Central Texas Turnpike Project Tour 2005. Donald C. Toner Jr., SR/WA Right of Way Administrator Texas Department of Transportation. Central Texas Turnpike Project Austin District Phone: (512) 225-1361 FAX : (512) 225-1400 email: dtoner@dot.state.tx.us. Teri J. Morgan SR/WA, R/W-RAC
E N D
Donald C. Toner Jr., SR/WA Right of Way Administrator Texas Department of Transportation Central Texas Turnpike Project Austin District Phone: (512) 225-1361 FAX : (512) 225-1400 email: dtoner@dot.state.tx.us
Teri J. MorganSR/WA, R/W-RAC EDA ROW / Utility Manager HDR Engineering Phone: (512) 225-1366 FAX : (512) 225-1400 email: t.morgan@HDRInc.com
Central Texas Turnpike Project Construction ROW • SH 130 $1.4 bill $389 mill • Loop 1/SH 45N $1.2 bill $145 mill • SH 45 SE $154 mill $40 mill
CTTP Office Impact • Over 2,000 FTEs at peak • Over $2 Billion Bond Package • $916 Million TIFIA Loan from US DOT • Over $220 Million from Local Public Agencies • $500 Million Budget for ROW and Utilities
SH 130 Impact • Move 30 million CY of dirt • Build 433 lane miles • Place 2.7 million SY of Concrete • Lay 1.7 million tons of Asphalt • Erect 590,000 sf of retaining wall • Install 150 new signals
SH 130 Impact continued • Build 119 bridges • Construct 14,000 sf of new Buildings • Construct 4 Mainlane Toll Plazas • Construct 30 Ramp Plazas
1 2 3 4 5 6 SH 130 Segments • 6 Segments • 91 Miles • 4-Lane divided, Controlled- • Access Turnpike • 103’ Median • Discontinuous 2-Lane • Frontage Roads • 8 Major Interchanges
SH 130 • NTP1 Issued July 8, 2002 • NTP2 Issued January 4, 2003 • NTP3 Issues December 30, 2004 • Construction began on October 3, 2003 • NTPs Issued for $999 Million • Change orders for 52.5 Million (5%) • LSI has earned 34% of contract amount and used 46% of contract time • Contractor: Lone Star Infrastructure, JV
SH 130 – ROW Summary Nov. 2004 Mar. 2004 Feb. 2005 Apr. 2005 • Parcels 410 408 407 408 • Surveys Completed 276 359 364 364 • Appraisals Approved 197 321 334 346 • Offers Made 153 310 329 343 • Offers Accepted 68 126 150 162 • Condemnation Packages Approved 50 215 235 251 • Parcels Acquired 39 163 199 230 • Possession & Use Agreements 12 23 46 44 • Parcels available for Construction 51 186 245 274