Communication in Substations: IEC61850 1.4 : INTEROPERABILITY. Sudhakar RAMPURKAR / AnshumanBHALLA 26th & 27th October 2009. Interoperability.
E N D
Communication in Substations:IEC618501.4 : INTEROPERABILITY Sudhakar RAMPURKAR / AnshumanBHALLA 26th & 27th October 2009
Interoperability • Ability of two or more IEDs from the same vendor, or from different vendors, to exchange information and use that information for correct execution of specified functions Has a DATA MODEL model that can be accessed Request IED Intelligent Electronic Device Response The WHAT to exchange (IEC 61850-7-3 &4) Event The HOW to exchange (IEC 61850-7-2)
IEC 61850: Interoperability, cont. I • What is needed for interoperability • Common standardised: • Language (data model) • Services (service model) • Protocol • Communication medium • Engineering data exchange • Conformance test • IEC 61850 standardised these needs
IEC 61850: Interoperability, cont. II • IEC 61850 does not automatically ensure interoperability • To reach interoperability a well-done engineering is necessary • IEC 61850-4 System and project management Clause Engineering Requirements • IEC 61850-6 Configuration description language for communication • Conformance Testing will be an important part to provide interoperability • IEC 61850-10 specifies the conformance testing
IEC61850 documentation needed Protocol ImplementationConformanceStatement (PICS) • Summary of the communication capabilities of the system or device (for testing) • Protocol Implementation eXtra Information for Testing (PIXIT) • Communication capabilities of the system or device which are outside the scope of the IEC 61850. The PIXIT shall not be subject to standardisation Model ImplementationConformanceStatement (MICS) • Details the standard data object model elements supported by the system or device Tissue Implementation Conformance Statement (TICS) • Details the Tissues (Technical Issues) that the IEC61850 implementation has incorporated
7 Layer Open Systems Interconnection model P444 P632 P143 IEC 61850 mapping of the device created from the ICD – file (MICS) Manual: Ethernet module IEC 61850 EN100 electrical (incl. PICS) Supported communication services Goose, Report-model, time – Synchronisation. Actual mapping of the device. Written version of the ICD – file generated for the specific device. P444 P632 P143 IEC 61850 Mapping of the device for test purposes (PIXIT) Start up IEC 61850 manual Description for the type conformance test.
Testing of IEC 61850 Systems • IED Protocol Implementation Testing • IED Object Models Implementation Testing • IED Functional Testing • Distributed Applications Testing • System Testing
Sample KEMA certificates P634 C264P Acrobat document Acrobat document
Conclusions • Conventional testing requires hard wiring, while in IEC61850, it may be partially or completely communications based. • Comparison between the performance of hard-wired and communications based solutions is required to confirm that IEC61850 can be successfully used to replace conventional substation control and protection systems without any degradation in the overall performance of the system.