App. Q) • J8. Other Steel Structure Inspections (App. Q.) • J9. Inspection of Composite Structures • J10. Inspection of H-Piles

  14. Document Re-Organization (Con’t.) • K. Prequalification and Cyclic Qualification Testing Provisions • K1. Prequalification of Beam-to-Column and Link-to-Column Connections (App. P) • K2. Cyclic Tests for Qualification of Beam-to-Column and Link-to-Column Connections (App. S) • K3. Cyclic Tests for Qualification of Buckling-Restrained Braces (App. T)

  15. Scope Statement / Gen’lReq’ts. • Intended Primarily for Building Structures • Also incorporated for “building like” non-building structures • Glossary clarifies that SLRS includes diaphragm chords and collectors, and all elements that resist seismic loads • For SDC A, B and C, designer has choice • Use the Seismic Provisions with appropriate R factor • Use AISC LRFD/ASD Provisions with R=3 • Required When Specified by ASCE 7-10 • SDC D, E, and F, typically • Clarifies use of ACI 318 for R/C elements in composite systems

  16. General Design Requirements • SDC, Height Limitations, Design Story Drift per ASCE 7-10 • Defines how to apply Ω0 and Emh in ASCE 7-10, • Required Strength either generated by analysis or the system requirements (capacity based design concepts) • Available Strength per LRFD or ASD

  17. Project Documentation Requirements • New Section to Define Expectations of: • Design drawings and specifications • Shop Drawings • Erection Drawings • Requirements for Shop and Erection Drawings moved to Chapter J • Includes lists of information to be provided such as SLRS designation, connection detailing, welding requirements, protected zones, etc. • Consistent with FEMA 353 and AWS D1.8 references incorporated in 2010

  18. Material Specifications • ASTM Specifications for Materials Employed • All major structural products incorporated • Material Properties for Determination of Required Strength for Connections or Related Members Based on Expected Yield Strength and Expected Tensile Strength (Ry and Rt) • Available Strength to consider both expected yield and tensile strengths • Intent is to ensure expected inelastic response and ductile failure modes

  19. Material Specifications (Cont.) • Requirements for Charpy V-notch testing of heavy shapes and plates • Expand use of yield strength above 50 ksi • Reference to AWS D1.8 for filler metals

  20. Connections - Bolted Joints • Fully Tensioned HSB, Class A Slip-Critical, design for bearing strength. • No sharing of load with welds in a joint or the same force component in a connection. • Standard holes, or short slots perpendicular to line of force. • Oversized holes in one ply of brace diagonals allowed • Other conditions allowed if verified by testing • Ductile limit - state controls design. • Yielding rather than fracture • Removed in 2010

  21. Connections - Welded Joints • New Appendix W with welded joint requirements beyond standard AWS D1.1 • Consistent with FEMA 353 • Being incorporated into new AWS D1.8 • Published in late 2005. Future editions of AISC Seismic will reference as appropriate. Referenced in 2010. • WPS required / Approved by EOR • Continuity plate welding and detailing specified

  22. Connections - Welded Joints • Filler metal CVN 20 ft.-lbs. @ -0° F for all welds in the seismic load resisting system (SLRS) • Reduction from -20° F in 2002 • Two level toughness required for designated Demand Critical Welds in SMF, IMF, OMF and EBF • based on FEMA recommendations • Consistent with previous testing • Appendix provides requirements for qualification • Referred to AWS D1.8. Locations defined in AISC 341

  23. Welded Joints (cont.) Fracture Shear Stud weld • Defines term “Protected Zone” where special care is required • Eliminates welding and other attachments in plastic hinge zones (shear studs, e.g.). Spot welds acceptable • OK outside hinge zones, but need to verify net section strength • Discontinuities caused by welding or other construction operations must be repaired. • Locations of Protected Zones defined for each system

  24. Members • Width-thickness ratios often stricter than main specification requirements • 2010 Defines new terms, “Moderately” and “Highly” Ductile (MD and HD) • Used for width-thickness and bracing reqt’s • Width-thickness table parallels B4.1 in AISC 360 • MD like compact, HD, like seismically compact • HSS values reduced due to test results • Boxed WF sections included • Composite elements included

  25. Plastic Buckling Mp Inelastic Buckling Moment Capacity Mr Elastic Buckling ps p r Width-Thickness Ratio Ductility

  26. Members – Cont. • New paragraph on diaphragm design • Load transfer details required • Nominal shear strength defined as concrete above deck, w/o ACI Ch. 22, or test results • Bracing requirements made uniform for various systems • Special requirements at plastic hinges • Columns with high axial load to be checked for amplified seismic loading • Similar to 341-05, but ALL columns checked for Ω0 level axial forces • New requirements for composite columns

  27. Column Splices/Bases • Strength requirement for partial penetration and fillet welded splices of 200% of required strength. • Beveled transitions not required where partial penetration welds are permitted. • Requirements for shear strength check of non-frame columns in all systems. • Only location in the provisions that refers to elements not part of the SLRS • Clarifies use beveled transitions in CJP splices and removal of weld tabs (but not backing) per D1.8 • Column base weld backing reqt’s also defined

  28. Members (cont.) • Column base design (Con’t) • General intent to design column base for same forces that the elements connecting to the base are designed for. • Axial, shear and flexural strength requirements presented • Interaction with concrete elements referred to ACI 318 Appendix D. • Clarifying language added • H-pile requirements included

  29. Deformation Compatibility • New Section highlights need to check non-SLRS members and connections for gravity load effects and deformations at the Design Story Drift as defined in ASCE 7-10 • User Note added to justify shear tab connections and allow self-limiting inelastic deformations in other connections

  30. Chapter C – Analysis (2010) • Entirely new chapter • Defines section properties for elastic analyses • Elastic sections for steel • Cracked sections for concrete and composite elements • Refers to system chapters for additional (capacity based requirements) • Refers to ASCE 7-10 Chapter 16 when nonlinear analyses used

  31. System Formats Unified in 2010! • Scope – defines system title • Basis of Design – defines expected system response (yielding and protected members etc.) • Analysis – defines special analyses for capacity definitions (SCBF, e.g.) • System Reqt’s – stability bracing and other system-wide reqt’s • Members – sets b/t limits, lists protected zones and defines individual member reqt’s • Connections – defines demand critical welds, and connection reqt’s, including splices

  32. Special Moment Frames (SMF) • Designs based on cyclic test results to 0.04 radians • Appendix S provides test requirements • For either project specific or “public” tests • Appendix P provides basis for “pre-qualification” of connections • Connections designed in accordance with AISC 358 standard • Shear connection capacity sufficient to develop force generated by fully plastic beam

  33. (N) AISC Moment Connection Prequalification Standard • Official title: “Prequalified Connections for Special and Intermediate Steel Moment Frames for Seismic Applications” • Developed by separate ANSI standards development committee (Ron Hamburger, Chair) • Allows engineers to submit moment frame designs without producing connection test results • First edition focuses on RBS and End Plate connections • More connections included (WUF-W, e.g.) • Adopted by 2005 & 2010 AISC Seismic

  34. SMF (Cont.) Mp1 at column face Mp1 Mp2 Mp2 at column face • Panel Zone Design • Intended to share yielding with beam • Equation differs from FEMA 350 • Doubler plate configurations may be adjusted to avoid “k” area • Continuity plates to match tested configurations

  35. SMF (Cont.) L L C C Mpc2 Mc1 Mc2 Mpc1 • SCWB Check required for SMF frames • Attempting to avoid weak stories • Exceptions provided • 2010 clarifies use of Ω0 for axial force reduction • Column splices pushed towards CJP

  36. SMF (Cont.) • Lateral Bracing of Beams • Nominal bracing required along length for both strength and stiffness based on main spec. equations • Bracing at hinges (6%) required as well • But, not IN hinge zones!

  37. IMF/OMF Requirements • Intermediate (IMF) provisions similar to SMF • Tested capacity to 0.02 radians, beam shear, etc. • Other requirements (SCWB, panel zone, etc.) not as restrictive as SMF. MD designation for members. • DC welds at splices • Ordinary (OMF) provisions • Allows calculation only, but for strength above 1.1 Ry Mp • Specific welding and detailing requirements (access holes, e.g.)

  38. STMF • Concept Similar to EBF’s • Ductile Special Segment (SS) • Other Parts of the Truss Remain Elastic • Both Cross-braced and Vierendeel configurations • Span limited to 65 feet • Depth limited to 6 feet • Minor change to SS capacity • DC welds added for column splices

  39. Cantilever Columns (2010) • Two (N) sections to be consistent with ASCE 7-10 • (N) SDC and height limits in ASCE 7-10 • Ordinary System (OCCS) • Column axial loads low (15% of available at Ω0) • AISC 360 b/t ratios, no DC welds or protected zones • Special System (SCCS) • HD b/t ratios, stability bracing for MD, protected zone at base, DC welds at base

  40. Special CBF Provisions • KL / r < 4 / E/Fy with exception to higher • Stricter b/t Ratios and Built-up Member Requirements • Connection Requirements • Strength to Develop Tensile Strength • Ductility to Allow Buckling in Member or Gusset Plate • Restrictions on Chevron and K-Bracing • Stronger Column Splices Required • Capacity Design Requires two load distributions be checked • Connection Reqts. Increased (EBF and BRBF also), to accommodate drift • DC welds at column splices and bases. No PJP groove welded splices

  41. 2010 Analysis Req’t. - SCBF oF3 T 0.3P F F oF2 T 0.3P F F oF1 F F 0.3P T T  0 in Center Column Uplift in Center Column!

  42. OCBF Provisions • Limited use in high SDC’s • For V or inverted V, KL/r < 4.23/E/Fy • Connection strength to develop brace tension capacity or amplified force • Reorganized language to clarify expected compression strength • Chevron bracing restrictions • Tension Only Bracing Systems Allowed for Low and Penthouses • No K-Bracing & define minor eccentricities (similar for SCBF’s)

  43. EBF Provisions • Inelastic behavior limited to link beams • Remainder of system (braces and columns) to remain elastic • Best results for shear link elements, but local demands are higher than SMF’s • Extensive stiffening requirements • Built-up Boxes added for links • Based on recent Bruneau research • Clarification on calc for inelastic rotation angle • Other changes similar to SCBF

  44. EBF Provisions (Cont.) Pbr Pu • Link-to-column connections • Require testing like SMF • Exception allowed • Beam outside link, braces and columns designed for link capacity, including strain hardening (1.25 & 1.1) • Lateral bracing requirements similar to SMF • 6% at ends of links • Elsewhere, strength and stiffness as required in main spec.

  45. BRBF Provisions • BRBF Frames • SCBF development improves braced frame performance, but still limited by brace buckling • Concept developed in Japan, with many applications • Hysteretic behavior similar to elastic - perfectly plastic • Development of provisions in U.S. • Joint AISC/SEAOC effort • Approach similar to EBF • Analytical work indicates good performance • U.S. practice will lead to larger drifts • Included in 2003 NEHRP

  46. BRBF Provisions (cont.) • Steel core restrained from buckling • Braces tested for twice Design Story Drift • Appendix T specifies testing requirements • Brace strength addresses strain hardening and compression strength increase due to confining system • Connections designed for adjusted strength • Chevron requirements less demanding than SCBF • Column splices similar to SCBF • Increased Connection Reqt’s, DC welds at column splices and base, and no PJP groove welded splices similar to SCBF

  47. SPSW Provisions • SPSW like plate girder design approach (tension field theory) • Can generate tremendous strength and stiffness as compared to CBF • SPSW concept developed in Canada • NBCC Code provisions in place • UC Berkeley work as well • Provisions incorporated into 2003 NEHRP • Panel Capacity Based on Simple Formula • Includes panel aspect ratio • L/h between 0.8 and 2.5

  48. SPSW Provisions (cont.) • Panels with Openings to have boundary elements (BE) • Connection between web and BE’s for plate capacity • BE’s to develop panels. OMF style connections • Lateral bracing spacing like SMF. • Vertical BE’s also have bending stiffness requirements • Perforated Webs and corner cut-outs added • Added HBE stiffness • Protected zones added • Increased Connection Reqt’s, DC welds at column splices and base, and no PJP groove welded splices similar to SCBF

  49. Composite Systems • Part II - Composite Construction Provisions • First Developed for 1994 NEHRP • Identifies Numerous System Options (10 total in 2010) • Provides Detailed Requirements for Member and Connection Design • Modified and Made Consistent with Part I • No longer Part II. Made Fully Consistent with Chapters E and F • MANY changes required

  50. Chapter D: General Member and Connection Requirements • SRC Beam-Columns: • Moderately and highly ductile detailing procedures (comparable to AISC 341-05) • CFT Beam-Columns: • Shear strengths is based on steel section alone • Connections: • Non-seismic provisions include clearer text on load transfer for general composite conditions: • Bond interaction • Direct bearing • Steel anchors • Non-seismic provisions include new provisions for steel anchors in shear, tension, and interaction for conditions beyond composite beams • Splice connection provisions for SRC refer to ACI Ch. 21 provisions for mechanical splicing • Seismic connection detailing provisions are mainly for steel girders framing into RC or SRC beam-columns • Written in early 1990’s