An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update Shelter Response CHIEF SECRETARY – ESC MEETING 14-12-2008

  2. Developments committments • Hilfswerke Austria committed 100 TS, start in January • Alfullah Bank planning to fund 100 TS, reviewing technical designs, contacting agencies • Al Ameen trust added 100 TS to the committed 130 TS. • Don Basco Church confirmed construction of 35 TS • Qatar Charity confirmed construction of 100 TS instead of 50 TS • Islamic Relief found funding for additional 128 TS • Calculation mistake: Jamaad Ud Dawa 650 double in sheet + 300 shelter material + NFI’s luted. 1.000 pipeline unsure. • Balance: + 500 – 950 = -/- 450 TS

  3. Progress - developments • Eid holiday: difficult to mobilize community, drivers and carpenters. Also the days after Eid • Strikes in Kach and Amadoon, blocked the road for traffic for 3 days, delays distribution. • Teachers are on the ground and instructed for Community Mobilization • Food Package (32 kg) incentives when shelter finished. Food is in the field, distribution / timing to be arranged • ESC permanent field coordinator in Ziarat • Aftershock of 5.7 (Richter scale) on Tuesday 10.30 am possible additional damage, impact on the community. • First snow fell in the area. • PRCS / IFRC prepares for distribution, material for 1.000 kits arrived in the field, start 15-12 till 31-12. • Turkish RC erected 90% of shelters, water supply pending.

  4. Community Participation • Community participation important for dealing with psychological aspects of the disaster and building resilience for the future • Not all beneficiaries are erecting the shelters since they are migrating or choosing different solutions • Limited capacity for monitoring / motivating the communities to erect shelter when distributions are ongoing. • Participation of the local government leaders is crucial

  5. Progress (sheet corrected as mentioned in meeting) Number of shelters erected in last week: 697

  6. Erection planning per Agency

  7. Concerns • If we want to move faster, the government is invited to mobilize additional resources • Looting… extra police support of the warehouses