1 / 10

CFEE Conference

CFEE Conference. State & Local Authority. What We Have, and What We Need. March 23 rd , 2007 By: Jim Madaffer. Presentation Outline. What We Have I-15 SR-125 What We Need New Opportunities. By the Numbers… Grew from 1,000 to 20,000 customers Over 10 million trips processed

nascha
Download Presentation

CFEE Conference

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFEE Conference State & Local Authority What We Have, and What We Need March 23rd, 2007 By: Jim Madaffer

  2. Presentation Outline • What We Have • I-15 • SR-125 • What We Need • New Opportunities

  3. By the Numbers… Grew from 1,000 to 20,000 customers Over 10 million trips processed Over $15 million in tolls collected Over $7 million in transit subsidy Over 1 million transit passengers Growth 1996 – Present … Average Daily Traffic (ADT) has increased by more than 100% HOV use has increased by 45% = VTMS = CMS Where We’ve BeenPast 10 Years

  4. Typical fee range is $0.50 to $4.00, with $8.00 maximum toll (Ex.) Pricing Table Dynamic Variable Pricing • Per-trip pricing using FasTrakTM electronic toll collection began in April 1998 • First project to employ dynamic variable pricing • Fees derived from volume of vehicles in Express Lanes; set to keep traffic free flowing

  5. Number of People per Hour Per Lane on I-15 3,000 2,500 2,100 More People During Average P.M. Commute 2,000 1,500 1,000 2:00 PM 2:30 PM 3:00 PM 3:30 PM 4:00 PM 4:30 PM 5:00 PM 5:30 PM 6:00 PM 6:30 PM General Purpose Lane Managed Lane Peak Hour Throughput

  6. Approve 66% Approve 88% Disapprove 28% Don’t Know 6% Other I-15 Users Disapprove 11% Don’t Know 1% FasTrak Customer Public Support for Managed Lanes • Conducted public outreach • Stakeholder interviews • Phone / Intercept Surveys • Focus Groups Approval of FasTrak Program By Group

  7. Approval of FasTrak Program By Age, Ethnicity, and Income Income ($000’s) Age Ethnicity Approval of FasTrak Program

  8. By the Numbers… Managed Lanes Project, constructed in 3 stages (middle, north, and south) Total length = 20 miles Four-lane concurrent (NB/SB) flow with movable barrier Project cost: over $1 billion ML FasTrak Projections… Over 6 million toll transactions expected each year (after 2012) Between $7 million to $9 million in revenue per year (after 2012) = Stations / Direct Access Ramps Where We’re HeadedI-15 Managed Lanes

  9. Existing & NewOpportunities • Existing Toll Road (SR-125) • Existing Value Pricing Corridor • New Value Pricing Corridors • Possible New Toll Roads

  10. Lessons Learned • There is public support for congestion pricing. • Pricing works as a congestion management tool. • Corridor-level public outreach and market research is needed. • Given growing demands and constrained revenues, new tools such as pricing and tolling are needed. • Need Authority at the State Level to expand the concept.