U.S. Government Printing Office FDsys Update. Fall Depository Library Council October 15, 2007. Program Office Updates. In July, the CTO organization, including the FDsys program office was combined with the CIO organization. New CIO group. Former CIO group. Former CTO group. Security.
E N D
U.S. Government Printing OfficeFDsys Update Fall Depository Library Council October 15, 2007
Program Office Updates • In July, the CTO organization, including the FDsys program office was combined with the CIO organization. New CIO group Former CIO group Former CTO group Security Project Management IT Operations Technology Management Program Management Strategic Programs like FDsys are now tightly aligned with IT Infrastructure and Operations.
GPO Strategic System Initiatives Business Information Systems Content Management Systems Digital Production Systems (Financial, HR) (FDsys, Composition System, ILS) (Manufacturing Systems, Print on Demand) IT Infrastructure and Operations The CIO Organization is well positioned to support GPO’s Strategic System Initiatives.
Presentation Outline • Project Overview and Status • FDsys Communications Update • Release 1C Development Update • Proof of Concept Demonstration • Questions and Answers
FDsys Communication Update Working Groups • Office of the Clerk of the House • Office of the Secretary of the Senate • Interagency Council on Digital Content Submission (ICDCS) Presentations were given to over 30 federal agencies in 8 cities
FDsys Communication Update Proof of Concept Demonstrations • Joint Committee on Printing • Office of the Clerk of the House • Office of the Secretary of the Senate • DC area librarians • Congressional Research Service • Office of the Federal Register • Interagency Council on Digital Content Submission
Release 1B Beta Testing 9/26 – 10/10 Federal Depository Library Community 11/30 – 12/7 GPO Internal – Submission 12/10 – 12/17 Federal Agencies - Submission
Release 1C Development Update • 1C is the first public release of FDsys • Builds on the foundation established for 1B
Release 1C Development Update • Will be rolled out in stages, or “increments” • Each increment will introduce additional system functionality
Release 1C Development Update • Release 1.C planning milestones accomplished • System Requirements Review (SRR) • Initial requirements document – RD 3.1 • System Design Review (SDR) • Feature sets approach • Requirements fine tuning
Release 1C Development Update • Future 1.C planning milestones • Delta SRR • Baseline for requirements – RD 3.2 • Delta SDR • Baseline for system architecture
Release 1C Development Update • So cut to the chase! • What’s in the feature sets? • What is the schedule?
Release 1C Development Update • What’s in the feature sets? • Infrastructure • Package management/OAIS • GPO Access replacement • Metadata management (ILS)
Release 1C Development Update • What else? • Congressional content submission • Persistent name • Agency content submission • Access and delivery
Release 1C Development Update • First public release – late 2008 • Additional releases – 2009 • R1.B demo system will remain available
Release 1.B • Proof of concept demonstration • Content submission • Access
Questions and Answers • Contact us by email pmo@gpo.gov • Visit the FDsys Website http://www.gpo.gov/projects/fdsys.htm