TDC2/TCC2 WG status report in EATM

TDC2/TCC2 WG status report in EATM. S. Evrard on behalf of the TDC2/TCC2 WG 18.06.2013 WP breakdown TDC2/TCC2 Visit on June 4 th Next issues ENTM agenda. Work package breakdown. Visit on June 4th: TCSC dose rate measurement by means of Telerob. TCSC contact : 11 mSv /h.

natane
Download Presentation

TDC2/TCC2 WG status report in EATM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TDC2/TCC2 WGstatus report in EATM S. Evrard on behalf of the TDC2/TCC2 WG 18.06.2013 WP breakdown TDC2/TCC2 Visit on June 4th Next issues ENTM agenda

  2. Work package breakdown

  3. Visit on June 4th: TCSC dose rate measurement by means of Telerob TCSC contact : 11 mSv/h

  4. T4 measurement from RP – 4th June 2013 Ratio D/U ~ 1.8 M. Calviani / E. Nowak - TCC2TDC2 WG meeting

  5. New CE issue: the mezzanine flooris not water tight

  6. Cablingwork: tough working conditions

  7. Next actions, topics, issues • Laser scan of TA801 (Thursday 20/06) BE-ABP + DGS-RP • Survey Work package  EN-MEF + BE-ABP • New dose rate measurement (Friday 21/06, TBC) EN-HE + DGS-RP • Tech. Spec. for: • Underground IT network  EN-MEF + IT-CS • Chilled pipe removal (asbestos ?)  EN-CV • Dismantlingworks  EN-MEF + DGS-RP • TCSC and Target boxes and monitor storage in B.954  GS-IS • PVC insulationanalysis TE-EPC + EN-MME • Mezzanine floor water tighness issue  GS-SE + EN-CV • Riskanalysis (cranes BA80, B954)  EN-HE • Shielded containers for target boxes and monitors  EN-STI + EN-MEF + DGS-RP • ENTM on July 2nd all WG members

  8. ENTM agenda July 2nd • Rationales for TDC2 Consolidation (S. Evrard) • PlannedActivities (E. Harrouch) • ALARA Optimisation (S. Evrard) • Transport Issues (J-L Grenard) • Waste management (E. Harrouch) • Riskanalysis (E. Harrouch)