240 likes | 381 Views
Stato Generale di Atlas Aprile 06. Sottosistemi Toroidi Solenoide Mu Barrel Mu EC LAr e Tiles TRT SCT Pixel LV1 DAQ RRB Conclusioni. Barrel Toroid-1. The operations are following the sequence given in September without relevant problems: The Toroid was predeformed by 30mm.
E N D
Stato Generale di AtlasAprile 06 • Sottosistemi • Toroidi • Solenoide • Mu Barrel • Mu EC • LAr e Tiles • TRT • SCT • Pixel • LV1 • DAQ • RRB • Conclusioni L.Mandelli
Barrel Toroid-1 The operations are following the sequence given in September without relevant problems: • The Toroid was predeformed by 30mm. After release of Jacks (830t) 18mm. After assembly of Mu stations (350t) 25-28mm. ok (-2/-5mm- ~ 10-4) • Interconnections of the cryoring completed. L.Mandelli
Barrel Toroid-2 • Pumping started . Check leaks. • When 10-2 mBar Switch to diffusion pumps ( 8x2) to reach 10-5 mBar end April • Proximity cryogenic connected • Clean Up Cavern • Cooling down and first current tests in May • Full test in June. Memo: it was Feb-March (+ 4 m) L.Mandelli
End Cap Toroids • The assembly of the EC toroids is done at CERN in H191. • Several problems have been hit during assembly of ECT-A: • The cooling lines of the thermal shield end plates were leaking ( do you remind Zanon...?) 3m delay • The 6K termal shield had to be redone 1m delay • The top plate of the service turret was leaking and has to be repaired 1m delay Now Cryostat open ready for cold mass insertion Transport to H180 ( parking!) and cool down to 80K in June Installation in UX15 in Sept (it was May +4m) Cool down in Nov. ECT-C will follow in Dec, cool down in March L.Mandelli
connections Central Solenoid • Coil assembled with the LAr cryostat. B=2T • Moved in its final position in Oct 05 • Next Connect the coil to its services: He, I, controls: -Connect the chimney to the coil and the control dewar -Vacuum and cooling down with LAr -Test coil • Field map when Calo EC “in” : end June L.Mandelli
Mu spectrometer EC(Barrel is left to following talk) staged Inner/Small Wheel Big wheel 1 MDT 3 TGC EO Wall Wheel L.Mandelli
EC Wheels The assembly of the “ Big Wheels” is the most challenging part ( 1MDT; 3 TGC) Remind that wheels are divided in sectors and sectors are assembled and tested in B180 and then lowered in UX15. There are 16x2 sectors of MDT and 12x6 sectors of TGC. MDT: 8 MDT Sectors (25%) are assembled and tested. End forseen in October 06. The MDT Inner and the EO wheels should not present problems L.Mandelli
EC-Wheels-2 TGC ( 6 wheels- 72 sectors ) TGC-1C and TGC-1A well advanced but at the nominal rate assembly (not yet reached) will finish in July 07 Not acceptable. Increase technical team (done). Open a new (3°) assembly line once MDT are terminated. This will bring the assembly of C side in Nov 06 and A side in April 07. The EC Mu is time wise CRITICAL. Furthermore their installation will depend on the real schedule of the other subsystems ( ECT, etc) L.Mandelli
Barrel Calorimeters: Successes and problems • Barrel: Tiles & LAr: • Moved at the IP end of October. Position < 1mm to nominal in all directions • Installation of services: cabling, cryolines, piping (including ID) well advanced • Assembly and commissioning of FE and BE electronics well advanced • Cool down of LAr will start 10th of April. • The cool down will take 6w • Barrel should be cold (end) of May and will stay cold for the next 10 years (at least) !! L.Mandelli
EC LAr and EB EC-C • LAr EC-C lowered at side C on the EB in Dec 05. • EC-C assembly finished 10mm Z dispacement between EB and LAr. • Installation of services started • Moved to det open position end Feb ( Big Wheel tooling installation) EC-A • LArEC-A moved to SX1 Jan 06 • Lowering in the pit forseen in 20th April 06 MBTSC (16 to be placed on HM shield) CRYO SC GAP SC 60/64 64/64 L.Mandelli
LAR Point of attentions: • FEB nearing completion but lack of one type of preamps recently discovered (25 Ohm, 5mA). Reason: use in TB and tests, change of type by the FCAL ( 10mA 5mA) • Controller and Calibration boards are in full production. • LVPS: A lot of recent progress on the LV PS Four final modules under long test. Retrofitting of all modules (L) started. Be optimistic ! However commissioning was painful. Getting critical. • Interaction with TC needed to finalize implementation of forced air cooling (piping..) • HV PS situation remains a concern (running channels problem). Temporary solution to for the commissioning period available • More difficult to evaluate whether existing modules can be usable on a long period. In parallel technical test of modules from other vendors started. • Back-end electronics: • Production finished except additional RODs. Installation of barrel and EMEC RODs in USA15 finished L.Mandelli
Hadron Tiles Calorimeter • Front-end electronicscommissioning: very low component failure ( 0.2 %) • Back-end electronics: validation 90% done, ~ 50% installed in the pit. • DCS:Control of crate PS and LVPS installed and running in the pit. • Finger Low Voltage power supplies: Digital noise increase of 30% with non gaussian tails respect to the use of a commercial one. Could impact ptmiss tail and mu identification. Good progress in understanding and recovering. Incorrect SW procedure of operating LVPS system resulted in two superdrawer damages. Repaired. One-two weeks to implement a temporary solution, one-two months for the final one. Production ongoing. • HVtested but not operational. • Online and offlinetools: ready and used daily for commissioning • EB-Astarting in April L.Mandelli
ID: TRT and SCT Very good progress from October Barrel: TRT-Leaks problem on TRT cooling circuit manyfold due to poor brazing. Complete repacement of all manyfold. Work well advanced (8/32) SCT-Leaks on 3 (the first ones installed)/44 exhaust joints of the cooling loop . Fix all 44 with internal peek insert and internal and external epoxi qualified resistent to C3F8 and radiation. SCT- Thermal enclosure added and integrated Insertion of SCT in TRT accomplished on 17 February with success Solder joint L.Mandelli
Insertion 17 Feb. • The cantilever was finally lowered few mm and the SCT is now supported by the TRT • SCT-TRT clearance very small (~1mm per side) Overall process longer then scheduled (end-Decmid-Feb) due to leak repair. L.Mandelli
Barrel-ID Ready for Integration: Early June. Commissioned: End September L.Mandelli
ID: TRT and SCT • Barrel Ready for installation: early June Commissioned: October • EC-C All 9 SCT disks are at CERN and will be integrated with the TRT wheels end April Ready for installation early October Commissioned end December • EC-A 6/9 SCT wheels assembled at Nikhef ( it was 3/6) in October All TRT wheel are stacked and at CERN. Integration SCT-TRT in June Ready for installation end November Commissioned end February 07 L.Mandelli
Present status and next steps • The assembly of ATLAS proceeds along the planned lines: • The BT is assembled • Cryogenics, connections, controls are almost completed and vacuum pumping has started. Cold in June • The Barrel calorimeter is at the IP, Commisioning has started. LAr cryogenic advanced, Vaccum pumping started. Cold in June ( forever!!) • EC-C at the detector open position. Services installation well advanced. • Lowering in the pit and assembly of EC-A will start in April. • TRT and SCT Barrel assembled at surface. Ready for installation in June • Assembly of the Mu Barrel Chamber has started. A large fraction should be assembled for August. The fraction will depend on the interferences with the ID, the LArEC cryogenic and the assembly of the Mu EC. L.Mandelli
RRB April 06 • Final documents received last week ( 30-03) • www.cern.ch/~nordberg/ncp2/018-construction.pdfwww.cern.ch/~nordberg/ncp2/028-cp.pdfwww.cern.ch/~nordberg/ncp2/029-mo.pdfwww.cern.ch/~nordberg/ncp2/027-report.pdf • Some details worth to be studied in depth, but the main points seem to me the following: L.Mandelli
Budget 05 – CERN–RRB- 2006-018 CP-CC-C&I 62 9 6 76 46 3 2 51 -25 0 Reasons: Delay in program and payments L.Mandelli
Budget 06 Updates • As a consequence of the variations in 05 budget, the constrain of the 07 budget as the final one for the staged detector, the 06 budget ( Core and CC-A) has been updated. • The large fraction of the needed budget has been promised by agencies. • Very optimistically the missing CP contributions, Ru+JINR (5.2), Greece(1.5); USA(1.0); China( 0.3) and also a good fraction of the promised CtC/deferrals (INFN : 2638-350 kCHF) are assumed as income ( 2006-018-Table12-13) . ATLAS knows that this is optimistic. In front of a promise from agencies, pressure should be made on CERN for a loan (also in absence of pledge letters). • CC(B): ok • C&I(B): ok L.Mandelli
MOF- 2005 (*) Russia; JINR; Greece;....... L.Mandelli
MOF- 07 • First proposal. To be analysed and looked at by the groups ( Scrutiny and IB’s) • No positive/negative surprises INFN 2006 922 400 1322 L.Mandelli
Conclusions • In front of many successes and progresses one has to recognize and face at present about 4 months delay. • At present the beam pipe closure is foreseen in June 07 , the last installation of the EO Mu Chambers in August 07 • Mu-EC and pixel look to be the most critical items • However it is quite impressive to note that in (late) autumn 06 ATLAS will have the central part ( BT, solenoid, Calo, ID, Mu ) installed and under the phase3 commissioning (CR). • EC’s will follow • Financial situation requires attention, but I cannot believe that possible problems at the few % level of the detector value could be a reason for a delay. L.Mandelli