Sustainable IT @ Stanford

Sustainable IT @ Stanford. What’s IT got to do with Sustainability?. May 3, 2012 Joyce Dickerson, Director, Sustainable IT Stanford University. Savings from Sustainable IT – to date. Electricity Savings from Sustainable IT. Chilled Water Savings from Sustainable IT.

nelson
Download Presentation

Sustainable IT @ Stanford

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sustainable IT @ Stanford What’s IT got to do with Sustainability? • May 3, 2012 • Joyce Dickerson, Director, Sustainable IT • Stanford University

  2. Savings from Sustainable IT – to date Electricity Savings from Sustainable IT Chilled Water Savings from Sustainable IT

  3. Savings from Sustainable IT – to date Energy to cool 13,000 servers for 1 year Electricity to power 10,000 servers for 1 year

  4. The Goal: Sustainable IT = Core Operating Practice Support Research & Learning Operate Campus Sustainably Drive Infrastructure Efficiency Educate Communities Broadly Stanford Sustainable IT

  5. Intentionally Dual-report SEM /LBRE ITS/BA Sustainability & Energy Management IT Services Sustainable IT Team Sustainable IT • Facilities • Motivation, staff and money • Energy supply and building demand • Operations • Funding • IT • Equipment & rooms • Right to say ‘no’ • Sustainable IT Team • IT Leads across org (12 -->115) • Know the issues • Make it happen • Projects driven by • Payback • Incentives & rebates (internal and external) • Contribution to Sustainable Story

  6. The Goal: Sustainable IT = Core Operating Practice

  7. Building the Program • Build a Team • Build Alliances • Quantify the Problem • Build a Framework • Find a ‘Quick Win’ • Communicate • Look for Opportunities/Continuous Improvement • Deliver & Report

  8. First Project -- Quantify the Problem IT electricity use ~15% of campus total … and growing rapidly, especially research computing

  9. Build a Framework & Roadmap • Priority Projects • Desktop Computing • Power Management • Vampire Power • Climate Savers • Administrative Computing • Facility: Datacenter • Servers: Virtualization • Research Computing • Server Rooms • Research Compute Facility • All • Incentives for Action • Future Projects • Networking • Storage • Server Hardware (The “1”) • Efficient UPS • Generators • Office Equipment • A/V Equipment • Conferencing • Telecommuting

  10. Quick Win: Desktop Power Management • Central management installed on 23,000 computers • 88%: Monitors off automatically (15 mins) • 50%: Standby Enabled • >80% EPEAT • Keys to Project Success • Dept IT ‘led’ the project • Feedback: Dept Rankings • Cultural fit: Local Control Credit: iStock iPhoto; used with permission

  11. Datacenter: Energy Efficiency Retrofit • 2008: • 20,000 square foot datacenter • Raised Floor • Cooling: 13 CRAH Units • Mostly Admin Computing • Some Research • Rack Orientation: Some hot/cold • Little focus on energy use • Minimal environmental monitoring • Three temperature gauges on the wall • 2009: • Kicked Off Energy Efficiency Project • Measures Taken: • Monitoring • Temperature monitors throughout • Datacenter Dashboard • Air Flow & Temperature • VFD’s on CRAH units – running at 75% • % Outside air increased • Water chilled racks raised to 74 • Average Ambient air temp raised to 74 • Containment • Replaced aging ceiling tiles (cleanroom) • Better aligned floor and ceiling tiles, relentless blanking panels • End-aisle doors (bathtub) PUE 1.4 PUE 1.8

  12. Datacenter: Energy Efficiency Retrofit • Keys to Success: • Team = Facilities + IT Staff • Project manager from IT • Funding from facilities • Visibility to overcome concerns • Turned meter readings into meaningful charts Total Cost of the Project$336,428 Est Annual Energy Savings $175,000 Simple Payback 1.9 years Incentives from PG&E $ 36,428 Incentives from Stanford$275,000 Net Cost to Department $ 25,000 Annual kWh Savings 1,842,105 kWh

  13. Look for Opportunities: Debunk a Widely Held Belief • Tension between IT and Departments • “Don’t believe it just because they say it” • Server Room Study  Design matters • Server/Telecom Room Facility Design Guide (led by facilities) • Turnkey Retrofit kit for Server Rooms • ERP Incentives to move to SRCF “Servers Rooms are inherently inefficient and everything should move to central datacenter” Cost/kW/year=$2390 Cost/kW/year=$1171

  14. Satellite Server Rooms – Summary Table 1.65 1.99 1.54 2.63 1.38 0.2% 12% 100% 15% 2.7% 7% 14% 100% 22% 41% $19,029 $62,875 $71,995 $141,918 $261,387 $153 $125 $133 $196 $96

  15. Quantified & Shared the Cost of Running Servers

  16. Listen for Opportunities: Software Site License • Department Suggested Virtualization Site License….. • The Challenge • Pockets of virtualization deployed • Three solutions deployed • No central funding source • Inconsistent channel and pricing • Tried, and failed, in 2009 -- “it can’t be done” • The Strategy • Find out who ‘cares’ • Structure the deal – “what they expect to pay” • Pass the hat – 6 departments • The Result • The time was right • Distributed software worth over $4 million in first 4 months

  17. Impact of VMware Enterprise License Agreement Forecasts ELA • VMware ELA Stats: • $4,270,104 software to 14 departments (6 months into 3 year term) • ~400 people downloaded free VMAP software • Two types of virtual desktop services now available • VMware software now in SmartMart • The VMware portal up and running

  18. Server Virtualization Rates Vary Widely

  19. Energy Incentive Programs Stanford Energy Retrofit Program (ERP) Pays you to do Energy Efficiency Projects • 5 Years of Energy Savings • Server Room Retrofit • hot/cold aisle containment • VFDs • Controls • Server Room Relocation to SRCF • - Room converted to non-T space • UPS Replacement • - >90% energy efficient models • 3 Years of Energy Savings • Computers, Servers, Storage • 80+ Platinum Power Supplies • Desktop Virtualization • Server Virtualization • Purchase Energy Star Models • Energy efficient designs • Open to new ideas

  20. Project 6 – UPS for IT Services Project: Replace aging 500 KVA UPS with Energy Efficient 500 KVA model

  21. Project 6 – UPS for IT Services – Payback Analysis • Mitsubishi 9900B recommended • May be additional construction costs, but have $233,000 available for installation of $136,000 UPS • Price Quote from ProPower • Able to replace UPS without interrupting power to facility

  22. Rebate & Incentive Programs Sustainableit.stanford.edu Joyce Dickerson -- jdickerson@stanford.edu

  23. Lessons Learned • Be Structured, but Flexible • Dare to Challenge • Think Big • Share • Be Inclusive • Know the Culture • Document Results ($) • Talk in their Language • $$ • Carbon • Payback • kWh • Efficiency • Green House Gas

  24. Updated Sustainable IT Website Sustainableit.stanford.edu sustainableit@stanford.edu

  25. What Next? • LBRE and IT Services committed to continuing Program • Committee to determine next steps: • Matthew Ricks – IT Services • Gerry Hamilton – Facility Energy Management • Fahmida Ahmed – Office of Sustainability • Bob Burkhardt – School of Medicine • Reed Sprague – School of Engineering • Matt Riley – School of Humanities & Sciences