An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Summary of Hg System Review at CERN Van Graves 13 Sep 2005

  2. Visit Made to CERN on Sept 5 • Chemical safety • J. Gulley, A. Fabich, V. Graves • Radiological safety • M. Silari, T. Otto, P. Carbonez, I. Efthymiopoulos, A. Fabich, V. Graves • Transport issues • Y. Bernard, I. Efthymiopoulos, A. Fabich, V. Graves • Current Hg system design presented, with emphasis on safety and monitoring, transport details V. Graves 13 Sep 2005

  3. Chemical Safety Discussion Summary • Details of passive & active Hg vapor filtration must be developed • Replace respirator cartridges with single filter • Cannot vent Hg vapor into tunnel • Monitor passive filter exit • Might require exhaust pipe to surface from passive filter • Considering keeping secondary vent closed during experiment • Active system required for Hg transfer operations V. Graves 13 Sep 2005

  4. Radiological Safety Discussion Summary • Proposed beam window design discussed • Similar to Hg plenum design • SS pipe welded to sheet metal Ti6AlV4 • Tubing fitting with hose for pressure or vacuum (prefer pressure) • Concept can be sized differently for upstream & downstream windows V. Graves 13 Sep 2005

  5. Radiological Summary II • Prefer Hg vapor monitors close to experiment to minimize secondary volume • Shielding issues must be considered • Suggested that powering down monitors during irradiation might protect electronics Access to TT2/TT2A discussed • Existing concrete blocks in TT2 pit can be removed at any time, with the condition that they be in place prior to TT2A beam • Replace with fence & access control cards • (Full) tubed LN2 exhaust through TT10 to ventilation system provisionally accepted • Exhaust delay must be determined V. Graves 13 Sep 2005

  6. Transport Discussion Summary • Methods for lowering solenoid and baseplate into tunnels discussed • Lower baseplate, then solenoid into pit • Use rollers or turtle to carry assembly into TT2A (sequence to follow) • CERN Transport personnel prefer to use their rollers and jacks • Will require slight modifications to baseplate design • CERN to provide equipment specifications to ORNL • Use three rollers instead of four • Add “tow-hooks” to ends of baseplates V. Graves 13 Sep 2005

  7. Reminder - Experiment Layout TT10 Hyd Pump & Controls in TT2 ISR (Control Room Location) MERIT TT2A TT2 V. Graves 13 Sep 2005

  8. Solenoid & Baseplate Pit Installation • Existing shield blocks incorporate wedge to compensate for floor slope • Must lower components onto level surface – not allowed a two-touch operation • Currently no overhead lifting capability in tunnel CERN “Turtle” V. Graves 13 Sep 2005

  9. Pit Installation Sequence for Turtle Transport of Solenoid Lower baseplate onto turtle, secure Lower solenoid onto baseplate, secure Remove wedge Drive turtle off wedge V. Graves 13 Sep 2005

  10. Turtle Transport of Solenoid Drive turtle onto level floor, negotiate step into TT2A Drive turtle down ramp Drive turtle into approximate position in TT2A Insert I-beams under baseplate Use jacks to lift baseplate/solenoid off turtle Remove turtle Lower baseplate onto floor or rollers V. Graves 13 Sep 2005

  11. Roller Transport of Solenoid • Turtle not used • Baseplate/solenoid moved on rollers • Wedge still required (perhaps larger), same basic sequence as with turtle • Cable attached to fixed location, use come-along to control baseplate/solenoid roll down slope • Move fixed attachment point to pull assy on level surfaces V. Graves 13 Sep 2005