An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Peak LAN Project Kirk Baringer Meagan Beeman Allison Benton Yolanda Boyd Thomas Guess

  2. Project Information • Peak Systems, located in Meridian, Louisiana • Information Systems Consultants • Project: City of Meridian’s social welfare agency • Goal: to build complete Local Area Network (LAN) • Budget $90,000 to be completed in 26 days

  3. Project Team Risk • Team Size • Three people • Team Composition • Project Manager and two interns • Is this enough manpower?

  4. Project Team Risk • Team Size • Three people • Team Composition • Project Manager and two interns • Is this enough manpower?

  5. Project Team Risk • Team Size • Three people • Team Composition • Project Manager and two interns • Is this enough manpower?

  6. Budget Risk • Established budget is $90,000 • Do not cut corners • Cheaper Hardware • Hardware and Software compatibility • Hardware reliability • Is this a realistic budget?

  7. Timeline Risk • Project complete in one month • Allot of hardware • Hardware • Locating and purchasing • Delivery • Testing • Multiple suppliers • Is this enough time?

  8. External Access Risk • Security • Wired always better • Privacy Act information • Wireless less secure • Physical vs. internet based database • Database corruption

  9. User Account Risk • List must be accurate • Names, roles, and permissions • Log on problems • Access problems • Earlier enough in project

  10. Risk Assessment • Mapping out risks can be beneficial for a project. • Helps prepare a team for what might occur. • Scenario analysis is the most commonly used technique for analyzing risks.

  11. Risk Assessment Matrix

  12. Project Team Risk Risk Management Matrix

  13. Team Size • Add personnel if needed • Sub-contract if within budget • Use the workload compared to the timeline as the trigger • Responsibility lies with both, Peak and the City of Meridian

  14. Team Budget • Increase the budget if possible or downsize the scope • Negotiate the budget with the city of Meridian • When it becomes obvious the budget is too small - trigger • Responsibility lies with both, Peak and the City of Meridian

  15. Availability of SW & HW • Send our multiple bids to suppliers of needed SW & HW • Research whether extras can be ordered and held/returned • If there are shortages this is an immediate trigger • The Peak project manager is solely responsible for this

  16. Secure external/internal access • Frequently test to ensure the system is working and secure • Establish alternate ways for remote employees to access • Earliest point system is tested and fails - trigger • Responsibility lies with Peak project manager

  17. Priorities: Authorizations/user log on • Stand-by system while transitioning to new LAN • Work weekends and during non-peak hours to test • Establish secondary server for temporary back-up • Test LAN early and often; if it fails - trigger • Responsibility lies with Peak project manager

  18. Performing Monte Carlo Simulation • A Monte Carlo simulation helps predict risk by using data to predict trends • Performing a risk analysis will assist both PEAK and the City of Meridian in determining if the LAN project can be completed on time and within budget • Having statistical data will allow the project manager to make sound decisions

  19. Benefits of Monte Carlo Simulation • Allows for testing of theories before launching the LAN project • Provides statistical validity to the City by measuring probability that the project will meet its stated goals • Reveals trends that can be modified to decrease risk • Assists the project manager in communicating ways that the project can be restructured for enhanced quality, efficiency and cost

  20. Steps to Perform • Define the problem to be solved • Can project be completed on time and within budget? • Define the drivers/variables of the problem • What might some of the delays and hidden costs be?

  21. Steps Cont. • Define the uncertainty for the variables • Assign best, most likely and worst case estimates to the identified variables • Analyze the model using simulation • Create a model that will compute the assigned formulas to create estimates

  22. End