1 / 17

Status of Neutrino Beamline Construction

Status of Neutrino Beamline Construction. K. Nishikawa IPNS, KEK 2006 . 12 . 4. The Neutrino Beam-Line. Target-Horn System. Target Station. Muon Monitoring Pit. Final Focusing Section. 295km to Super-Kamiokande. Preparation Section. 100m. SCFM at ARC Section. Beam Dump.

neil-alston
Download Presentation

Status of Neutrino Beamline Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of Neutrino Beamline Construction K. Nishikawa IPNS, KEK 2006.12.4

  2. The Neutrino Beam-Line Target-Horn System Target Station Muon Monitoring Pit Final Focusing Section 295km to Super-Kamiokande Preparation Section 100m SCFM at ARC Section Beam Dump Decay Volume Near Neutrino Detector

  3. Components Primary proton beam line Normal conducting magnets Superconducting arc Proton beam monitors Target/Horn system Decay pipe Beam dump muon monitors Near neutrino detector Special Features Superconducting combined function magnets Off-axis beam (2~2.5deg) Construction: Apr.2004~Mar.2009 Neutrino Beam Line for T2K Experiment Target Station decay volume 280m Beam dump/m-pit Near detector To Super-Kamiokande

  4. Primary beam line • Preparation section • NC magnet,2D(H),5Q,4str • 750W loss • Arc section • 28 superconducting combined function magnets • D2.6T,Q18.6T/m, L=3.3m • 1W/m loss • FF section • NC, 2D(V), 4Q, 4str • 250W loss • Bending • H: 84.5o • V: 3.1~3.6o downward in FF sect. (OA angle 2~2.5o) • Proton beam monitors • Intensity, Profile, Position, Loss

  5. Tunnel for Primary Beam-line Preparation Section 50GeV Preparation Section Extraction area Arc Section Final Focus Section

  6. Primary line components • Normal-conducting magnets - Installation in coming July for preparation section - Fabrication of FF magnets in progress, and to be installed in FY2008. • Power supply - Spec. examination for assignment to magnets be done • Vacuum - Beam pipe installed in magnets for prep. - Intra-magnet beam pipe being designed. • Beam plug - ready for installation in coming summer • Collimator - re-examining aperture due to optics change.

  7. Superconducting magnets and cryogenics • SC magnets • R&D since 2001 • Successfully developed and tested • Mass production started in FY2005 • 17 magnets completed • 6 “doublet” (2mag in 1 cryostat) completed • Installation in FY2008 • Cryogenics • Design completed • Contract made • Manufacturing started Cryo. Sci. C. and Cryo. G., IPNS

  8. Beam Monitors • Configuration - Position : Electro-static monitor (ESM) - Profile : Segmented Secondary Emission Monitor (SSEM), OTR - Intensity : CT - Loss monitors (BLM): Ion. chamber • Status - ESM : ESM#0 and ESM #1 successfully made and tested Bidding for all Prep ESM in progress - SSEM Chamber bidding be placed soon Moving mechanisms of SSEM for super-conducting parttested and moved smoothly at liquid-nitrogentemperature. Moving mechanism for normal-conducting part also tested. To be adopted with several minor modifications. OTR

  9. Secondary Beam Line Beam Dump(BD) •graphite core in helium vessel TS BD DV Target station (TS) •Target & horns in helium vessel Decay Volume (DV) •94m long helium vessel •6m thick concrete shield Muon monitor in muon pit • Civil construction of underground part will finish soon. • (10cm thick iron) • Helium vessel being manufactured • 50m part already constructed • Civil construction of downstream part just started Spill-by-spill monitor of muon intensity/profile

  10. Target Station Top part Bottom part Cooling channels • Civil construction of • underground part will finish soon. • He vessel will be installed • from Aug. 2007. • Helium vessel is being manufactured • at the factory.

  11. Target Graphite 26mm(D)x900mm(L) Heat load: 58kJ/spill (~20kW) Thermal shock (DT~200K) ~ 7MPa (<Tensile strength 37MPa) Forced flow Helium gas cooling Remote maintenance The target full prototype is being manufactured. The He circulation system achieved >200m/s flow at the (imitated) target surface. Installation in FY2008 Prototype

  12. Electromagnetic horns target Beam Horn1 Horn2 Horn3 • As endurance test, 1st horn prototype have been operated with 8.5E5 pulses without serious troubles. • The 3rd Horn was produced and connected serially with the 1st horn. • The long term test at 320kA with this configuration just started and will continue until the end of August. • The 320kA operation with full setup at Fuji-Hall is being prepared. 3rd Horn 1st Horn • The support module for the 3rd horn was produced. • This 12tons iron box hangs the 3rd horn.

  13. Decay Volume • 94m-L iron helium vessel cooled by water • 6m concrete shields • ~150kW heat on iron walls and concrete • Middle part (50m-L) was already constructed. • Construction of most upstream and downstream parts just started. Cooling channels Middle part (50m-L) Feb. 2005 Most upstream part

  14. Beam Dump / Muon Monitor Beam dump Muon monitor • 98 graphite blocks cooled by Al modules. • Production of Graphite blocks finished. • First module was assembled. • Machining of graphite blocks: FY2007 • Production of cooling modules: FY2007 • Fabricationof He vessel plates: FY2007 • Assemble/installation: FY2008 Graphite blocks First module • Two Independent System • Semiconductor detector array • Ionization chamber array • Spill –by-spill monitor for the muon profile center • Prototype being tested w/ beam

  15. Neutrino Detector: ND280 10m • Detectors • On-axis • neutrino profile measurement • Off-axis • measure neutrino on the direction • to Super-Kamiokande before • neutrino oscillation • Design is in progress and will be • fixed soon. • Technology • Scintillator + WLS opt. Fiber • + Multipixel APD • (new photo sensor) • test of samples before mass • production is being performed • TPC with micromegas • --> prototype is being build 17.5m Off-axis 0.2T B1 23m On-axis 29m B2 Beam 33m B3 • Civil construction • will start soon.

  16. Schedule of n beam line • Beam dump & • half of Decay vol. • const.: ’07~’08 • Install: ’08 • Target station • const.: ’06~’08 • Install: ’08 • Near detector • const.: ’07~’08 • Install: ’08 • Proton beam line • const.: ’05~’06 • Install: 07, ’08 2004.4-2006.3 2005.4-2007.3 • half of Decay volume • const.: ’04~’05 • Install: ’04 2006.4-2008.3 2007.4-2009.3 • Buildings • Const.: ’07

  17. Summary • Beam line construction is on schedule • No fatal problem so far • Superconducting/normal magnets are being manufactured • Production of other components are in progress or in preparation • Civil constructions are on schedule. • Almost all components will be installed in FY2008 • Beam will start in Apr. 2009

More Related