Moving Archive Data to the EMC Storage ArrayMarch 14, 2003 Faith Abney Implementation Review
Motivation for Migration • EMC has higher availability and throughput • Less downtime • Data gets to users quicker • More online processing space available on EMC • Current processing areas not large enough to process all retrieval requests when they are submitted • Requests are routinely queued and held until processing space is available Implementation Review
Portion of EMC array to be used for faster access to Archive data • Currently all data is on MO platters in jukeboxes • Limited by number of platters mounted • Slow read/write access • Greatly affected by hardware downtime • Moving data to the EMC array will eliminate these bottlenecks which are due to data being in a jukebox Implementation Review
Portion of EMC array to be used for faster access to Archive data • Calling this area the “Data Depot” to avoid confusion with other staging areas • DADS will check this area first (DADS 10.1) • if files are available will use them • if not, it will get them from MO • Ingest software will be updated to write appropriate data to the depot after write to MO (DADS 10.1) • Data to depot will come from read of MO platter, verifying the write to MO Implementation Review
Data going to the Depot • All POD files (raw science data) for instruments with OTFR – 1.5 TB • ACS, NICMOS, STIS, WFPC2 • All legacy data - .5TB • GHRS, FOS, FOC, WFPC, HSP, AST • Calibration reference files - .15TB • FUSE data - .3 TB • Jitter files, Metadata - < .1TB • Mission scheduling data < 50 GB • SMS, MTL, MSC, ORB Implementation Review
Data not going to the Depot • Some data is rarely requested and does not need faster access: • Calibrated data for which OTFR is available • Raw Engineering data • Log and Ancillary data Implementation Review
Methodology: Requirements • Any movement of Data from MO platter to EMC will compete with both Ingest and Distribution for Jukebox access. • Migration should not prevent operations from meeting performance goals. • Migration of data off jukebox can proceed as background task • Task becomes high priority if jukebox failure rate begins to impact performance goals in operations. • Migration should allow for selection of highly requested data classes to be segregated and moved first. • POD files (raw science) for OTFR prime candidate to reduce overall retrieval times. Implementation Review
Methodology: Options • MMM server within NSA • Used to populate MO from older Sony media • Required manual intervention for simultaneous efficient operations and transfer performance • Well understood operationally • Bulk copy using primary platters • Same copy mechanism used for other mirror archives (CADC, ECF) • Not a routine operational procedure, manual intervention • DADS 10.* beta test environment • V280R loading uncertain • Rapid Test and Build cycle for beta test environment • Copy from safe store platters using DADS 9.* test environment. • Highly manual (requires platter loads) • No operational impact (impacts testing schedule only) Implementation Review
Methodology: Prescription • Perform trade studies to evaluate the quickest and least intrusive method. • Develop contingencies to accelerate transfer should jukebox failures become more frequent. • Initiate transfer and develop a good understanding of maximum transfer rate before predicting a completion date. • Lessons learned from MO migration • Note that DADS 10.1 delivery makes transfer progress non linear! Implementation Review
Schedule • DADS 10.1 – scheduled for Spring – contains: • Software to populate Depot on ingest • Software to be able to read from the Depot • Tools to migrate existing data to Depot already written • Migration can start as soon as EMC Depot is connected to operational system • Migration completion estimate will be prepared after we complete acceptance testing and get actual performance numbers using the EMC and our tools Implementation Review