Processing until QM2011. Do we have a plan ?. The absolute must. LHC10h Pass 2 reconstruction 15/02 15/03 (<119> s/ evt × 90M evts / 6K parallel jobs (T0+T1) ⁄ 0.85 eff ) × (1 + 0.3 pass0) = 30 days MC 15/02 15 /05
E N D
Processing until QM2011 Do we have a plan ?
The absolute must • LHC10h • Pass 2 reconstruction 15/02 15/03 (<119> s/evt × 90M evts / 6K parallel jobs (T0+T1) ⁄ 0.85 eff ) × (1 + 0.3 pass0) = 30 days • MC 15/02 15/05 <1496> s/evt × 9M evts / 2K parallel jobs (T2) ⁄ 0.85 eff = 92 days • LHC11? (pp reference run) • Pass 1&2 reconstructions 15/04 5/05 (<6.6> s/evt × 50M evts × 2 ⁄ 0.85 eff ) × (1 + 0.3 pass0) / 20 days = 585 jobs in parallel • MC 15/04 15/07 <103> s/evt × 50M evts × 2 / 2K parallel jobs (T2) ⁄ 0.85 eff = 70 days • 3000 job-slots on average available for analysis (first priority tasks)
Left over • LHC10f-g • Pass 2 reconstruction (not possible in parallel with other period reconstruction path) (<6.6> s/evt × 355M evts/ 3K parallel jobs (T1) ⁄ 0.85 eff× (1 + 0.3 pass0) = 10 days • MC <103> s/evt × 355Mevts /2K parallel jobs (T2) ⁄ 0.85 eff = 249 days • LHC11a • Pass 1 reconstruction at T0 while data taking • LHC10a-g • Pass 3 reconstruction (not possible in parallel with other period reconstruction path) (<6.6> s/evt × 355M evts / 3K parallel jobs (T1) ⁄ 0.85 eff= 42 days
Conclusion We must • Prioritize our objectives for Quark Matter • Which physics contributions ? • Processing strategy to achieve previous • Make a planning and stick to it • Detectors readiness • Offline code and framework readiness • The Computing Model will adapt to (almost) any requirements