Use of Full Depth Shoulders on Wisconsin Highways Steve Krebs, Bob Arndorfer, and Jed Peters – DTSD-Bureau of Technical Services April 29, 2013
Overview of presentation Literature Review Current Design Practices Pavement Performance Observations Full Depth Shoulder (FDS) Construction and Cost Considerations FDS Life Cycle and Benefit-Cost Analyses Benefits Recommendations/Implementation Costs
Literature Review • Design Standards • 1990 FHWA Advisory • Mechanistic-Empirical Pavement Design Guide • Wisconsin Highway Research Program (WHRP) Report • FDS Benefits • Construction Maintenance of Traffic • Incidents/Events • Emergency Evacuations • Other State Practices
Current WisDOT Design Practices Geometry Thickness
Pavement Performance Observations • Pavement Distress • NE Region • SE Region • NW Region • Preventative Measures
FDS Construction and Cost Considerations - Overview • 10 Projects Analyzed • 8 Concrete Mainline • 2 HMA Mainline • As-built and Estimated FDS Costs
FDS Construction and Cost Considerations – Cross-Sectional Assumptions
FDS Construction and Cost Considerations – Cross-Sectional Assumptions
Construction Cost Summary • Concrete Mainline Projects • As-built average (avg) cost: $182,920/mile • FDS HMA avg cost: $346,430/mile • FDS concrete avg cost: $265,000/mile • HMA Mainline Projects • As-built average (avg) cost: $123,320/mile • FDS HMA avg cost: $171,600/mile
Life Cycle Cost Analysis (LCCA) - Overview • Costs/Impacts not Considered • Maintenance Schedules • Conventional • FDS • Time Value of Money
LCCA– Summary • Concrete Mainline Projects • As-built avg net present value (NPV) life-cycle 50 year cost: $276,720/mile • FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile • FDS concrete avg NPV life-cycle 50 year cost : $345,140/mile • HMA Mainline Projects • As-built avg NPV life-cycle 50 year cost : $198,050/mile • FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile * NPV calculated with 3.5% discount rate
Benefit Cost Analysis (BCA) • LCCA vs BCA • Dissimilar Alternative: User Delay • Conventional Shoulder User Delay NPV = $146,830/mile
BCA– Summary • Concrete Mainline Projects • As-built avg NPV life-cycle 50 year cost: $423,550/mile • FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile • FDS concrete avg NPV life-cycle 50 year cost : $345,140/mile • HMA Mainline Projects • As-built avg NPV life-cycle 50 year cost : $344,880/mile • FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile * NPV calculated with 3.5% discount rate
Additional Identified Benefits • Non-Denominated • IH-43 • IH-94 • Denominated • IH-39 – Shoulder Replacement • IH-94 – Shoulder Widening • USH 41 – Shoulder Widening
IH-39 Cost Summary • Estimated As-Built Construction Cost/Mile • $151,570/mile (1984 Dollars) • $337,550/mile (2012 Dollars) • Estimated 10” FDS Construction Cost/Mile • $190,840/mile (1984 Dollars) • $425,010/mile (2012 Dollars) • LCCA Costs • As-built NPV = $456,110/mile • FDS NPV = $535,720/mile • 2012 Project - 8” Shoulders Let Cost/Mile • $333,850/mile
IH-39 Cost Summary Cont… • Adjusted LCCA Costs • As-built NPV = $515,000/mile • FDS NPV = $467,540/mile
USH 41 Cost Summary Actual Widening Cost = $7.28 Million Estimated Widening Cost with Incorporation of FDS = $5.17 Million Cost Savings of $272,000/mile
IH-94 Cost Summary Actual Widening Cost = $3.99 Million Estimated Widening Cost with Incorporation of FDS = $3.07 Million Cost Savings of $178,000/mile
Recommendations • Selective Application of FDS • High Volume Arterial Corridors • Mass Evacuation Routes • Incorporate FDS (Existing and Future) into Emergency Planning
Volumes Estimated For Highest Direction in 30th Highest Hour in 2013
Cost to Implement • Average Outside FDS Cost: $248,575/mile • Average Inside FDS Cost: $165,480/mile • HMA Conventional Shoulder to Concrete FDS • Outside shoulder only: additional $108,100/mile • Both shoulders: additional $164,000/mile • Concrete Conventional Shoulder to Concrete FDS • Outside shoulder only: savings of $28,800/mile • Both shoulders: savings of $41,500/mile
Region Self Implementation • Southeast • N-S and Zoo Freeways • Southwest • IH-39 Corridor Reconstruction • Northeast • USH 41 (Winnebago and Brown Counties)