Status Report on all Capital Improvement Projects

Status Report on all Capital Improvement Projects. Facility Construction Committee Meeting February 11, 2002. Nixon High School. Architect: Cavazos Architects & Assoc. Contractor: Leyendecker Construction Inc. Design Status: Under Construction Budget: Construction Cost: $ 8,864,795

nasnan
Download Presentation

Status Report on all Capital Improvement Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report on all Capital Improvement Projects Facility Construction Committee Meeting February 11, 2002

  2. Nixon High School • Architect: Cavazos Architects & Assoc. • Contractor: Leyendecker Construction Inc. • Design Status: Under Construction • Budget: Construction Cost: $ 8,864,795 Soft Cost: $ 1,886,543 Total: $10,751,338 • Const. Start Date: Jan. 2002 • Completion Date: August 2003 • Scope of Work: Remodeled Campus – New facilities and renovation • New Construction: New Gymnasium, Cafeteria, Two Story Educational Complex and Administrative Addition • Renovation: Remodeling of existing classrooms, expansion of existing library • Comments: Portable classroom buildings for the displaced students

  3. Cigarroa High School • Architect: Ashley Humphries Sanchez Arch. • Contractor: To be determined • Design Status: Construction Document Phase • Budget: Construction Cost:$ 8,232,358 Soft Cost: $ 1,751,952 Total: $ 9,984,311 • Const. Start Date: April 2002 • Completion Date: Aug. 2003 • Scope of Work: Remodeled Campus – New facilities and renovation • New Construction: New Gymnasium, Educational Complex, Band Hall • Renovation: Remodeling of existing classrooms, expansion of existing cafeteria and extra curriculum programs • Comments: No portable buildings required

  4. R & T Martin High School • Architect: Sepulveda Assoc. Arch. • Contractor: To be determined • Design Status: Construction Document Phase Gymnasium and Academic Center • Budget: Construction Cost: $ 7,885,095 Soft Cost: $ 1,678,050 Total: $ 9,563,145 • Const. Start Date: May 2002 • Completion Date: Aug 2003 • Scope of Work: Remodeled Campus – New facilities and renovation • New Construction: New Gymnasium, Educational Complex • Renovation: Remodeling of existing classrooms, expansion of existing band hall.

  5. Cigarroa Middle School • Architect: Ashley Humphries & Sanchez • Contractor: To be determined • Design Status: Construction Document Phase – Academic classroom additions • Budget: Construction Cost: $ 3,424,319 Soft Cost: $ 728,740 Total: $4,153,059 • Const. Start Date: April 2002 • Completion Date: Aug 2003 • Scope of Work: Remodeled Campus – New facilities and renovation • New Construction: New Gymnasium, Educational Complex • Renovation: Remodeling of existing classrooms, expansion of existing cafeteria and extra curriculum programs

  6. Christen Middle School • Architect: Sepulveda Assoc. Architects • Contractor: To be determined • Design Status: Construction Document Phase • Budget: Construction Cost: $ 7,223,636 Soft Cost: $ 1,537,283 Total: $ 8,760,919 • Const. Start Date: June 2002 • Completion Date: Aug 2003 • Design Population: 1350 Students • Scope of Work: 80% of existing campus will be new replacement middle school and 20% will be remodeling of existing buildings • New Construction: New middle school with Gymnasium, cafeteria, classrooms, administration area and support areas. • Renovation: Remodeling of existing historical building into classrooms. • Comments: Portable classroom buildings will be required for on-site displacement of students

  7. Lamar Middle School • Architect: Cavazos Architect & Assoc. • Contractor: To be determined • Design Status: Construction Document Phase • Budget: Construction Cost: $ 7,261,862 Soft Cost: $ 1,545,418 Total: $ 8,807,280 • Const. Start Date: May 2002 • Completion Date: August 2003 • Design Population: 1350 Students • Scope of Work: 80% of existing campus will be new replacement middle school and 20% will be remodeling of existing buildings • New Construction: New middle school with cafeteria, library, classrooms, administration area and support areas. • Renovation: Remodeling of existing gymnasium and classroom building • Comments: No displacement of students

  8. Memorial Middle School • Architect: Turner Hickey & Assoc. • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 8,968,097 Soft Cost: $ 1,908,527 Land Acquisition: $ 1,000,000 Total: $ 11,876,624 • Const. Start Date: Aug 2002 • Completion Date: Jan 2004 • Design Population: 900 Students • Scope of Work: 80% of existing campus will be new replacement middle school and 20% will be remodeling of existing buildings • New Construction: New middle school with Gymnasium, cafeteria, classrooms, administration area and support areas. • Renovation: Remodeling of existing historical building into classrooms and support/core facilities. • Comments: Portable classroom buildings will be required for on-site displacement of students. Historical designated school

  9. Milton Elementary School • Architect: Turner Hickey Architects • Contractor: To be determined • Design Status: Competitive Sealed Proposal Phase • Budget: Construction Cost: $ 5,246,865 Soft Cost: $ 970,670 Total: $ 6,217,535 • Const. Start Date: April 2002 • Completion Date: April 2003 • Design population: 850 students • Scope of Work: New Replacement Campus • Comments: Portable classrooms buildings introduced on site for partial on-site displacement of students – Asbestos abatement / demolition has started

  10. Santo Niño Elementary • Architect: Franks Architects, Inc. • Contractor: To be determined • Design Status: Competitive Sealed Proposals Phase • Budget: Construction Cost: $ 5,191,225 Soft Cost: $ 960,377 Total: $ 6,151,602 • Const. Start Date: April 2002 • Completion Date: April 2003 • Design population: 850 students • Scope of Work: New Replacement Campus • Renovation: Minimal renovation to ECC • Comments: No displacement of students

  11. Kawas Elementary School • Architect: Ashley Humphries Sanchez, Inc. • Contractor: To be determined • Design Status: Competitive Sealed Proposal Phase • Budget: Construction Cost: $ 4,211,386 Soft Cost: $ 968,619 Total: $ 5,180,005 • Const. Start Date: April 2002 • Completion Date: April 2003 • Design population: 850 students. • Scope of Work: Renovations and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas. • Comments: No portable building required

  12. Ligarde Elementary School • Architect: Ashley Humphries Sanchez Arch. • Contractor: To be determined • Design Phase: Construction Document Phase • Budget: Construction Cost: $ 3,388,153 Soft Cost: $ 779,275 Total: $ 4,167,428 • Const. Start Date: April 2002 • Completion Date: April 2003 • Design population: 850 students • Scope of Work: Renovations and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas. • Comments: No portable classroom building required

  13. K. Tarver Elementary • Architect: Cavazos Architects & Assoc. • Contractor: To be determined • Design Status: Construction Document Phase • Budget: Construction Cost: $ 4,606,191 Soft Cost: $ 1,059,424 Total: $ 5,665,615 • Const. Start Date: May 2002 • Completion Date: May 2003 • Design population: 700 students • Scope of Work: Renovations and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas. • Comments: Portable classroom buildings will be required

  14. H. B. Zachry Elementary • Architect: Design Group Int’l, Inc. • Contractor: To be determined • Design Status: Construction Document Phase • Budget: Construction Cost: $ 1,456,725 Soft Cost: $ 335,047 Total: $ 1,791,772 • Const. Start Date: April 2002 • Completion Date: August 2003 • Design population: 850 students • Scope of Work: Renovation and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas.

  15. Alma Pierce Elementary • Architect: Cavazos Architects & Assoc. • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 5,061,225 Soft Cost: $ 936,327 Total: $5,997,552 • Const. Start Date: July 2002 • Completion Date: August 2003 • Design population: 850 students • Scope of Work: New Replacement School • Renovation: Minimal upgrades to ECC • Comments: Total displacement of students to Temporary Campus # 1 Airport for the Academic year 2002 – 2003.

  16. J. C. Martin Jr. Elementary • Architect: Ashley Humphries & Sanchez Arch. • Contractor: To be determined • Design Status: Preliminary Design • Budget: Construction Cost: $ 1,997,044 Soft Cost: $ 459,321 Total: $ 2,456,365 • Const. Start Date: May 2002 • Completion Date: August 2003 • Design population: 850 students • Scope of Work: Renovations and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas. • Comments: No displacement of students

  17. Daiches Elementary • Architect: Turner Hickey Architects, Inc. • Contractor: To be determined • Design Status: Construction Documents Phase • Budget: Construction Cost: $ 5,191,225 Soft Cost: $ 960,377 Total: $ 6,151,602 • Const. Start Date: May 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: New Replacement School • Renovation Work: Minimal upgrades to ECC • Comments: Introduction of portable classroom buildings for on-site displacement of students will be required.

  18. Macdonell Elementary School • Architect: Ashley Humphries & Sanchez Arch. • Contractor: To be determined • Design Status: Design Development Phase • Budget: Construction Cost: $ 5,107,115 Soft Cost: $ 944,816 Land Acquisition: $ 360,000 Total: $ 6,411,931 • Const. Start Date: May 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: New Replacement School • Developments: Land acquisition • Comments: Portable buildings required for total displacement

  19. Bruni Elementary School • Architect: Sepulveda Architects & Assoc. • Contractor: To be determined • Design Status: Design Development Phase • Budget: Construction Cost: $ 5,107,115 Soft Cost: $ 944,816 Land Acquisition: $ 360,000 Total: $ 6,411,931 • Const. Start Date: May 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: New Replacement School • Developments: Land acquisition • Comments: Campus will be totally displaced to the temporary campus # 2 for the 2002 – 2003 school year.

  20. Ryan Elementary School • Architect: Design Group Int’l, Inc. • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 5,246,865 Soft Cost: $ 970,670 Total: $ 6,217,535 • Const. Start Date: August 2002 • Completion Date: August 2003 • Design population: 850 students • Scope of Work: New Replacement School • Renovation: Minimal upgrades to ECC • Comments: Total displacement to Lamar Middle School Campus

  21. Buenos Aires Elementary School • Architect: Franks Architects, Inc. • Contractor: To be determined • Design Status: Preliminary Status • Budget: Construction Cost: $ 5,759,585 Soft Cost: $ 1,065,523 Total: $ 6,825,108 • Const. Start Date: August 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: New Replacement School • Comments: Total displacement of students to Ochoa Elementary school site.

  22. Leyendecker Elementary School • Architect: Architects Plus, Inc. • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 4,488,315 Soft Cost: $ 830,338 Total: $ 5,318,653 • Const. Start Date: August 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: New Replacement School • Renovation: Minimal upgrades to ECC • Comments: Introduction of portable buildings for partial on-site displacement of students

  23. D. D. Hachar Elementary • Architect: Cavazos Architects & Assoc. • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 5,348,285 Soft Cost: $ 1,230,106 Total: $ 6,578,391 • Const. Start Date: August 2002 • Completion Date: August 2003 • Design population: 650 students • Scope of Work: Renovations and Additions • New Construction: New program additions (classrooms and gymnasium) • Renovation: Remodeling of existing classrooms and support areas • Comments: No displacement of students will be required.

  24. Heights Elementary School • Architect: To be determined • Contractor: To be determined • Design Status: Preliminary Design Phase • Budget: Construction Cost: $ 5,191,225 Soft Cost: $ 960,377 Total: $ 6,151,602 • Const. Start Date: May 2003 • Completion Date: August 2004 • Design population: 600 students • Scope of Work: New replacement school • Developments: Historical Designation • Comments: Displacement of students will be required – Land acquisition

  25. Sta. Maria Elementary School • Architect: Cavazos Architects & Assoc. • Contractor: Leyendecker Construction, Inc. • Design Status: Under construction • Budget: Construction Cost: $ 5,107,115 Soft Cost: $ 944,816 Total: $ 6,051,931 • Const. Start Date: October 2001 • Completion Date: August 2002 • Design population: 600 students • Scope of Work: New replacement school • Comments: Complete student displacement to temporary campus # 1

  26. Sanchez / Ochoa Elementary School • Architect: Sepulveda Architects & Assoc. • Contractor: Leyendecker Construction, Inc. • Design Status: Under construction • Budget: Construction Cost: $ 5,140,785 Soft Cost: $ 951,045 Total: $ 6,091,830 • Const. Start Date: October 2001 • Completion Date: August 2002 • Design population: 850 students • Scope of Work: New replacement school • Renovation: Minimal upgrades to ECC • Comments: Partial displacement of students to Ochoa Elementary School and addition of portable building

  27. Farias Elementary School • Architect: Ashley Humphries & Sanchez Arch. • Contractor: Leyendecker Construction, Inc. • Design Status: Under construction • Budget: Construction Cost: $ 4,594,395 Soft Cost: $ 849,963 Total Cost: $ 5,444,358 • Const. Start Date: October 2001 • Completion Date: August 2002 • Design population: 650 students • Scope of Work: New replacement school • Renovation: Minimal upgrades to ECC • Comments: Total displacement of student to temporary campus # 2

  28. Dovalina Elementary School • Architect: Design Group Int’l, Inc. • Contractor: Leyendecker Construction, Inc. • Design Status: Under construction • Budget: Construction Cost: $2,806,612 Soft Cost: $ 389,807 Total Cost: $3,196,419 • Const. Start Date: October 2001 • Completion Date: August 2002 • Design population: 600 students • Scope of Work: Program additions (New gymnasium, cafeteria, classrooms) • Renovation: Administration area, library and existing classrooms • Comments: No displacement of students

  29. Technology Center • Architect: Pending • Contractor: To be determined • Design Status: Pending • Budget: Construction Cost: $1,275,000 Soft Cost: $ 293,250 Total Cost: $1,568,250 • Const. Start Date: To be announced • Completion Date: To be announced • Scope of Work: New state of the art technology center for the instruction of computer science and to house support facilities

  30. Food Service – Central Kitchen • Architect: Pending • Contractor: To be determined • Design Status: Pending • Budget: Construction Cost: $3,750,000 Soft Cost: $ 862,500 Total Cost: $4,612,500 • Const. Start Date: To be announced • Completion Date: To be announced • Scope of Work: New state of the art central kitchen and support facilities

  31. Transportation Department • Architect: Pending • Contractor: To be determined • Design Status: Pending • Budget: Construction Cost: $495,000 Soft Cost: $113,850 Total Cost: $608,850 • Const. Start Date: To be announced • Completion Date: To be announced • Scope of Work: Transportation bus depot for parking of district transportation fleet and support facilities to complement existing mechanic yard.