190 likes | 303 Views
King George Wireless Authority. Joseph W. Grzeika Chairman King George Board of Supervisors. Background. In mid 90’s Board of Supervisors added requirements on all new cell phone tower special exceptions to allow county use of tower for county communication purposes
E N D
King George Wireless Authority Joseph W. Grzeika Chairman King George Board of Supervisors
Background • In mid 90’s Board of Supervisors added requirements on all new cell phone tower special exceptions to allow county use of tower for county communication purposes • By early 2000’s Internet Access was becoming more of an expected “utility” vice “nice to have”
Background Continued • 2003 General Assembly enacted Wireless Service Authority Act (Code of Va. 15.2-5431.10) • 2007 General Assembly added Wireless broadband equipment and infrastructure to definition of Public Private Education Facilities and Infrastructure Act (PPEA)
Project Summary • 2006 King George formed Wireless Authority • Board of Directors are the Board of Supervisors • Identified need; • Private suppliers (Verizon, Cable franchisee, and satellite) not serving many rural areas of county • Economic Development impacted by availability of broadband in county • Defense Contractors and employees need reliable broadband access at work and home • Commercial sector reliant upon internet • Sheriff/EMS/Schools/County Admin needs reliable county wide access to broadband
Project Summary (Continued) • 2006-2007 Board developed and issued Request for Qualifications • Asked for vendors to propose solutions that would achieve 95% geographic coverage • Public-Private partnership desired • Open to all approaches that achieve the goals
Project Summary (Continued) • 4 Proposals received and evaluated • Various responses, pure fee for service, franchises, etc • Virginia Broad Band selected, regional wireless company
Project Summary (Continued) • Spring 2007 • Worked with VABB to develop contract • Identified existing assets (Communications and County Service Authority Towers) • Network deployment goals • Financing plan • December 2007 • Finalized deal Conceptually
Project Summary (Continued) • January 2008 Wireless Authority/VABB sign Contract and close on financing • VABB responsible for development and implementation of Network • VABB responsible for all marketing, customer service, billing • Authority obtains Financing (Loan to VABB due to Authority repayment schedule in contract) • $740,000 obtained through local bank, incremental disbursement based on schedule of activity • Authority has applied for Stimulus funds – none received to date
Project Summary (Continued) • Spring 2008 • VABB Commences deployment • Pilot equipment installed • Summer 2008 first subscribers signed up and VABB works with Schools to provide portion of their network
Project Summary (Continued) • Summer 2008 • Tower Owners raise issues with access despite provisions • VABB continues installation on unaffected towers and increase customer base • Authority works through the legal issues with tower access
Project Summary (Continued) • Current Status • Issues with all but 1 of the Towers resolved through negotiation • VABB is operational on 4 towers • In process of deploying on 4 additional towers (operational by end of calendar year)
Project Summary (Continued) • Current Status (Continued) • 1 tower still in dispute • County provides access to towers identified as Phase 1 in contract • VABB responsible for marketing and network operations
Project Summary (Continued) • Status • Delay in access to towers has impacted deployment schedule: • 70% geographic coverage in Phase 1 delayed almost 1 year • Authority will conduct Network Assessment Acceptance Test upon completion of Phase 1 to ensure coverage met • VABB to provide Authority with regular progress/financial reports per contract
Project Summary (Continued) • Status (Continued) • Work Outstanding • Phase 2 completion (95% geographic coverage) • Network Service to Governmental Agencies • Free/discounted service/training to Digital Inclusion Residents • VABB assumes payment for Phase 2 facilities • Procure follow-on Network Agreement
Challenges/Lessons • Tower agreement provisions need to be as broad as possible to allow Authority use • Competitors will react to deployment • Local cable provider aggressively deploying fiber; but not seeing them expand their coverage to less dense areas • Verizon does not seem interested in rural county • Broad Band is the new Utility Service residents expect
Challenges/Lessons (Continued) • Provider needs to be in tune with the market and step up to serve the new areas • Rural areas pose technical challenges that the provider needs to solve: • Terrain • Tree Canopy • New Equipment/changes to Technology • Small (5-20 house clusters) • Customer Service – reflects on the county
Challenges/Lessons (Continued) • Deployment takes much longer than you expect – manage expectations • Establish customer service and marketing requirements in the contract • Competitive Environment poses challenges to obtaining reports/data while protecting the provider’s proprietary information
Conclusion • Broad Band is the “New Utility” • Rural Markets are not high on the commercial providers priority due to the density/business payoffs • Tower Access Key • King George Still a work in process • Questions?