2007 Floods – 5 Years On Worcestershire September 2012 Dave Throup

2007 Floods – 5 Years On Worcestershire September 2012 Dave Throup. A reminder Progress Preparedness and response Communities protected The future. June/July 2007. Wettest on record Periods of very heavy rain 6” rain on July 20 th Exceptional flooding on Teme, Severn and Avon

nami
Download Presentation

2007 Floods – 5 Years On Worcestershire September 2012 Dave Throup

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2007 Floods – 5 Years OnWorcestershire September 2012Dave Throup

  2. A reminder • Progress • Preparedness and response • Communities protected • The future

  3. June/July 2007 • Wettest on record • Periods of very heavy rain • 6” rain on July 20th • Exceptional flooding on Teme, Severn and Avon • Surface water flooding

  4. Impacts • 6000 buildings, 3500 homes, 800 businesses flooded • Rescues from buildings and caravans • Road network crippled for days • Long term infrastructure damage • Agriculture • £6.5m per week

  5. Progress – Preparedness & response • Governance • Assessment of flood risk • Reduction of flood risk • Reduction of flood impact • Response triggers and actions

  6. Progress – Protected communities • 7 most vulnerable communities now protected • 260 properties • Vital infrastructure • £10.5m investment into Worcestershire

  7. Upton upon Severn £4.5m 51 homes and businesses Replaces temporary barriers Careful design and landscaping

  8. Hylton Road Worcester £1m 19 Homes Businesses along Hylton Road A443 Replaces temporary barriers Raised cycle and footway

  9. Powick £900k 19 homes A449 Protects both sides of village

  10. Kempsey £1.7m 37 Homes Fish friendly pumps

  11. The future • Vulnerability of Worcestershire • Climate change • Economic recovery and growth