Stay informed about the progress in East Hall construction, de-cabling, and renovation activities. Detailed overview of ongoing work in B.352 and B.157. Project Team meeting highlights and updates on the East Area Renovation schedule. Any questions? Get in touch now!
E N D
East Area Renovation: Project Team meeting #31News from East hall, b.352 & b.157 East Hall under construction - 1962 Aboubakr Ebn Rahmoun / EN-EA, 20-09-2019 East Area Renovation
Activities overview • B.352 • De-cabling stopped to the trench of PS pending cleaning asbestos, 95% completed • Renovation of the ground for marking by EN-SMM • The shielding, beam lines and elements. B.157 Currently in the primary area : De-cabling campaign and removal hoses will finish soon All magnets and supports are removed Dismantling walls & removal scaffolding during the night CLOUD run : Setup on going Project Team #31
Primary area Yesterday 26 July Project Team #31
EAR Schedule Project Team #31
Questions? East Area Renovation