Next Generation Adaptive OpticsMeeting #2CaltechNovember 14, 2006 P. Wizinowich for NGAO Executive Committee
Welcome - Participants • In-Person Participants • NGAO Executive Committee: Rich Dekany, Don Gavel, Claire Max, Peter Wizinowich • Sean Adkins, Antonin Bouchez, Ian Cameron, Mike Ireland, Anna Moore, Chris Neyman, Viswa Velur • Telecon Attendees: • Brian Bauman, Ralf Flicker, Erik Johansson, Franck Marchis, David Le Mignant, Mike Liu NGAO Meeting #2
Goals of Today’s Meeting • Introduce team structure & responsibilities • Review System Requirements document • Review key drivers for NGAO performance budgets • Review Keck Interferometer requirements • Review instrumentation study strategy NGAO Meeting #2
Meeting Agenda 08:30 Welcome & Introductions 09:00 Management Report (Wizinowich) 09:30 Science Requirements Document (Max) 10:30 Break 10:45 Key Performance Drivers (Dekany) 12:15 Lunch 13:00 LGS Asterism Geometry & Size (Flicker) 13:30 Fixed vs Variable LGS Asterism (Velur) 14:00 Keck Interferometry Requirements (Neyman) 14:30 NGAO Instrument Study Strategy (Adkins, Moore) 15:45 Break 16:00 Discussion: Upcoming tasks & milestones (Wizinowich) 16:30 General Discussion 17:30 Adjourn NGAO Meeting #2
NGAO System Design Phase Management Report P. Wizinowich for NGAO Executive Committee
Presentation Sequence • System Design (SD) Phase Systems Engineering Management Plan (SEMP) + Approval Status + Budget • Management Tools • WBS & tracking • Milestones • Work scope planning & approval • Document management • Science Requirements & Performance Budget Process NGAO Meeting #2
Systems Engineering Management Plan • Document describing how the Executive Committee (EC) plans to manage the SD phase • http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning NGAO Meeting #2
System Design Phase Approval Status • SEMP submitted to the Observatory Directors on 9/29/06 for approval • Official response not yet received (has been requested) • Major issue is how many $ can be made available in FY07 • Direction from WMKO management to proceed while decision is being made • Contracts (effective 10/1/06) to COO & UCSC need to be worked out NGAO Meeting #2
NGAO SD Phase: Budget $163 increase in cost of labor. Total work same as in proposal. NGAO Meeting #2
SD Phase - Work Breakdown Structure Each major WBS produces one of the 4 major deliverables of the SD Phase: 1 System Design Phase Management System Design Report 2 System Requirements System Requirements Document 3 System Design Approach System Design Manual 4 Systems Engineering Management Plan • Systems Engineering Management Plan WBS dictionary defines each element in WBS NGAO Meeting #2
WBS 1 SD Phase Management 1.1 Planning & Contracting 1.2 Meetings 1.3 Tracking & Reporting 1.4 Proposals & Fundraising 1.5 System Design Report & Review NGAO Meeting #2
WBS 2 System Requirements 2.1 Science Requirements 2.2 Observatory Requirements 2.3 System Requirements Document NGAO Meeting #2
WBS 3 System Design Approach 3.1 Systems Engineering 3.2 AO System 3.3 Laser Facility 3.4 Operations Tools 3.5 Science Instruments 3.6 System Design Manual NGAO Meeting #2
WBS 4 System Engineering Management Plan 4.1 Project Plan 4.2 Risk Assessment & Management Plan 4.3 Preliminary Design Phase Plan 4.4 Integration & Test Plans 4.5 Configuration Management Plan 4.6 Project Management Plan 4.7 Systems Engineering Management Plan NGAO Meeting #2
System Design Phase Tracking • Tracked version of the plan posted at http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning NGAO Meeting #2
NGAO SD PhaseMilestones NGAO Meeting #2
Team Meeting Calendar NGAO Meeting #2
Work Scope Planning & Approval • Template posted at http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/WebHome under “Systems Engineering” • To be prepared by WBS element lead & approved prior to performing significant work on a WBS element • In general these should be submitted at least 1 week prior to the MS Project start date • Approvals & document control by Dekany & Wizinowich • We will endeavor to provide approvals within 5 working days of submittal NGAO Meeting #2
Document Control • All materials to be posted on Twiki site • All significant items should be made Keck Adaptive Optics Notes & will also be archived on Keck’s docushare site (Wizinowich to provide KAON numbers) • Simple documents can use “Work Scope” template with “Keck Adaptive Optics Note XXX” at top of title block • SD phase deliverable documents should use SEMP document as a template NGAO Meeting #2
NGAO SD Phase:Science Requirements & Performance Budget Process NGAO Meeting #2
NGAO System Design Phase Upcoming Tasks & Milestones P. Wizinowich for NGAO Executive Committee
Upcoming Tasks • Work Scope planning sheets • These should be submitted for all WBS elements that need to start in CY06 by 12/8 • These include WBS elements under: • 2.1 Science cases • 2.2 Observatory requirements • 2.3 System requirements • 3.1.1 Performance budgets • 3.1.2 Trade Studies • 3.5 Science Instruments • Work on the scheduled WBS elements for CY06 NGAO Meeting #2
Upcoming Meetings & Milestones • Meeting #3 is a Dec. 13 telecon • http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061213_Remote_NGAO_Meeting_3 • Will need % complete for WBS elements prior to meeting • Milestones: • SD phase contracts in place was due 10/27 • Science requirements summary v1.0 was due 10/27 • System Requirements document v1.0 due 12/8 NGAO Meeting #2