An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Movex Stepping-up Project2007-2008 Peter Mason Joint CEO & Finance Director FW Thorpe plc

  2. Who are FW Thorpe plc? • My role • Original Movex Implementation • Stepping-up Project • Why? • Goals • Process • Results • Future plans

  3. Who are FW Thorpe plc • Listed on the Alternative Investment Market • “Family Company” established 1936 • Turnover £50 million • Profit £12 million • 500 Employees • UK based

  4. Who are FW Thorpe plc • Manufacturers of professional lighting systems • Gas lighting -> discharge lighting -> fluorescent lighting -> LED’s • Sheet metal “bashing” -> web monitoring of emergency lighting systems • Energy saving solutions for lighting

  5. Who are FW Thorpe plc • Sales: 80% Home / 20% Export • 5 UK factories • 2/3 of business at Thorlux Lighting, Redditch – (uses Movex) • Other business units use small business systems

  6. Thorlux Lighting • Lighting for offices, schools, hospitals factories, warehouses, tunnels, power stations & outdoor areas • Specification market • Customers • Stock

  7. My role • Joined company 1987 • Project responsible • Original implementation • Stepping-up project

  8. Original Movex implementation • History of business process • 1936 to1960’s • 1960’s to 1970’s • 1980’s to 1990’s • 1998 Movex implementation • 2007 to 2008 M3 Stepping-up project

  9. Original Movex implementation

  10. Original Movex implementation • Business process • Selection • Hardware – AS400 • Software • Operating system • Movex version (10.8 Explorer) • Reporting (Cognos) • Documents (Autoform) • Result

  11. Original Movex implementation • “Vanilla” Movex • Movex modules • Manufacturing/ SOP/ Stock control/MRP/Finance • Export documentation • Kits • Make to order/make for stock • Dates

  12. Original Movex implementation Financial Results –FW Thorpe

  13. Stepping-up Project – why? • “If it ain’t broke…….” • Explorer • Response • Capacity

  14. Stepping-up Project – goals

  15. Stepping-up Project – process

  16. Stepping-up Project – process & Workplace

  17. Stepping-up Project – process

  18. Stepping-up Project • Results • Measure of success • Future plans • Advice to others