D-R Compressor Cel l

D-R Compressor Cel l. RIT Senior Design Team P13458 Week 4 Status Report. Agenda. Review of activities thus far Short term goals Questions / Requests. Project Summary. Overall goal of project:

nerina
Download Presentation

D-R Compressor Cel l

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. D-R Compressor Cell RIT Senior Design Team P13458 Week 4 Status Report

  2. Agenda • Review of activities thus far • Short term goals • Questions / Requests

  3. Project Summary • Overall goal of project: • Transform their fixed material position assembly process for their gas application reciprocating compressors into a flowing cell layout • Motivations: • Prepare for a projected increase in demand for their newly released MOS compressor • Create a safer environment for the operators (no overhead cranes) • Increase their on-time delivery rating • Specific Task: • Create the material handling system that will allow the assembly to travel through this cell and will support the lean manufacturing initiatives this project is pursuing Note: A consultant has created a conceptual design of the process flow through this cell.

  4. Customer Needs

  5. Concept Selection – Moving

  6. Concept Selection – Propulsion

  7. Concept Selection – Loading

  8. Goals for next 2 weeks • D-R Approval for customer needs, functional decomposition • Specifications definition from D-R • Develop solutions based on feedback from D-R • Risk Management • Schedule Systems Design Review • Create Systems Design Review Presentation

  9. Requests • Data on Cylinder weights for all families • Data Cylinder dimensions for all families • Is there an expectation for future line expansion?

  10. Project Requests Requests: • Review customer needs & provide feedback • Review functional decomposition & provide feedback • Specifications and constraints definition to meet customer needs • Ideas: time to move, size envelope for system within layout, no overhead crane, no monuments

  11. Next Steps • Systems Design Review • Tentatively Scheduled Friday, January 18th