Processing until QM2011

Processing until QM2011. Do we have a plan ?. The absolute must. LHC10h Pass 2 reconstruction 15/02  15/03 (<119> s/ evt × 90M evts / 6K parallel jobs (T0+T1) ⁄ 0.85 eff ) × (1 + 0.3 pass0) = 30 days MC 15/02  15 /05

nira
Download Presentation

Processing until QM2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Processing until QM2011 Do we have a plan ?

  2. The absolute must • LHC10h • Pass 2 reconstruction 15/02  15/03 (<119> s/evt × 90M evts / 6K parallel jobs (T0+T1) ⁄ 0.85 eff ) × (1 + 0.3 pass0) = 30 days • MC 15/02  15/05 <1496> s/evt × 9M evts / 2K parallel jobs (T2) ⁄ 0.85 eff = 92 days • LHC11? (pp reference run) • Pass 1&2 reconstructions 15/04  5/05 (<6.6> s/evt × 50M evts × 2 ⁄ 0.85 eff ) × (1 + 0.3 pass0) / 20 days = 585 jobs in parallel • MC 15/04  15/07 <103> s/evt × 50M evts × 2 / 2K parallel jobs (T2) ⁄ 0.85 eff = 70 days • 3000 job-slots on average available for analysis (first priority tasks)

  3. Left over • LHC10f-g • Pass 2 reconstruction (not possible in parallel with other period reconstruction path) (<6.6> s/evt × 355M evts/ 3K parallel jobs (T1) ⁄ 0.85 eff× (1 + 0.3 pass0) = 10 days • MC <103> s/evt × 355Mevts /2K parallel jobs (T2) ⁄ 0.85 eff = 249 days • LHC11a • Pass 1 reconstruction at T0 while data taking • LHC10a-g • Pass 3 reconstruction (not possible in parallel with other period reconstruction path) (<6.6> s/evt × 355M evts / 3K parallel jobs (T1) ⁄ 0.85 eff= 42 days

  4. Conclusion We must • Prioritize our objectives for Quark Matter • Which physics contributions ? • Processing strategy to achieve previous • Make a planning and stick to it • Detectors readiness • Offline code and framework readiness • The Computing Model will adapt to (almost) any requirements