Brazilian Tunable Filter Imager (BTFI) Preliminary Design Review (PDR) . Team Management (Claudia & Keith) Version 1.0. USP-IAG Universidade de São Paulo 18-19th June 2008. BTFI Team Management. BTFI phases: Design Post-PDR to final specifications and drawing set Fabrication
E N D
Brazilian Tunable Filter Imager(BTFI)Preliminary Design Review (PDR) Team Management (Claudia & Keith) Version 1.0 USP-IAG Universidade de São Paulo 18-19th June 2008
BTFI Team Management • BTFI phases: • Design • Post-PDR to final specifications and drawing set • Fabrication • Assembly, Integration & Test • Commissioning
BTFI Core Team(in no particular order!) • Claudia Mendes de Oliveira (CMdO – IAG/USP) • Keith Taylor (KT - contracted) • Rene Laporte (Rene - INPE) • Fernando Laurenco (FL – INPE) • Cesar Strauss (CS – INPE) • Luiz Reitano (Reitano – INPE) • Antonio Cesar de Oliveira (ACdO – LNA) • Fernando Fontes (FF – contracted) • Dani Guzman (Dani – contracted: AstroInventions) • Giseli Ramos (Giseli – IAG/USP) • Bruno Quint (Bruno – IAG/USP) • Luiz Cavalcanti (Luiz – IAG/USP) • Javier Ramirez Fernandez (Javier – USP) • Antonio Kanaan (AK – UFSC) • Fabricio Ferrari (FFe – U. Santa Maria)
Design Phase Responsibilities • Optical • Final iteration with manufacturers (DJ – subcontract) • Placing orders (CMdO @ IAG) • Opto-Mechanical • Design (Rene + FL @ INPE) • Drawings (FL + Reitano @ INPE) • Instrument Control Electronics • Design (Denis + CS @ INPE) • Detector Controller • Design (Olivier – PhotonEtc sub-contract) • Comms PCB & Power Supply (Denis + CS @ INPE) • FP Controller • Design (Jean-Luc Gach + Luiz @ LAM) • Software • Instrument Control (Giseli + FF @ IAG) • CCCP-v2 (Olivier Daigle @ U.Montreal + Giseli @ IAG) • OtF to Pipeline DR (CMdO + KT + Bruno @ IAG + AK + Ffe @ UFSC/USM)
Fabrication Phase Responsibilities • Optical • Managing procurement (KT) • Opto-Mechanical • Fabrication (eg: MetalCard and/or Proteo) • Instrument Control Electronics • Fabrication (Denis + CS @ INPE) • Detector Controller • Fabrication (PhotonEtc) • Comms PCB & Power Supply (Brazilian Industry) • FP Controller • Fabrication (@ LAM) • Software coding • Instrument Control (Giseli + FF @ IAG) • CCCP-v2 (Olivier Daigle @ U.Montreal + Giseli @ USP) • OtF to Pipeline DR (Bruno @ IAG + AK + FFe @ UFSC/USM)
AI&T Phase Responsibilities • Optical • Evaluation & acceptance testing + I&T (KT + Rene + ACdO @ LNA?) • Opto-Mechanical • Acceptance (Rene + Reitano - INPE) • I&T (Rene + Reitano + ACdO @ INPE or LNA) • Instrument Control Electronics • Test (Denis + CS) • Detector Controller • Debug and evaluate (Dani – sub-contract to AI) • Test (Javier @ USP + Dani) • FP Controller • Debug, evaluate and test (Luiz @ IAG) • Software test & debug • Instrument Control (Giseli + FF @ IAG) • CCCP-v2 (Giseli @ IAG) • OtF to Pipeline DR (Bruno + CMdO + KT @ IAG + AK + FFe @ UFSC/USM)
Commissioning Responsibilities • Final Instrument Integration (@ INPE or LNA- tbc) • Opto-mechanical (Rene, Reitano, CdO) • Control Electronics (Denis + CS) • Detector Controller (Javier + Giseli + FF) • FP Controller (Luiz) • Software • Instrument Control (Giseli and/or FF) • CCCP-v2 (Giseli) • Data Redn spec - OtF to Pipeline (Bruno + AK) • On-site Integration & Final Test (@ SOAR) • Rene, Reitano, ACdO, Denis, CS, Giseli, FF, Luiz, Bruno, AK • Commissioning (@ SOAR) • CMdO, KT, Rene, ACdO, Denis, Giseli, Luiz, Bruno, AK, FFe, FF